AGENDA ITEM SUMMARY
REGULAR MEETING DATE:
November 14, 2012
AGENDA ITEM TITLE:
Resolution Approving a Revision to the 2012 Budget for the
½-Cent Transit Sales and Use Tax
STAFF RESPONSIBLE:
Brian Pettet and Tom Oken
ISSUE STATEMENT:
Attached for your review and approval is a resolution which, if
approved, would authorizethe following supplemental 2012 ½-cent transit sales and use tax
budget:
Increase AABC pedestriancrossing design & engineering by $125,000
Each of themembers of the Elected Officials Transportation Committee is required to passits
own resolution to approve of budget requests.
BACKGROUND:
The Aspen City Council, Pitkin County Commissioners and Snowmass
Village Town Council meet together as the Elected Officials Transportation Committee
(“EOTC”). The proposed$125,000 increase in the 2012budget for AABC pedestrian crossing
design & engineering was approved by the EOTC at its October 18, 2012meetingon the
condition that an itemization of the tasks and time comprising the increase be provided.
Attached is a memo from the Parsons engineering team itemizing the original scope of the
project and the additional tasks required to complete the project.
LINK TO STRATEGIC PLAN:
Flourishing Natural and Built Environment: Ease of mobility
via safe and efficient transportation systems.
KEY DISCUSSION ITEMS:
BUDGETARY IMPACT:
The resolution approvesa $125,000 addition to the 2012budget for
the ½-cent transit sales and use tax.
RECOMMENDED BOCC ACTION:
Approve as aninformal (one reading) resolution as part
of the consent agenda.
ATTACHMENTS:
Resolution Approving a Revision to the 2012Budget for the ½-Cent Transit Sales and Use Tax
Fund
Parsons Scope vs. Budget Summary
A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF PITKIN
COUNTY, COLORADO, APPROVING A REVISION TO THE2012BUDGET FOR THE
½-CENT TRANSIT SALES AND USE TAXFUND
RESOLUTION NO. _______-2012
RECITALS
1.The Aspen City Council, the Pitkin County Board of County Commissioners and the Town
Council of Snowmass Village (the "Parties") have previously identified general elements of
their Comprehensive Valley Transportation Plan (the "Plan") which are eligible for funding
from the Pitkin County one-half cent transit sales and use tax.
2.By intergovernmental agreement dated September 14, 1993, the Parties agreed:
a.to conduct regular public meetings to continue to refine and agree upon proposed
projects and transportation elements consistent with or complimentary to the Plan; and
b.that all expenditures and projects to be funded from the County-wide one-half cent
transit sales and use tax shall be agreed upon by the Parties and evidenced by a
resolution adopted by thegoverning body of each party.
3.At a public meeting held on October 18, 2012, the Parties considered the following
supplemental budget request for2012:Increase the AABC pedestrian crossing design &
engineering by $125,000.
4.By adoption of this resolutionthe Board of County Commissioners wishes to approve the
supplemental budget request.
NOW THEREFORE BE IT RESOLVED
by the Board of County Commissioners of
Pitkin County, Colorado,that the followingincreaseto the 2012budget for the one-half cent transit
sales and use tax is hereby approved as summarized below:
AABC pedestrian crossing design & engineering $125,000
INTRODUCED, READ AND ADOPTED ON NOVEMBER 14, 2012.
ATTEST: BOARD OF COUNTY COMMISSIONERS
OF PITKIN COUNTY, COLORADO
_________________________ By: _________________________________
Jeanette Jones Michael M. Owsley, Chairman
Deputy County Clerk
Date: ________________
MANAGER APPROVAL:
______________________
Jon Peacock, County Manager
Parsons Scope vs. Budget Summary
th
October 29, 2012
th
As requested of Parsons by the E.O.T.C. during the meeting on October 18, 2012, below is an itemized
list of scope elements necessary to provide a thorough and complete Publ
Alternatives Analysis, required Agency Coordination, Preliminary Des
Post Advertisement Support for the Pitkin County Pedestrian Cros
The Project tasks below are broken out as original scope elements and unforeseen or additional out of
scope work. Several of these categories are comprised of both i-scope and out-of-scope elements.
The out-of-scope work has often been part of in-scope services but required a higher amount of effort
than could have been anticipated at the time of contract execution with Pitkin County.
Original Scope Required Tasks: Required Budget: Hours:
Planning and Alternatives Analysis Phase:
Coordination and Interface with CDOT, Airport, RFTA and Citizens $90,000 = 682 Hrs
As-needed meetings with each Agency and Public
Groups to gain input on proper site and crossing technique
Evaluation of options with both public groups and agency of
recommended design and locations with below grade and above grade option.
Coordination and Interface with CDOT updating them
on design decisions and requesting comments
Update Airport, RFTA and Citizens on preferred selection
Preliminary Design:
Coordination and Interface with CDOT, Airport, RFTA and Citizens: $70,000 = 594 Hrs
Meetings with Agencies to review plan
Design preferred option to present to both public
groups and agencies to evaluate design issues
Update Airport, RFTA and Citizens on preferred selection
Final Design:
Extensive coordination with CDOT` $90,000 = 800 Hrs
Coordination Meeting with multiple Agencies
Final Design of Preferred Alternative
Construction Plan and Specification Package
Developed and sent for Advertisement
Sub-Total for Original Scope Budget: $250,000
Unforeseen / Additional Scope Required Tasks: Required Budget: Hours:
Planning and Alternatives Analysis Phase:
Coordination and Interface with CDOT, Airport, RFTA and Citizens $51,500 = 356 Hrs
Individual meetings with multiple Agencies and Public
ensured proper siting
Thorough Evaluation Process with both public groups
and agency / consultant teams to design and evaluate 2
locations with a below grade and above grade option.
Continued high level of coordination and Interface with
CDOT to identify plan format, funding, schedule and
environmental process requirements
Preliminary layout and evaluation efforts of 4 alternatives,
2 above and 2 below grade crossings
Responses to E.O.T.C. request for additional evaluation: $ 4,500 = 61 Hrs
Structural evaluation of McBride Proposal
Quantity / Cost Estimate of McBride Proposal
2 additional renderings of alternative sites
3 additional rendered cross-sections developed for site
Preliminary Design:
Coordination and Interface with CDOT, Airport, RFTA and Citizens $25,000 = 263 Hrs
Additional Potholing needs, special use permit preparation
and Traffic Phasing required for tunnel alternative instead
of a simpler bridge option.
RFTA Airport and CDOT Coordination Efforts:
Coordination and Interface with CDOT, Airport, RFTA and Citizens $10,000 = 86 Hrs
Additional Meetings with all Agencies coordinating multiple
phasing and design options to create an integrated project
Thorough Evaluation Process with agency / consultant teams
to evaluate crossing design, schedule, scope and cost sharing.
Additional Meetings with all Agencies including sharing
and receiving files from RFTA Consultant
Provide multi-project schedule and interfaces to ensure
constructability of 3 projects
CDOT Plan Checking and Design Process: $30,000 = 260 Hrs
Alternative Structures Selection Report
Alternative Wall Selection Report
Additional coordination with CDOT and specialty groups
Multiple discussions on plan process as CDOT or local agency
CDOT requested Parsons provide recommendation for
most appropriate drainage design requirements.
Post Design Advertisement Support: $ 4,000 = 34 Hrs
Additional hours estimated to answer contractor
questions regarding design, quantities or specifications
Sub-Total for Additional Budget Required: $125,000
Project Total: $375,000
This list of required steps, including unanticipated planning, design and coo
describe legitimate reasons as to why the tunnel project is exceeding the budgetary goal of $250,000.
Parsons, under the direction of the E.O.T.C. and County Staff, has strived to execute the project as
efficiently as possible.
Thank you for your time and your trust and if you have any furth
answer.
Parsons Team