CONTRACT #: 146-20091 l
~~}9~IV.~~-NTH 3Z~33 3 y'~ 3SJ
ORIGINATING DEPARTMENT/DIVISION: OST
CONTACT PERSON: Gary Tennenbaum PHONE #: 920-5355
PROJECT NAME: Crystal Trail Construction
^ BOCC AGENDA ITEM ®STAFF AUTHORIZED SIGNATURE
(Requires BOCC Signature) (per Revised Procurement Code 7/2005)
® Over $50,000 (Requires County Manager's Signature)
/ CHECK PROCUREMENT TYPE:
^None ^Informal ®Fonmal ^Sole Source ^Emergency ^State Bid ^
^Compliance with House Bills 06-1343 and 07-1073 -Immigration Form (Under $10,000, Letters of Engagement, e~
w.
DOLLAR AMOUNT: $23,409.00 BUDGET LINE ITEM/LEDGER NUMBER: 118.58.02506.86120
/ CHECK CONTRACT TYPE:
^ Services/Maintenance
^License/U se
^Lease
^Construction
^Goods, Equipment, Supplies
^Other (e.g. revenue)
^Employment (for county employees)
^Intergovernmental Agreement (Requires BOCC Action)
^Non-Profit
^Quasi-Public
^Grant Agreements (Requires BOCC Action)
®Change Order/Contract Amendment
CONTRACTOR: Heyl Construction, Inc COMPLETE LEGAL OF NAME OF BUSINESS (if different from
contractor)
Contract Execution Date: Contract End Date:
Automatic Renewal: ^Yes ®No Term of Contract:
~~
g All Contracts should be proofed for the following:
/ ®No Pages Missing ~~
/ ^If a Page is Left Intentionally Blank Note on Page (~
/ ^Page numbered consecutively ` `~
/ ®All Signatures Affixed
/ ^All Dates Filled In
/ ^All Other Blanks Filled In
/ ^All Exhibits Attached
/ ^HB 06-1343 and 07-1073 (Immigration Legislation) Included in RFP and/or Contract
/ ^All Legal Descriptions Attached (if applicable)
/ ^Notice of Award/Notice to Proceed Attached (if applicable)
/ ^Warranty (if applicable)
/ ®Special Instructions for Finance Department:
/ ^Sent to Clerk and Recorder for Scanning/Archiving
/ ®Authorized Staff Person's Name: Gary Tennenbaum
BY CHECKING ABOVE AND ENTERING NAME, THE AUTHORIZED STAFF PERSON INDICATES THAT
THE ATTACHED DOCUMENT HAS BEEN PROOFED AND READY FOR SCANNING.
NOTE: CLERK'S OFFICE WILL KEEP ORIGINAL DOCUMENTS IN COMPLIANCE WITH COLORADO STATE
ARC'HTVFR RRTATNAC;F. R( FTRT)TTT.F.
Project Coding_118.58.02506.86120
~ I 'a
Change Order Number: 32,33,34,35
OWNER:
CONTRACTOR:
Pitkin County
Aspen CO 81611
Heyl Construction, Inc.
Description of Change: See attached Change Orders
Reason for Change: See attached Change Orders
Rev 12/10/09 js
Contract # 146-2009
Original Contract Price $ 2,475,827.00
Total of Previous Change Orders $ 403,543.34
Net Increase/Decrease in Contract Price (these change orders) $ 23,409.20
Total Adjusted Contract Price (including these Change Orders) $ 2,879,369.35
In all other respects the Agreement is in full force and effect and remains unchanged by this
Amendment.
Si atures attached
Contractor
~ ~.
Authorized Co Representative
Date ~ ~ ~ ~~
Date
1
CHANGE ORDER/CONTRACT AMENDMENT
Change Orders 32-35 Descriptions
32 -This is for extra concrete to avoid erosion between 2 culverts.
33 -Before the Crystal Trail went to bid we were working with the Tom Bailey to determine what to do
with an old cattle crossing culvert that is under Hwy 133. There is also the Bowles and Holland Ditch
culvert that travels under the highway at this location that dumps water right at the opening of the
cattle crossing. At the time Bailey could not decide what the use would be since the former owners of
the Perry ranch did not use the cattle culvert for many decades. We did not include any costs in the
request for proposals since we had no idea what Bailey would want. Now that the trail is almost
complete it was determined that he will use the cattle culvert for actually transferring cattle under the
highway and to avoid a huge mess we agreed to extend the Bowles and Holland ditch an extra 80 feet so
the cattle can cross over the ditch without having to walk through it. This change order covers the extra
80 feet of irrigation pipe.
34 -Our original plans had the trail approaching Thomas Road at a higher grade. When Bill Fales
received approval for a homesite near Thomas Road it was determined that the higher crossing would
prevent him from creating a driveway to this homesite. This development approval was received after
the plans were approved by CDOT and prepared to go to bid. This change order covers the cost of
lowering the trail grade to accommodate a future driveway.
35 - As the trail is being excavated we are finding many more wet areas than originally planned. This
change order covers the cost of muck excavation and placement of fabric to control future water to pass
under the trail without damaging the pavement.
~v
~"i Yl.
coni~rreuc~rioiu
6560 CR 335
New Castle, CO 81647
To: PltlCln COUtlty
Date: 4/30/2010
Owner Change Order No.: 032
Project: Crystal Valley Trail
Description of Changes: Concrete Invert @ Wall #4
Change Order
Heyl LLC Change Order No.: 032
Subcontractor's Change Order No.: N/A
Original Contract Amount: $ 2,475,827.00
Previous Change Orders: S 403,542.35
This Change Order Amount: $ 601.35
Revised Contract Amount: $ 2,879,970.70
Item Approx. Unit Total
No. Description Quantity Units Price Amount
2-935 Pour Concrete Invert 1 LS $ 601.35 $ 601.35
$ -
$ -
$ -
TOTAL: $ 601.35
The following conditions and terms will cooly:
1) It is understood that the quantities set forth herein will be adjusted and the unit price will be applied
to the adjusted quantity, including both overruns and underruns.
2) This change represents complete accord to all adjustments in contract to perform work identified
by the aforementioned change directive.
Please sign this change order in the space provided below and return all copies to this office
within five (5) days of receipt.
Accepted by: Sincerely,
Heyl LLC
I ° '` k.~
By: BY:
Title: s Title: Project Manager
970-984-3404 Office
970-984-6403
In accordance with the terms of our Contract Agreement covering the
above named project, the following changes are hereby authorized. All
other terms and conditions of the Contract Agreement, as they may
heretofore have been modified, shall be and do remain the same.
~j
EYL
CONSTRUCTION
CHANGE ORDER ESTIMATE SUMMARY SHEET
PROJECT: Cystal Valley Trail
PROJECT NO.: N/A
HEYL PROJECT NO.: 09-CC-175
EYL CHANGE ORDER NO.: 32
DESCRIPTION: Concrete Invert @ Wall #4
DATE: Apri130, 2010
COST ESTIMATE SUMMARY
Labor
Administration Costs, Profit @ 45 %:
Insurance, Tax @ 25 %:
Subtotal Labor:
Materials•
Sales Tax @ 0.00
Administration, Profit @ 15%:
Subtotal Material:
Owned Equipment:
Administration, Profit @ 15%:
Subtotal Owned Equipment:
Rental Equipment:
Administration, Profit @ 15%:
Subtotal Rental Equipment:
Administration, Profit @ 15%:
Subtotal Subcontractors:
Subtotal:
Bond @ 1 %:
TOTAL AMOUNT:
TOTAL UNIT PRICE:
$ 296.00
$ -
$ 44.40
$ 340.40
$ -
$ -
$ -
$ -
$ -
$ -
$ -
$ -
Subtotal: $ -
$ -
$ -
$ 595.40
$ 5.95
$ 601.35
QUANTITY = 1 TM $ 601.35
"~
~~
EYL
CONSTRUCTION
PROJECT: Cystal Valley Trail
PROJECT NO.: N/A
HEYL PROJECT NO.: 09-CC-175
HEYL CHANGE ORDER NO.: 32
DESCRIPTION: Concrete Invert @ Wall #4
DATE: April 30, 2010
DETAILED COST ESTIMATE BREAKDOWN
TOTAL
DESCRIPTION QUANTITY UNITS RATE/[JNIT AMOUNT
T ~~~
Supervisor 2.00 HR $ 35.00 $ 70.00
Laborer 4.00 HR $ 20.00 $ 80.00
$ - $ -
$ -
$ -
$ -
$ -
~uuw~ai. a iw.vv
nrt.,~,...:.,i~.
Concrete Class B/D 1.00 CY $ 161.00 $ 161.00
Short Load Charge 1.00 EA $ 95.00 $ 95.00
4" Perf. Drain Pipe 40.00 LF $ 1.00 $ 40.00
$ - $ -
$ -
~uoroiai: a ~7o.vv
$ - $ -
$ - $ -
$ - $ -
$ -
$ -
$ -
~uowiai: a -
Rental Eauiument:
$ -
$ -
$ -
$ -
$ -
$ -
Subtotal: $ -
H~r~
tONiTRUCT~ON
6560 CR 335
New Castle, CO 81647
To: Pitkin County
Date: 5/26/2010
Owner Change Order No.: 033
Heyl LLC Change Order No.: 033
Change Order
Subcontractors Change Order No.: N/A
Project: Crystal Valley Trail
Original Contract Amount: $ 2,475,827.00
Previous Change Orders: $ 404,143.70
This Change Order Amount: $ 11,800.00
Revised Contract Amount: $ 2,891,770.70
Description of Changes: Concrete Invert @ Wall #4
Item Approx. Unit Total
No. Description Quantity Units Price Amount
2-934 38" X 57" Culvert Extension 1 LS $ 11,800.00 $ 11,800.00
$ -
$ -
$ -
TOTAL: $ 11,800.00
The following conditions and terms will aoDly:
1) It is understood that the quantities set forth herein will be adjusted and the unit price will be applied
to the adjusted quantity, including both overruns and under-uns.
2) This change represents complete accord to all adjustments in contract to perform work identified
by the aforementioned change directive.
Please sign this change order in the space provided below and return all copies to this office
within five (5) days of receipt.
Accepted by: Sincerely,
Heyl LLC
By: By:
Title: Title: Project Manager
970-984-3404 Office
970-984-6403
In accordance with the terms of our Contract Agreement covering the
above named project, the following changes are hereby authorized. All
other terms and conditions of the Contract Agreement, as they may
heretofore have been modified, shall be and do remain the same.
I"jEYI..
CONiTRUCT~dN
6560 CR 335
New Castle, CO 81647
To: Pitkin County
Change Order
Date: 5/26/2010
Owner Change Order No.: 34
Heyl LLC Change Order No.: 34
Subcontractors Change Order No.: N/A
Project: Crystal Valley Trail
Original Contract Amount: $ 2,475,827.00
Previous Change Orders: $ 415,943.70
This Change Order Amount: $ 2,029.09
Revised Contract Amount: $ 2,893,799.79
Description of Changes:
Item Approx. Unit Total
No. Description Quantity Units Price Amount
2-936 Lower Bill Fails' Entrance at Thomas Rd. 1 T8M $ 2,029.09 $ 2,029.09
$ -
$ -
$ -
TOTAL: $ 2,029.09
The following conditions and terms will ap~ly~
1) It is understood that the quantities set forth herein will be adjusted and the unit price will be applied
to the adjusted quantity, including both overruns and underruns.
2) This change represents complete accord to all adjustments in contract to perform work identified
by the aforementioned change directive.
Please sign this change order in the space provided below and return all copies to this office
within five (5) days of receipt.
Accepted by: Sincerely,
Heyl LLC
~ ` ~~
By: ~' ~ f'~~ By:
Title: j 7 Title: roject Manager
970-984-3404 Office
970-984-6403
In accordance with the terms of our Contract Agreement covering the
above named project, the following changes are hereby authorized. All
other terms and conditions of the Contract Agreement, as they may
heretofore have been modified, shall be and do remain the same.
I""iEYL
CONSTRUCTION
6560 CR 335
New Castle, CO 81647
To: Pitkin County
Change Order
Date: 5/26/2010
Owner Change Order No.: 35
Heyl LLC Change Order No.: 35
Subcontractor's Change Order No.: N/A
Project: Crystal Valley Trail
Original Contract Amount: S 2,475,827.00
Previous Change Orders: $ 417,972.79
This Change Order Amount: $ 8,978.76
Revised Contract Amount: $ 2,902,778.55
Description of Changes: See Attached Summary
Item Approx. Unit Total
No. Description Quantity Units Price Amount
2-937 Muck Ex. 2' - 131+00 to 133+00 334.63 CY $ 15.00 $ 5,019.45
2-937 Place Tensar BX 1200 1067.2 SY $ 3.71 $ 3,959.31
$ -
$ -
TOTAL: $ 8,978.76
The following conditions and terms will apply:
1) It is understood that the quantities set forth herein will be adjusted and the unit price will be applied
to the adjusted quantity, including both overruns and underruns.
2) This change represents complete accord to all adjustments in contract to pertorm work identified
by the aforementioned change directive.
Please sign this change order in the space provided below and return all copies to this office
within five (5) days of receipt.
Accepted by: Sincerely,
Hevl LLC
( ~
By: c,J~:/
Title: 1 f ~Z
~ `
By:
Title: P j ct Manager
970-984-3404 Office
970-984-6403
In accordance with the terms of our Contract Agreement covering the
above named project, the following changes are hereby authorized. All
other terms and conditions of the Contract Agreement, as they may
heretofore have been modified, shall be and do remain the same.