HomeMy WebLinkAboutbocc.res.162.2010 A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF
PITKIN COUNTY, COLORADO APPROVING AN
WATER COURT APPLICATION TO APPROPRIATE A
RECREATIONAL IN- CHANNEL DIVERSION WATER RIGHT
RESOLUTION NO. f -2010
1. The Piktin County Board of County Commissioners ("BOCC") has been
interested for the past three years in developing and improving a river park on the
Roaring Fork River above the confluence of the Fryingpan River.
2. The BOCC engaged consultants to evaluate and design a water park near the
Town of Basalt on the Roaring Fork River.
3. The BOCC has also asked its staff and consultants to investigate the appropriation
of a Recreational In- Channel Diversion water right for the water park.
4. The BOCC's staff and consultants recommend that the Board of County
Commissioners file an application for a Recreational In- Channel Diversion water right
with a peak flow not to exceed 2,000 cfs.
5. The BOCC has discussed these recommendations and has determined that it is in
the best interest of the citizens of Pitkin County to file an application to adjudicate a
Recreational In- Channel Diversion water right.
NOW, THEREFORE, BE IT RESOLVED that the BOCC hereby authorizes and
directs its staff, consultants, and attorneys to file a water court application to adjudicate a
Recreational In- Channel Diversion water right not to exceed 2,000 cfs, with an
appropriation date of July 13, 2007.
BE IT FURTHER RESOLVED that that the Pitkin BOCC directs its staff and
consultants to post appropriate notices as necessary to give further notice of its intent to
appropriate this water right.
ATTEST: BOARD OF COUNTY COMMISSIONERS
OF PITKIN COUNTY, COLORADO
'ff %t. // L By t-
Je. 4 Jones / George Ne an, C air
ty Clerk & Recsrder
Date: J din A)
APPROVED AS TO FORM: MANAGER ' ROVAL:
c- -- )e
John o • s ttorney Phyli .ttice, ActingCounty Manager
1
, i w y .. a .... .�
EFILED Document
DISTRICT COURT, WATER DIVISION NO. 5, g Date: Dec 30 2010 "° c' "" tit .11)
> Filing Date: Dec 3U 2UtU 3:59PM MS "/'
COLORADO Filing ID: 35131615
Review Clerk: Kathy_ Nall
109 - 8 Street, Suite 104
Glenwood Springs, CO 81601 -3361
(970) 947 -3861
CONCERNING THE APPLICATION FOR WATER • COURT USE ONLY AL
RIGHTS OF BOARD OF COUNTY
COMMISSIONERS OF PITKIN COUNTY,
COLORADO Case Number: 10CW 305
IN PITKIN COUNTY
Timothy J. Beaton, #10403
Aaron S. Ladd, #41165
Moses, Wittemyer, Harrison and Woodruff, P.C.
P. O. Box 1440
Boulder, Colorado 80306 -1440
Telephone: (303) 443 -8782
Facsimile: (303) 443 -8796
tbeaton(;mwhw.com; aladd(a;lnwhw.com
APPLICATION FOR SURFACE WATER RIGHT APPROPRIATIONS FOR
RECREATIONAL IN- CHANNEL DIVERSION
1. Name, address and telephone number of applicants:
Board of County Commissioners of Pitkin County
c/o John M. Ely, Pitkin County Attorney
530 East Main Street, Third Floor
Aspen, Colorado 81611
(970) 920-5190
2. Introduction: This application seeks two conditional recreational in- channel diversion
( "RICD ") water right appropriations for the Pitkin County River Park Project, which
consists of two in- channel diversion and control structures that divert, capture, possess,
and/or control the flow of the Roaring Fork River in its natural course to create
reasonable recreation experiences in and on the water for all non - motorized boating and
related recreational uses as described more fully below.
Board of County Commissioners of
Pitkin County, Colorado
Case No. 10CW30.5
Page 2
3. Name of structures: The Pitkin County River Park Project is comprised of two control
structure units: (1) the Pitkin County River Park Project Upper Control Structures
( "Upper Structure Unit ") and (2) the Pitkin County River Park Project Lower Control
Structures ( "Lower Structure Unit').
4. Description of conditional water right appropriations:
A. Location of structures: The Pitkin County River Park Project will be located on
the Roaring Fork River downstream of the Highway 82 Upper Bypass Bridge,
upstream of the confluence of the Fryingpan and Roaring Fork Rivers, within the
channel of the Roaring Fork River in Sections 17 and 18, Township 8 South,
Range 86 West of the 6` P.M., Pitkin County, Colorado. The Pitkin County
River Park Project will consist of two structure units within the Roaring Fork
River. This application seeks two RICD water right appropriations, one for each
of the two structure units, each of which will, by design, control, concentrate and
direct the stream flows between the upper and lower extent of that structure units,
independent of the other structure units, for the beneficial uses described below.
A map depicting the upstream and downstream extent of the Pitkin County River
Park Project, within which both structure units will be constructed, is attached as
Exhibit A. Each of the two structure units will be constructed in the channel of
the Roaring Fork River between the following two points:
i. The Pitkin County River Park Project Upstream Extent will be located in
the SW'% of the NW% of Section 17, Township 8 South, Range 86 West,
6 P.M., Pitkin County, Colorado, at a point 320 feet from the west
section line and 1480 feet from the north section line of said. Section 17.
i. The Pitkin County River Park Project Downstream Extent will be located
in the NE'% of the NE% of Section 18, Township 8 South, Range 86 West,
6 P.M., Pitkin County, Colorado, at a point 265 feet from the east section
line and 560 feet from the north section line of said Section 18.
The precise location of the two structure units and related water right
appropriations, upon construction, may be located within this stretch of the
Roaring Fork River. Provided that the structure unit locations remain within the
stream reach described above, the actual locations will be described in the decree
entered herein, identified by upper and lower control structures for each of the
two structure units, or, if such decree is entered before construction of any or all
of the structures, in subsequent applications for diligence or to make absolute the
water rights claimed herein.
Board of County Commissioners of
Pitkin County, Colorado
Case No. 10CW 305
Page 3
B. Source: Roaring Fork River, tributary to the Colorado River.
C. Appropriation:
i. Date of appropriation: July 13, 2007.
ii. How appropriation was initiated: Engineering, field work, planning,
considerations and decisions of the Board of County Commissioners, and
posting notice of the appropriations.
iii. Date water first applied to beneficial use: Not applicable.
D. Amounts claimed: Applicant claims two RICD water right appropriations for the
following time periods and amounts, CONDITIONAL, as follows:
i. Upstream Structure Units: Between April 1 and Labor Day of each
year, this RICD water right appropriation will not exceed 1,500 cfs.
ii. Downstream Structure Units: Between April 1 and Labor Day of each
year, this RICD water right appropriation will not exceed 2,000 cfs.
iii. Pitkin County hereby reserves the right to refine time periods and flow
rates associated with either or both of the RICD water right appropriations
claimed in this application. The RICD water right appropriations will not
extend beyond the time periods listed above nor exceed the flow rates
listed above for each RICD water right appropriations. Because any
refinement in time periods and flow rates would constitute a reduction in
the claims, the above constitutes notice to all interested parties.
iv. The above amounts are claimed as conditional. However, Pitkin County
reserves the right to seek these amounts as absolute to the extent that the
Pitkin County River Park Project or individual Structure units are
constructed and flows are placed to beneficial use prior to the date of entry
of a decree in this case.
E. Beneficial use: Recreational uses including all beneficial uses associated with
RICD water rights as permitted under Colorado Law as may be later changed or
amended, including but not limited to non - motorized boating including kayaking,
canoeing, rafting, tubing, floating, and paddling.
Board of County Commissioners of
Pitkin County, Colorado
Case No. 10CW 305
Page 4
5. Name and address of owner of land upon which anv new diversion structure or
modification to any existing diversion structure is or will be constructed:
Town of Basalt
Tom Smith, County Attorney
600 E. Hopkins
Aspen, CO 81611
970 -925 -2600
Torn Kinney, Town of Basalt Water Rights Counsel
201 Main Street #301
Carbondale, CO 81623-2216
970 -963 -3900
Fredrick S. Arbaney Trust
Josephine Arbaney, Trustee
252 Cottonwood Drive
Basalt, CO 81621
Applicant
c/o John M. Ely, Pitkin County Attorney
530 East Main Street, Third Floor
Aspen, Colorado 81611
(970) 920-5190
WHEREFORE, Applicants respectfully request this Court enter a decree granting
the two conditional recreational in- channel diversion water right appropriations claimed in this
application for the Pitkin County River Park and granting such other relief as may be
appropriate.
Board of County Commissioners of
Pitkin County, Colorado
Case No. 10CW 305:
Page 5
Respectfully submitted this 30th day of December, 2010.
MOSES, WITTEMYER, HARRISON AND
WOODRUFF, P.C.
1
J •
Timothy J. B 0403
Aaron S. Ladd, #41165
A"T"TORNEYS FOR APPLICANT, BOARD
OF COUNTY COMMISSIONERS OF
PITICIN COUNTY, COLORADO
E -FILED PURSUANT TO C.R. C.P. 121 Duly signed original on file at the law offices of
Moses, Wittemyer, Harrison and Woodruff P.C.
DEC -30 -2010 15:23 GLENWOOD INSURANCE 9709450788 P.002
Board of County Commissioners of Pitkin County, Colorado
Case No. 10CW 305
Page 6
VERIFICATION
STATE OF COLORADO )
Ga ---(• , ) ss.
COUNTY OF-PITIffN )
James F. Pearce, being first duly sworn upon oath, deposes and says that he is the
water rights consultant, for applicant herein, that he has read the foregoing Application for Surface
Water Right Appropriations for Recreational In- Channel Diversion, knows the contents thereof, and
that the same is true to the best of his knowledge and belief.
Jail, F. Pearce
SUBSCRIBED AND SWORN to before me this 30 day of December, 2010.
Witness my hand and official seal.
My Commission Expires
My conunission expires: 05/16/2014 y
\ \VRIN . . • ... C r /
: 9 p . o Notary Public
i .4:Z0
I r � (< "
g4 IC
ygO..013`Dp_
43 53000r N, 43 ggouum N. 6000om N
W '►
ijq 11 L"jj• 1l r ', I rF` �` .� a �/
cn < r �€
'U m '„1f y � Y a
4 k - ti
b
C 5 m 7 / � / ti a / rn it
o . 1 I 666 = ,a
l lli f J t i�i / . /S {/} � : SID
i y�, e ar �yi T k ' ff i , 1 ': .
„ ,22..??. ' j � i �.: ` I it V e�v , %, . 1 i t ai
Z / ) �ti2 j / p VA
O ( tit J / 7 I \ I? „ 9 �" , • V $ f ✓41,1 J./1111
o O i�, ! 9 P� q 'U' . :i Y \ � t 3 � , ', i
ZI
a r C f
� ' 1LT.*" �C � r 1 � Oi
it $ I',i j r
/ { e �9p r L i 1
lc; v �, "'} 1 •r 7 -' v im ' 4 � r . 'I III v
Ns
I—
l • ., r ,s J I r
43 55000m N. 43 59000m N
436000om N
Granicus Deployment Tracker - Pitkin Page 1 of 3
granicus.
Pitkin Deployment - OpenPlatform / GovermentTransparency /MobileEncoder
Live Project Tracker
About I Knowledge Base I Support Resources I Feedback!
Kickoff Call Agenda
Granicus Project Manager: Alyarn Marronuin Overall Project Progress: 19.38%
Client Project Lead: Nancy fie
Project Start Date: 01/03/2011
Project Target Completion Date: 02/08/2011
Project Days Remaining: 21.0 ® Current Milestone: Hardware Ordered
Project Status: On Schedule S..
Project Milestones
Current Milestone Name Milestone Owner Help Target Date Completed?
Milestone
Technical Review Call Scheduled Granicus & Client More Info 01/03/2011 ✓
Technical Review CMLCOmpleted Granicus More Info 01/03/2011 ✓
K'eko C Ia Scheme. Granicus & Client More 01/06/2011 J
KlckoffCall Completed Granicus More info 01/06/2011 1
Hardware Ordered Granicus More info 01/03/2011 X
bardwareinstelfation Client Mor_nInfo 01/28/2011 X
Software Installation Granicus More Info 01/31/2011 X
Project Validation Granicus More Info 02/01/2011
Begin Training Dote Client More Info 02/07/2011 X
Training Completed Date Client More info 03/03/2011 X
Go live Completed Client More Info 02/08/2011 X
Transitionto CMStomerCate Granicus More info X
Training Dates
Online Training Session Training Date Onsite Training Session Training Date
Needs Analysis Call Onsite Session 1 03/03/2011
New Client Tutorial 02/02/2011 Onsite Session 2
Online Session 1 02/07/2011 Onsite Session 3
Online Session 2 02/16/2011 Onslte Session 4
Online Session 3 Onsite Session 5
Online Session 4 Onsite Session 6
Online Session 5
Online Session 6
http: / /granicus.force.com !deployments ?id= a11300O0000xpR6 1/18/2011
•
Granicus Deployment Tracker - Pitkin Page 2 of 3
Milestone Review
Back to 1'op
Hardware Installation Milestone Review Target Date: 01/28/2011
Milestone Completion: 0.0% Days Remaining: 10
More Info on this Milestone
Case Subject Status Due Date
Provide Clients with Install Information New 01/28/2011
Back to Top
Software Installation Milestone Review Target Date: 01/31/2011
Milestone Completion: 12.5% Days Remaining: 13
More Info on this Milestone
Case Subject Status Due Date
New CUSTOMIZED Client Integration - Pitkin Awaiting Client 01/17/2011
Validation
Please create and validate agenda and parser - Pitkin New 02/02/2011
Configure and Validate MediaManager Installation New 01/31/2011
Create GADS Build for Meeting Server / MediaVault / StreamRepllcator New 01/31/2011
Install and Validate Open Platform Software New 01/31/2011
Install and Validate LiveManager Software Standard New 01/31/2011
Create Parser and AgendaTemplate(s) - Pitkin New 01/31/2011
Back to lot
Project Validation Milestone Review Target Date: 02/01/2011
Milestone Completion: 0.0% Days Remaining: 14
More Info on this Milestone
Case Subject Status Due Date
Project Validation Checklist New 02/01/2011
Back to Top
Begin Training Date Milestone Review Target Date: 02/07/2011
Milestone Completion: 0.0% Days Remaining: 20
More Info on this Milestone
Case Subject Status Due Date
Onsite Training - MoblleEncoder New 03/03/2011
Back to Top
Training Completed Date Milestone Review Target Date: 03/03/2011
http: / /granicus. force. com /deployments ?id= a1130000000xpR6 1/18/2011
Granicus Deployment Tracker - Pitkin Page 3 of 3
Back to Tap
Go Live Completed Milestone Review Target Date: 02 /08/2011
Milestone Completion: D.0% Days Remaining: 21
More Info on this Milestone
Case Subject Status Due Date
Verify Public Access to View Pages New 02/08/2011
Enable Podcasts and Add Client to Crones Library New 01/28/2011
Project Team Members and Contact Information
Granicus Contacts
Role Name Phone Number
Granicus Project Manager Alvaro (415) 357 -3618 x1144
Deployment Technician Alvaro Marroquin (415) 357- 3618 x1144
Web Designer Brian Brown (415) 357 -3618 x1565
Training Specialist Rebecca. Cleary (415) 357 -3618 x1137
Sales Executive Ed Burrell x1724
Account Manager
Support Engineer x
Pitkin Contacts
Role Name Phone Number
Client Project Lead Nanty Pearce (970) 429 -1758
Client Technical Lead Ann Mare Prince (970) 920 -5180
Client IT Technician 1 John Sobleralski (970) 429 -1756
Client IT Technician 2
Client AV Lead
Client Webmaster
Client Primary User 1
Client Primary User 2
Client Primary User 3
About the Deployment Tracker System
http: / /granicus. force. com /deployments ?id= a1130000000xpR6 1/18/2011