HomeMy WebLinkAboutpitkin.eh.264335105003 (2013)MEH/NR ONSITE WASTEWATER TREATMENT SYSTEM (OWTS) CONSTRUCTION PERMIT 76 Service Center Rd- Aspen, CO - 81611 Phone: 970.920.5070 Fax: 970.920.5374 Permit #: 0026.2013.powt Parcel ID #: 2643-351-05-003 Permit Issued: ®NEW []REPAIR ❑REMODEL/ADDITION ❑TANK ONLY ❑FIELD ONLY []AMENDMENT Owner(s): Larry Property Address: Legal Description: and David Roth 1153 & 1155 South Starwood Dr Size of Lot: 4.371 Size of Building: 6862 Acres Detached Accessory Unit: ®YES ❑NO Sq. Ft. Size of Accessory Unit: 1346 The system is designed for: 4 bedrooms in the main structure and 1 bedroom in the ADU Designed By: All Sery ce Septic Phone #: 970-618-5033 Fax #: 30:3-216-2796 Project #: Mailing Address: Email Address: Perc Rate: 30 MPI Profile Hole Depth Minimum Tank Capacity: 1425 gallons Sq. Ft. C1021 Dated: -02/11/2013�^j �Zd' 13 Po Box 2844 Glenwood Springs Tpetzl C@comcast.net 8' Depth to Groundwater or Bedrock Greater than 8 ft Minimum Absorption Area: 1093 ftz (50% reduction Permit Conditions: This OWTS Construction Permit is approved on the condition of compliance with the engineer design as submitted with the application and the specifications cited above. Changes must be approved by this Department and the engineer prior to construction. The OWTS is designed for a 4 -bedroom main residence and a 1 bedroom detached caretaker unit. Sewage will flow via gravity to a 1500 gallon two-compartment septic tank with an effluent filter installed in the second compartment. Effluent will flow via gravity to a 1000 gallon, two compartment pumping vault with a ProPak pumping system installed in the second compartment. Effluent will be pumped to a distribution box and will the flow via gravity to 5 -trench, soil treatment area. Each trench will have 23 Quick -4 chambers for a total of 115 chambers. The soil treatment area must be a minimum of 134 feet to any well, 84 feet to any pond, stream or irrigation ditch, and 59 feet to any dry gulch. This Permit must be kept on-site during installation. The engineer must do a final inspection of the installation and submit an "as -built" letter to this Department within 30 days of the final inspection, unless a longer period of time has been agreed upon, in writing. This Department must also be called for the final inspection with a minimum of 48 hours notice. Minimum horizontal distances between components of the system and physical features shall conform to the requirements of the Pitkin County OWTS Regulation. This Permit is conditioned upon the property owner(s) providing for regular inspection, cleaning, and maintenance of the system by qualified personnel, in accordance with the manufacturer's recommendations and the requirements of the Pitkin County OWTS Regulation. Issuance of this OWTS Construction Permit does not constitute a guarantee, warranty, or representation by the Department that the system will operate properly or will not fail. THIS PERMIT IS EXPRESSLY CONDITIONED UPON COMPLIANCE WITH ALL REQUIREMENTS OF THE PITKIN COUNTY OWTS REGULATION, INCLUDING BUT NOT LIMITED TO THOSE CONDITIONS SPECIFIED ABOVE. Plans and specifications for the proposed OWTS have been reviewed and are considered satisfactory. Permission is hereby given to the property owner(s) to perform the work indicated in accordance with the Pitkin County OWTS Regulation. This Permit will expire 1 year from the date of issuance unless construction on the system has commenced. An "as -built" drawing must be submitted and approved by EH before final approval of the system will be issued. Issued By:f>:"� (�',.. Date: 8/24/13 Expires: 08/24/2014 Installer. License #: - Reactivation Authorized by: Final Approval Issued By' Date: T+ New Expiration Date: �� t " 0 U Z 6.2rn,3 . eo�---T ONSITE WASTEWATER TREATMENT SYSTEM (OWTS) �� CONSTRUCTION PERMIT APPLICATION I?tlAhlt 76 Service Center Rd • Aspin, Co • 81611 0 Phone:'970.920,5070 Fax: 970.920.5374 Parcel 100 (available from the Pitkin County Assessors Office" t 670.9211.5160 or at ympitkinassessor.oral: l t _ OO Purpose of Permit: O NEW ❑ REPAIR DUE TO FAILURE ❑ REMODEL/ADDITION ❑ TANK ONLY ❑ FIELD ONLY Cost of System Repair or RemodellAddition (approximate): Property Address: /!5 � � A A S lov7,v ri9Q wbo%> .��• ,,nlo�rt/ c � 8`1 rS�/ Lot: f5 Block: Filing: Subdivision: ry .Jv Properly Owner(s)': Email Address: XW? y I.D9vv �Po7'N Owner's M11;1, Address: City, State, Zip: r,✓rso �O •9i wFc - it/ // 0.�. Homo Phone: Business Phone: 'Contact Information must be providod for the owner signing tris application. Primary Contact PersoruApplicant (if not owner): Company, Rte' fNJ' Co�,�vGj.onJ ggrw Lr 0"0 Contact/pflcant Malting Address: x 6 7N -,V1'4/ ,c�A7r pd City, State, Zip: 4rIve-v (71 Cell Phone: o X7`/07o Business Phone: p� Fax Number: Email Adds G// rres R07--.etFa01VJ41 fU fon/. Ge Building Permit N of appicable):oo S o k o l f . 12y.4 if O o Lot Size (In acres): Size of BwWing (square feel): / e /.Z' Number of Potential Bedrooms: Detached Accessory Uril7 OYES ❑ NO Size of Accessory Unit (square (eel): /� 6 Number of Potential Beitrooms In or Fixture List for the Accessory Unit: YYtlICI 0Vl{14tl. ❑ PRIVATE WELL ❑ SURFACE WATER ❑ SPRING ❑ COMMUNITY/PUBLIC WATER SYSTEM PLEASE READ BEFORE SIGNING: 1 codify that the abovo Information Is complete and accurate and that I havo providad complete and accurate Information In all of the documents Included In my application package. 1 acknmvtedge that EWNR may revoke any permit I am issuod If my application is found to contain any Inaccurato, false, or misloading Information. I understand that no construction may bo undertaken on on OWTS until an OWTS Construction Permit Is Issued. Owner Signature(Requ'ued): � Date: SignaldW. Oats: ' F.OR�"OhFl0Ett13E_ _1r Recelved by EN/HR Staff: Fee 8 Receipt N: Date: 162 c 8 r Zoi IS arcIEW KEGS\Office - m omis Const FormAMIScomtruc on Perot apPtalon. s I. updated. 11017108 L ONSI It E WASTEWATER TREATMENT � ISTEM (OWTS) =EH USE PERMIT APPLICATION CHECKLIST 76 Service Center Rd - Aspen, CO • 81611 Phone: 970.920.5070 Fax: 970.920.5374 A complete amlication package must be presented at the time of your pre -application conrerence Tor a4ceptance. To schedule a pre -application conference, please call 970-920-5070. PLEASE INITIAL EACH ITEM TO INDICATE COMPLETION Only one copy of each item is necessary. OWTS Use Permit Application (completed) Site Plan F1 Please indicate the type of document to be submitted below. [] 11" X 17" and/or ❑ Electronic document emailed to ehnr(d.co.oitkin.co.us before the date of the pre -application conference ❑ All des gns must be 1" to 20' in scale. ❑ Site plan must include locations of existing wells, buildings, property lines, ditches, water lines, springs, irrigation lines, drinking water cisterns, drain tiles, water bodies, wetlands, riparian areas, floodplains, dry gulches, and existing OWTSs. Soil Testing Notification & Report (must be provided by a PE) ❑ This Department should be notified when soil tests are conducted. A 2"- 4" perforated PVC pipe should be placed in the soil profile hole for monitoring purposes. F] Report must include percolation test results and the soil profile evaluation. Building Floor Plans ❑ 11" X -17", or submitted electronically to ehnr(a)co.aitkin.co.us before the date of the pre -application conference. Land Use Approvals & Other Relevant Permits 8r Approvals ❑ Recorded Site Plan that designates approved envelope(s) for development. If the property is exempt from this requirement, please have a Community Development Planner email ehnr(a)co.oitkin.co.us with confirmation of the exemption. ❑ 24" X 36" and ❑ 11" X 17", or electronic document emailed to ehnr(cDco.aitkin.co.us before the date of the pre -application conference ❑ Copies of all land use approvals, as well as all other documentation relevant to the siting of the OWTS(s) and any other develcpment on the property (e.g., Resolutions, Administrative Decisions, recorded easements). Comments from EHINR regarding Land Use review referrals can be accessed by opening http //www aspenoitkin com1Pdfs/depts/7/landuse.pdf and clicking the blue link in the Referrals" column. Referral comments more than 2 years old may need to be requested from the County Planning Department. Construction Management Plan ❑ Required & Obtained ❑ Not Required Requirements: http //www aspenoitkin com/pdfs/depts/7/CMP Manual.pdf Forms: http //www aspenpitkin com/deptsl7lbldodiv.cfm Proof of Adequate Water Supply Legal water supply must be demonstrated in accordance with Colorado water law and meet the requirements of the Pitkin County Land Use Code. ❑ Private systems: Proof generally includes a well driller's report, well permit issued by the Colorado Division of Water Resources, final augmentation plan (if required), and a recent pumping report. Wells must be drilled before an application will be accepted. ❑ Public systems: Proof generally includes a letter from the CWQCD - approved public water system confirming it has sufficient water to supply the development and it has agreed to do so. Initial Site Inspection ❑ All components of the OWTS, as well as the proposed buildings, water source, and other pertinent physical features must be deariy staked and labeled prior to the inspection. Inspection must be scheduled between May 1st and Oct 31st, unless otherwise approved by EH/NR. Applicable Fee ❑ OWTS Construction Permit: $1,023' ❑ Tank Only: $523' *There is an additional Administrative Fee of $175.00 for properties in the Town of Snowmass Village. Please Make Checks Payable To: Pitkin County Environmental Health & Natural Resources Department TO SUBMIT A BUILDING PERMIT APPLICATION PRIOR TO OBTAINING AN OWTS CONSTRUCTION PERMIT THE FAST TRACK WAIVER MUST BE SUBMITTED TO COMMUNITY DEVELOPMENT WITH YOUR BUILDING PERMIT APPLICATION. Please note that this waiver only allows for the submittal of the Building Permit Application. It does not allow for the issuance or approval of the Building Permit without OWTS Construction Permit approval from the EH Department. G:\OWTS March 8,2008 ISIB. -GS Office -Ad minForms OWTS Const Forms OWTS Cons- on checklist.xls ;pdated:3 20 09 ENVIRONMENTAL HEALTH CHECKLIST (for approval prior to receiving a building permit) If any of the items below apply to your development, please make an appointment one of the Environmental Health professionals at 970-920-5070 or ehnr(a)co.Pitkin.co.us to avoid delays in obtaining your building permit. The Environmental Health Department keeps files of permitted onsite wastewater treatment systems (OWTS) and can provide you with information pertaining to your parcel. If you have any questions concerning the last two items please contact the Planning Engineer (970-429-2799). ❑ The new construction (including an addition/remodel) will require an onsite wastewater treatment system (OWTS), or require the addition of capacity to an existing OWTS. In this case, an OWTS permit must be obtained prior to issuance of a building permit. ❑ The additionlremodel will use an existing OWTS. If the existing system is sized appropriately and the valuation of the addition/remodel exceeds $30,000, an OWTS use permit must be obtained prior to issuance of a building permit. ❑ There are other OWTSs on the property, although none of those systems will serve the new development. These systems must obtain an OWTS use permit prior to the issuance of any OWTS permit or building permit. ❑ The project involves a food service establishment (e.g., grocery or restaurant). Environmental health staff will need to review any new construction or modifications to assure compliance with the Colorado Retail Food Establishment Rules and Regulations. These regulations can be found at http://www.cc]phe state co us/op/reqs/consumer/101019retailfood.pdf. ❑ The project involves a childcare facility. In this case, EH/NR staff will need to review any new construction or modifications to assure compliance with the State Board of Health's Rules and Regulations Governing the Health and Sanitation of Child Care Facilities. These regulations can be found at http://www cdphe state co us/op/reqs/consumer/101007childcarecentersanitarystandards.pdf. ❑ The property is located on the Smuggler Superfund Site and you will be moving more than one cubic yard of soil. In this case, you will need to complete a Smuggler Mountain Superfund Site Soil Removal Permit. See http://www.aspenpitkin.com/pdfs/depts/12/SMUGGLER dirt.pdf. ❑ You will be importing soil to the jobsite from the Smuggler Superfund Site, an old mining site, or a site that previously housed junked vehicles, oil or gasoline tanks, or other chemicals. More information, including regulations, applications, checklists, and other documents can be found at www.aspenpitkin.com/ehnr. Property Owner's Name: Z- /J--� ✓/0 P, o N Contact Numbers: (w) 9,70 % 2 S d'? Z:2— (c) Property Address: 1137 'r //SSjo1;W f".40dV 04 . f1l.Qt'�J � Co Contact Name: C tib I r LA/ 4--1711;1�2.r C,oma/ Contact Numbers: (w) 9,70 % 2 S d'? Z:2— (c) 7 7 0 'e? 9 S r / September 4, 2012 eh bldg ck1st.docx y.� OWTS DESIGN CALCULATIONS - for Pitkin Owner's Name Parcel ID # House Size (sq. ft.) (75 gpd or 100 gpd) Number of Bedrooms in Main House Number of Offices, Libraries, Studies, Similar -sized Rooms in Main House Number of Bedrooms in Detached Caretaker unit Number of Offices, Studies, Similar -sized Rooms in Caretaker Unit (If the caretaker unit is ATTACHED, treat as if part of main house.) Average Daily Waste Flow 950 State Review Required? no Perc Rate now (T) Design Flow (Q) _ # potential bedrooms X 2 people/bedroom X gpd X 1.5 Q= 1425 Minimum tank capacity 1781 gallons Absorption Area (=Q/5 X SQRT perc rate)(1.4 loading factor) A = 2,185 sq. ft. of absorption area required Absorption Area (=Q/5 X SQRT perc rate) WITH SECONDARY TREATMENT (no loading factor) A= 1,561 sq. ft. of absorption area required 100 Abs. Area w/ loading factor (1325) Trench Bed Qmck4 Trench Quick4 Bed Pipe and Gravel (-10%) 1967 no red. 2185 199 221 Dosing (20%) 1748 (-20%) 1748 177 177 Chambers (30%) 1530 (-10%) 1967 155 199 Max Allowable LK2il 1093 (-30%) 1530 111 155 Secondary Treatment Abs Area w/ out loading factor (B28) Trench Bed Pipe and Gravel (-10%) 1005 no red. 1561 142 158 Dosing (-20%) 1249 (-20%) 1249 127 127 Chambers (-30%) 1093 (-10%) 1405 111 142 Max Allowable (-50%) 781 (-30%) 1093 79 111 134 SETBACK FROM WELL # of feet = 84 SETBACK FROM POND, STREAM OR IRRIGATION DITCH # of feet = SETBACK FROM DRY GULCH # of feet = LL 33 Four Wheel Drive Rd Carbondale, CO 8162323 970-309-5259 Sf �VICf December 11, 2.015 Tony Rutgers Rutgers Construction tonvC@_rutgersconstruction.com Onsite Wastewater Treatment System (OWTS) Installation Observations Roth Residence 1153 &1155 South Starwood Drive Tract R-55 Starwood Pitkin County, Colorado OWTS Construction Permit 0026.2013.powt Tony, Project No. C1021 ALL SERVICE septic, LLC observed the installation of the onsite wastewater treatment system (OWTS) on June 17, 2014 for the subject property. Aspen Earthmoving installed the system. The OWTS was installed in accordance with ALL SERVICE septic, LLC design dated August 20, 2013. The installation included a new 1500 -gallon, two-compartment Valley Precast concrete septic tank with an Orenco® Biotube Effluent Filter on the outlet tee to serve the Main House. The sewer line from the 1500 -gallon septic tank ties into a new 1000 -gallon, two-compartment Valley Precast concrete septic tank with a screened dosing siphon in the second compartment that serves the Caretaker Dwelling Unit (CDU). Both the Orenco® Biotube Effluent Filter in the septic tank serving the Main House and the screen surrounding the dosing siphon in the septic tank serving the CDU must be cleaned annually, or as needed. The original design specified a pump; however, sufficient fall was able to be obtained to utilize a dosing siphon. Effluent is dosed to a distribution box, and then gravity flows to five rows of 23 `Quick 4' Infiltrator® chambers for a total of 1135 square feet of infiltrative area (using 9.87 square feet per chamber). There was a minimum of 6 -feet of undisturbed soil between each trench. Inspection ports were installed at the end of each trench. The OWTS was generally installed according to specifications. This observation is not a guarantee of workmanship and/or parts and materials. ALL SERVICE septic, LLC should be notified if changes are made to the O`JVTS in the future. Any additional OWTS construction must be according to the county regulations. LIMITS: Observations are limited to components that are visible at the time of the inspection. The installer must have documented and demonstrated knowledge of the requirements and regulations of the county in which they are working. The quality of the installation is dependent of the expertise of the installer, soil type, and weather conditions. Please call with questions. Sincerely, ALL SERVICE septic, LLC oaf Carla Ostberg, MPH, REHS (Inlet tee) 1500 -gallon tank serving main house Reviewed ``� Richard H Clean out Inlet tee View of clean out from inlet side of tank r �2 4 Dosing siphon with screen X Sewer line exiting bottom of 1000 -gallon tank Sewer line from tank to distribution box View of septic tank Clean out exiting CDU Distribution box (prior to placement of angled pipe on inlet and riser extensions) • E amber row N 4" SDR -35 SEWER PIPE WITH °= CL�WUT(Iy1M �°/ SLOPE TO / J TA—N- 0. AN—o Scale: 1" = 20'-0" /1000 -GALLON TWPXCOMP/CRTMFiNT NCRE SEP;r T PQK WIT�I / / / / / : , / / i / / S�Q DI TRIB TION BOX / / / 7, "S H E 0 N D IV SL T 150 -GALLON, / I COMP°yr�rM NT, RETpSEPTI 4„ SDR- SEWE IPIP W TH / I CLEANO T (MIN , SL E TO / /'QUIC 13' A E ES. ANK 1 5 RO $ CH E =11 ) 1 i CH / E SI 11 I S 1 AV 1 1 I l l k ' I I / � I /f / / / 1 i OBS RVATI POKMAT-TFIE _ J / / j I I / I N I( ENDI F EAC TRENCH RECOR 33 Four Wheel Drive Road Roth Residence Date: 12/11/15 Carbondale, CO 81623 Lot R-55 Starwood 970-309-5259 Aspen, Colorado 81611 record BMW carla@allservicesepdc.com Designed By: CO Project Number. C1021 Drawn Bv: ANG Sheet 1 of 1 e eco 4 -r rC7 AJ to g w r ' ':.v„ �� �x" � �.::d`� .a.•'Lk�'" ;�. iM' ��•�� ... ../� .,� � �_ .'"tie. � ';�5{ 4� �r � ri ,r � � +e9M, r*'c v, � � { �� ,rt ' rA, � t � • t y ��" �1�' `"�5.,.�,f I <* HT S'�•' �.� sk s4�' F+ /ter_ r ��*� ti�,`t.%ti`s� T 'n�XESY'��rs y '�i� �- r ��, pt���yY' �, X �]�J,,�,,p/,�►1":®� �� f,..L � �• . G o il n km�rood� 081602 d[HII Ph 970-618-5033 OW303-216-27% August 20, 2013 Tony Rutgers Rutgers Construction tonygrutgersconstruction.com Onsite Wastewater Treatment System Design Tract R-55 Starwood Pitkin County, Colorado Tony, Project No. C1021 ALL SERVICE septic, LLC performed has designed an onsite wastewater treatment system (OWTS) design for the subject property to serve two proposed residences. The property is located outside of Aspen, in an area where OWTSs are necessary. Domestic water will be supplied to the residences by a public water system. The original design dated February 11, 2013 should be discarded. SITE CONDITIONS The property is currently vacant. Two residences are proposed; one main house with greater than 6000 square feet of living area and 4 -bedrooms, and a guest house with one bedroom. A report prepared by HP Geotech dated December 31, 2012, Job #112 425A, describes the lot as northwest facing with a strongly sloping to moderately steep natural ground surface. Vegetation consists of aspen stands, grass, weeds, and brush. There are two active irrigation ditches located on the south and west sides of the lot. SUBSURFACE The subsurface investigation was performed by HP Geotech on November 29, 2012. One profile hole and three percolation holes were drilled. Results are detailed in the above mentioned HP Geotech report. An average of 30 minutes per inch (MPI) will be used to design the OWTS. DESIGN SPECIFICATIONS The OWTS design is based on 4 -bedrooms in the main residence with greater than 6000 square feet of living area and 1 -bedroom in the guest house. An average daily wastewater flow of 950 GPD will be used. The installation must include a 1500 -gallon, two-compartment septic tank to serve the main house. The main house tank will be connected to the inlet side of the 1000 -gallon, two-compartment tank which will serve the guest house. A Biotube® pump vault will be installed in the second compartment of the 1000 -gallon tank. An Orenco® PF3005 pump will dose effluent to a distribution box, which will distribute effluent to five rows of 23 Quick4 Infiltrator® chambers. 0 0 Page 2 The trenches may be placed at the base of the grading for the driveway, with each trench following the natural contours. Angle pieces can be used to better follow the contours and keep the depth of trench burial between 2' and 4' over chambers. The component manufacturers are typical of applications used by contractors and engineers in this area. Alternatives may be considered or recommended by contacting our office. Construction must be according to Pitkin County Onsite Wastewater Treatment System Regulations, the OWTS Construction Permit provided by Pitkin County Environmental Health Department, and this design. REVEGETATION REQUIREMENTS An adequate layer of good quality topsoil capable of supporting revegetation shall be placed over the entire disturbed are of the OWTS installation. A mixture of native grass seed that has good soil stabilizing characteristics (but without taproots), provides a maximum transpiration rate, and competes well with successional species. No trees or shrubs, or any vegetation requiring regular irritation shall be plated over the area. Until vegetation is reestablished, erosion and sediment control measures shall be implemented and maintained on site. The owner of the OWTS shall be responsible for maintaining proper vegetation cover. OPERATION INFORMATION AND MAINTENANCE The property owner shall be responsible for the operation and maintenance of each OWTS servicing the property. The property owner is responsible for maintaining service contracts for manufactured units, alternating absorption systems, and any other components needing maintenance. Geo -fabrics or plastics should not be used over the absorption area. No heavy equipment, machinery, or materials should be placed on backfilled absorption area. Livestock should not graze on the absorption area. Plumbing fixtures should be checked to ensure that no additional water is being discharged to OWTS. For example, a running toilet or leaky faucet can discharge hundreds of gallons of water a day and harm an absorption area. The homeowner should pump the septic tank every two years, or as needed gauged by measurement of solids in the tank. Garbage disposal use should be minimized, and non -biodegradable materials should not be placed into the OWTS. Grease should not be placed in household drains. Loading from a water softener should not be discharged into the OWTS. No hazardous wastes should be directed into the OWTS. Mechanical room drains should not discharge into the OWTS. The OWTS is engineered for domestic waste only. ADDITIONAL CONSTRUCTION NOTES If design includes a pump, air release valves and weep holes should be installed to allow pump lines to drain to minimize risk of freezing. Excavation equipment must not drive in excavation of the absorption area due to the potential to compact soil. Extensions should be placed on all septic tank components to allow access to them from existing grade. J Page 3 INSTALLATION OBSERVATIONS ALL SERVICE septic, LLC must view the OWTS during construction. The OWTS observation should be performed before backfill, after placement of OWTS components. Septic tanks, distribution devices, pumps, dosing siphons, and other plumbing, as applicable, must also be observed. ALL SERVICE septic, LLC should be notified 48 hours in advance to observe the installation. LIMITS: The design is based on information submitted. If soil conditions encountered are different from conditions described in report, ALL SERVICE septic, LLC should be notified. All OWTS construction must be according to the county regulations. Requirements not specified in this report must follow applicable county regulations. The installer should have documented and demonstrated knowledge of the requirements and regulations of the county in which they are working. Please call with questions. Sincerely, ALL SERVICE septic, LLC '0,tt (a, OS-�&A.Lg Carla Ostberg, MPH, REHS Reviewed A� Richard H N 6—ml e Sca I 'I/ I R-55 I I 4.371 :,C± I I� / I 2 �• w2.0 UE I n SITE PLAN sig IP.O. Box 2844 Roth Residence Date: 02/11/13 (, Glenwood Springs, Colorado 81602 Lot R-55 Starwood \ /fj / . 0 S�IIYL Phone 970.618.5033 Aspen, Colorado 81611 Revision: 08/20/13 y �/ Fax 303.216.2796 Designed By: CO Project Number. C1021 Drawn By: ANG Sheet 1 of 4 n TRENCH DETAILS FLUENT PIPE SEPTIC TANK BUTION PLACEDIN ORT OF BER END S BOX AND COVER BROUGHT TO GRADE CONCRETE LID ' FINSHED GRADE 0000 INLET OUTLETS DISTRIBUTION BOX BAFFLE /�ND-BOX DETAIL fl I I P.O. Box 2844 Roth Residence Glenwood Springs, Colorado 81602 Lot R-55 Starwood Date: 02/11/13 SENYICf S Phone 970.618.5033 Aspen, Colorado 81611 Revision: 08/20/13 W3.0 Fax 303.216.2796 Designed By: CO Project Number: C1021 Drawn By: ANG Sheet 3 of 4 DRAIN FIELD CROSS SECTION -TYP. INFILTRATOR(R) QUICK4 TM CUT SHEET a" PVC OBERVATION 52" SLIP-ON PVC CAP GLUE 48" PIPE FINISHED PVC (EFFECTIVE LENG ) GRADE OBERVATION O `-3a F PIPE 12 ENT LINE - 4" DULE 40 OR 4" SDR 3.5' X UNDISTURBED SEWER LINE -.C. SOIL 2'min40 4"SCHEDULE P.V.C.ATED tDT COPPER TRACER 6' min I —34" MAY BE INSTALLED TO LIMIT ���lll LINES TO ENTER E LINE IN FUTURE A EXCAVATION GRAVELLESS'QUICK-4' AND EXIT IN TOP SCARIFY SURFACE CHAMBER (4'x 3') PORT OF CHAMBER END PLATE 4 CLEANOUT DETAIL NOT TO zcuc PI GN \/I PW _ TYP r_o niei i cee ni iiry n rnr n TRENCH DETAILS FLUENT PIPE SEPTIC TANK BUTION PLACEDIN ORT OF BER END S BOX AND COVER BROUGHT TO GRADE CONCRETE LID ' FINSHED GRADE 0000 INLET OUTLETS DISTRIBUTION BOX BAFFLE /�ND-BOX DETAIL fl I I P.O. Box 2844 Roth Residence Glenwood Springs, Colorado 81602 Lot R-55 Starwood Date: 02/11/13 SENYICf S Phone 970.618.5033 Aspen, Colorado 81611 Revision: 08/20/13 W3.0 Fax 303.216.2796 Designed By: CO Project Number: C1021 Drawn By: ANG Sheet 3 of 4 DESIGN 4 -BEDROOM RESIDENCE > 6000 SF 1 -BEDROOM GUEST HOUSE (100 GAL/PERSON/DAY x 2 PERSONS/BEDROOM x 4 BEDROOMS) (75GAL/PERSON/DAY x 2 PERSONS/BEDROOM x 1 BEDROOM) AVERAGE DAILY FLOW = 950 GALLONS DESIGN FLOW = Q = 1.5 x 950 = 1425 GALLONS TANKS 1425 x 1.25 = 1781 GALLONS 1500 -GALLON, TWO-COMPARTMENT TANK FOR MAIN RESIDENCE 1000 -GALLON, TWO-COMPARTMENT TANK FOR GUEST HOUSE ABSORPTION AREA PERCOLATION RATE = 30 MPI 0/5 X SORT 30 = 2185 SF 30% REDUCTION FOR CHAMBERS IN A TRENCH CONFIGURATION 20% REDUCTION FOR DOSING ABSORPTION AREA REQUIRED =1093 SF 1093 SF / 9.87 SF/CHAMBER = 111 CHAMBERS 5 ROWS OF 23'QUICK-4' CHAMBERS = 115 Q4 CHAMBERS =1135 SF Septic Tank with the Addition of an Effluent Filter - 1500 Gallon, 2 -Comp. ProPakT' Effluent Pumping System - 2nd Compartment Drawdown 1000 -Gallon Scale: 1"= 2' Corarol Panel Top Vlew (NTS) Simplex Pumping System lope Ground \ Slope Ground Away From Risen Axay from Riser Filter Cartridge Handle (field cut to desired height) conduit Seal To of lee to come to 1' from top of tank lid Tank Adapter (cast or bolted) To Control Panel Inlet Tee Inlet Ta Vent Orifice Effluent Discharge ;4Vauft 2'Modulating Discharge Orifices Inlet Ports ORENCO BRAND NAME NOT ENFORCED n TANK DETAIL V Aw NWSE N Filter Cartridge Effluent Filter n TANK DETAIL OPnoNAI AT (AIEST XWg N spli a Ban w/Cord Grips Fiberglass Gasketed Lid with Stainless Steel Bolts PVC Riser with Grommetls) Discharge Assembly Fksible Hase EM.mt Discharge Tank Adapter (Cast or Bolted) Level Cantrol Float Assembly Carb dge LIM Pada Effluent Pump "Pump Vauh on Orenco Systems" 814 ARRAY AVM StMi hN, CREOM 97479-9011 TOLL FREE: (1100) 748-BB/I TREPME (541) 459-4449 FA SYE (5411459-2884 IP.O. Box 2844 Roth Residence Date: 02/11/13 rp } L 5 �, LI. Glenwood Phone 9 0 6P 8.5033 Colorado 81602 Lot R-55 Starwood Aspen, Colorado 81611 Revision: 8/20/13 Will S�I I�L " Fax 303.216.2796 Designed By: CO LI�1 L Project Number: C1021 Drawn By: ANG Sheet 4 of 4 Pump Selection for a Non -Pressurized System - Single Family Residence Project C1021 Roth Parameters Discharge Assembly Size 1.50 inches Transport Length 20 feet Transport Pipe Class 40 Loss through Discharge Transport Line Size 1.50 inches Distributing Valve Model None feet Max Elevation Lift 10 feet Design Flow Rate 30 gpm Flow Meter None inches 'Add-on' Friction Losses 0 feet Calculations 300 250 6r.nco Pig obtmi' 50 an ■rfi "0 5 10 15 20 25 30 35 40 Net Discharge (gpm) PumpData PF3005 High Head Effluent Pump 30 GPM, 1/2HP 115/230V 10 60Hz,200\/ 3060Hz PF3007 High Head Effluent Pump 30 GPM, 3/4HP 230V 10 60Hz, 200/460V 30160Hz PF3010 High Head Effluent Pump 30 GPM, 1HP 230V 10 60Hz, 200/460V 30 60Hz PF3015 High Head Effluent Pump 30 GPM, 1-1/2HP 230V 10 60Hz, 2001230/460V 30 60Hz Legeno System Curve: Pump Curve:_ Pump Optimal Range Operating Point`' Design Point - 200 Frictional Head Losses LL Loss through Discharge 2.7 feet S G Loss in Transport 1.0 feet Loss through Valve 0.0 feet Lossthrough Flowmeter 0.0 feet 150 'Add-on' Friction Losses 0.0 feet y Pipe Volumes Vol of Transport Line 2.1 gals O Minimum Pump Requirements 100 Design Flow Rate 30.0 gpm Total Dynamic Head 13.7 feet 6r.nco Pig obtmi' 50 an ■rfi "0 5 10 15 20 25 30 35 40 Net Discharge (gpm) PumpData PF3005 High Head Effluent Pump 30 GPM, 1/2HP 115/230V 10 60Hz,200\/ 3060Hz PF3007 High Head Effluent Pump 30 GPM, 3/4HP 230V 10 60Hz, 200/460V 30160Hz PF3010 High Head Effluent Pump 30 GPM, 1HP 230V 10 60Hz, 200/460V 30 60Hz PF3015 High Head Effluent Pump 30 GPM, 1-1/2HP 230V 10 60Hz, 2001230/460V 30 60Hz Legeno System Curve: Pump Curve:_ Pump Optimal Range Operating Point`' Design Point HEPWORTH-PAWLAK GEOTECHNICAL, INC. TABLE 2 PERCOLATION TEST RESULTS JOB NO. 112 425A HOLE NO. HOLE DEPTH (INCHES) LENGTH OF INTERVAL (MIN) WATER DEPTH AT START OF INTERVAL (INCHES) WATER DEPTH AT END OF INTERVAL (INCHES) DROP IN WATER LEVEL (INCHES) AVERAGE PERCOLATION RATE (MIN./INCH) P1 31 15 8'/ 8 Y2 30 8 7 Y 'Y2 7'/ 7 Y2 7 6 Y 'Y2 6 Y2 6 'Y2 6 5'/ 'Y2 P2 33 15 8 Y2 8 'Y4 Y 30 8 7 % Y 7% 7% Y2 7'Yn 6% Y2 6'/ 6'/ A 6% 5% / P3 36 15 8% 8Y2 'Y< 30 8 Y2 8 Y. 8 7 Y2 'Y2 7 Y2 7 Y2 7 6 Y Y2 6 Y2 6 Y Note: Percolation test holes were drilled with a 6 inch auger and soaked on November 28, 2012. Percolation tests were conducted on November 29, 2012. The average percolation rates were based on the last three readings of each test. HEPWORTH-PAWLAK GEOTECHNICAL, INC. TABLE 1 SUMMARY OF LABORATORY TEST RESULTS Job No. 112 425A SAMPLE LOCATION NATURAL MOISTURE CONTENT NATURALjAVEL DRY DENSITY GRADATION PERCENT PASSING NO. 200SIEVE ATTERBERG LIMITS SOIL TYPE Sandy Silty Clay BORING DEPTH SAND LIQUID LIMIT 1 PLASTIC INDEX 1 4 6.6 106 73 27 10 9 8.2 116 Sandy Silty Clay 14 7.9 113 75 23 7 Sandy Silt and Clay 19 11.8 117 77 Sandy Silty Clay 2 4 10.9 111 Sandy Silty Clay 9 4.8 110 72 Sandy Silt and Clay 14 15.1 1.15 Sandy Silty Clay 19 6.9 126, 76 Sandy Silty and Clay Profile 21/2 6.9 7 19 74 Loam 0 40 Do Your Part, Be SepticSmart. The Do's and Don'ts of Your Septic System Learn these simple steps to protect your home, health, environment and property value: septicsmart US Ermronmental Protection Agency .1"" , , , , " - — , " MTFTM Do: • Have your system inspected (in general) every three years by a licensed contractor and have the tank pumped, when necessary, generally every three to five years. Don't: • Pour cooking grease or oil down the sink or toilet. • Rinse coffee grounds into the sink. • Pour household chemicals down the sink or flush them. Do: • Eliminate or limit the use of a garbage disposal. • Properly dispose of coffee grounds & food. • Put grease in a container to harden before discarding in the trash. F uon j: uv: • Flush non -degradable products or Dispose of these items in the trash can! chemicals, such as feminine hygiene products, condoms, dental floss, diapers, cigarette butts, cat litter, paper towels, pharmaceuticals. Don't: • Park or drive on your drainfield. The weight can damage the drain lines. + Plant trees or shrubs too close to your drainfield, roots can grow into your system and clog it. Don't • Concentrate your water use by using your dishwasher, shower, washing machine, and toilet at the same time. All that extra water can really strain your septic system. Do: • Consult a septic service professional to advise you of the proper distance for planting trees and shrubs, depending on your septic tank location. Do: • Stagger the use of water -generating appliances. This can be helpful especially if your system has not been pumped in a long time. • Become more wader efficient by fixing plumbing leaks and consider installing bathroom and kitchen faucet aerators and water -efficient products. L GEx.r),tech HEPWORTH - PAWLAK GEOTECHNICAL SUBSOIL STUDY Hepworth-Pawlak Geotechnical, laic. 5720 Comm Road 154 Glenwood Springs, Colorado 81 (9)1 Phone: 970-945-7988 Fix: 970-945-8454 email: hpgco@hpgeotech.com FOR FOUNDATION DESIGN PROPOSED RESIDENCE LOT R-55, STARWOOD SUBDIVISION SOUTH STARWOOD DRIVE PITKIN COUNTY, COLORADO JOB NO. 112 425A DECEMBER 31, 2012 PREPARED FOR: LARRY ROTH 14 FOXWOOD ROAD GREAT NECK, NEW YORK 11024 Parker 303-841-7119 • Col mido Springs 719-633-5562 9 Silverthorne 974-468-1989 � A g D _ ! (kN. k/ ~ >0 kk >1kml, \ ,m coo (§§ 8c �M, ° ,� ° ^ f( )§@2 §2 / 2Erf` ®�(- 80 CT) §§) ;B�o 0- ))[ �§ t)Oo §0 ƒK° )k 11rn ` , ® zz \( j\ -n |4 ! g §< /! , § �Q f§ /e ,_ m )$ § kk� r- CDk ° \( 22 co 7 Cl)» Xo c0CD M (/ ƒ m( �f O m : ■!E-� ƒ / \ / ND 6 o co -.R ; § i { o A$]m»§G2 qQg@§g\] `;QGdT f ± »,aozGk » §S�zz,�x 922338@; f>;am;u, �m�nq, M - > 2 kt§§) :2 z §\t z ` \\ % !ik 7 \ 00- m % cq / ( y57 0 - km ( (\\ - k k S R :03CD �_ ) � k \ ) Qo // {/ m !_ } (D �I yy , J ? e k ± -) 9 l 1) k ° \ /_�F5a / ! !� y 9,mo ;f! I 2 \ ! _ -! U \§ E k $ y >f @, lnm; o% �1-0 0 / m / |§ , ! � � ! O TABLE OF CONTENTS FIGURE PURPOSE AND SCOPE OF STUDY .................................................. ................. - I - PROPOSED CONSTRUCTION................................................................................. - 1 SITECONDITIONS................................................................................................... - 2 FIELDEXPLORATION............................................................................................ - 2 SUBSURFACE CONDITIONS.................................................................................. - 2 - -FOUNDATION FOUNDATION BEARING CONDITIONS............................................................... 3 - DESIGN RECOMMENDATIONS............................................................................. - 3 FOUNDATIONS.................................................................................................... - 3 - FOUNDATION AND RETAINING WALLS......................................................... - 4 - FLOORSLABS...................................................................................................... - 6 - UNDERDRAINSYSTEM...................................................................................... - 6 - SURFACEDRAINAGE......................................................................................... - 7 - .................................................................................... - 8 - -LIMIPERCOLATIONTESTING LIMITATIONS TATIONS.......................................................................................................... - - 8 - FIGURE 1 - LOCATIONS OF EXPLORATORY BORINGS AND PERCOLATION TEST HOLES FIGURE 2 - LOGS OF EXPLORATORY BORINGS FIGURE 3 - LEGEND AND NOTES FIGURES 4 AND 5 - SWELL -CONSOLIDATION TEST RESULTS FIGURE 6 - USDA GRADATION TEST RESULTS TABLE 1- SUMMARY OF LABORATORY TEST RESULTS TABLE 2 - PERCOLATION TEST RESULTS PURPOSE AND SCOPE OF STUDY This report presents the results of a subsoil study for a proposed residence to be located on Lot R-55, Starwood Subdivision, South Starwood Drive, Pitkin County, Colorado. The project site is shown on Figure 1. The purpose of the study was to develop recommendations for the foundation and septic disposal design. The study was conducted in accordance with our proposal for geotechnical engineering services to Larry Roth dated November 20, 2012. A field exploration program consisting of exploratory borings was conducted to obtain information on the subsurface conditions. Samples of the subsoils obtained during the field exploration were tested in the laboratory to determine their classification, compressibility or swell and other engineering characteristics. The results of the field exploration and laboratory testing were analyzed to develop recommendations for foundation types, depths and allowable pressures for the proposed building foundation. This report summarizes the data obtained during this study and presents our conclusions, design recommendations and other geotechnical engineering considerations based on the proposed construction and the subsurface conditions encountered. PROPOSED CONSTRUCTION The proposed construction will consist of a two story main residence over a walk -out basement level with an attached garage and a single story CDU over walk -out basement level, located on the lot as shown on Figure 1. The basement levels will be slab -on -grade and a portion of the main residence will be structurally supported over a erawlspaee level. Grading for the structure is assumed to be relatively minor with cut depths between about 4 to 10 feet. We assume relatively light foundation Ioadings, typical of the proposed type of construction. If building loadings, location or grading plans change significantly from those described above, we should be notified to re-evaluate the recommendations contained in this report. Job No. 112425A Ck� tech -2 - SITE CONDITIONS The lot was vacant at the time of our field exploration. The lot is located on a northwest - west facing hillside with a strongly sloping to moderately steep natural ground surface down to the northwest. Vegetation consists of dense aspen stands, grass, weeds and brush. Active irrigation ditches are located on the southeast and west sides of the lot. FIELD EXPLORATION The field exploration for the project was conducted on November 28, 2012. Two exploratory borings were drilled at the locations shown on Figure 1 to evaluate the subsurface conditions. The borings were advanced with 4 inch diameter continuous flight augers powered by a truck -mounted CME -45B drill rig. The borings were logged by a representative of Hepworth-Pawlak Geotechnical, Inc. Samples of the subsoils were taken with a 2 inch I.D. spoon sampler. The sampler was driven into the subsoils at various depths with blows from a 140 pound hammer falling 30 inches. This test is similar to the standard penetration test described by ASTM Method D-1586. The penetration resistance values are an indication of the relative density or consistency of the subsoils. Depths at which the samples were taken and the penetration resistance values are shown on the Logs of Exploratory Borings, Figure 2. The samples were returned to our laboratory for review by the project engineer and testing. SUBSURFACE CONDITIONS Grapaic logs of the subsurface conditions encountered at the site are shown on Figure 2. The subsoils consist of about 1 foot of topsoil overlying very stiff to hard, slightly gravelly, sandy, silty clay with clayey silty sand and sandy silt lenses. Laboratory testing performed on samples obtained from the borings included natural moisture content, density, finer than sand size gradation analyses and liquid and plastic Job No. 112 425A CPtech -3 - limits. Results of swell -consolidation testing performed on relatively undisturbed drive samples of the natural clay soils, presented on Figures 4 and 5, indicate low to moderate compressibility under conditions of loading and wetting and minor swell or collapse potential (settlement under constant load) when wetted under constant light surcharge loading. The laboratory testing is summarized in Table 1. No free water was encountered in the borings at the time of drilling or when checked I day later and the subsoils were slightly moist to moist. FOUNDATION BEARING CONDITIONS The sandy silty clay soils encountered in the borings typically possess a low bearing capacity and low settlement/heave potential if wetted. Spreading footing bearing on the natural fine-grained soils can be used provided the risk of potential differential movement is acceptable to the owner. We should further evaluate the bearing conditions and settlement/heave potential at the time of construction. DESIGN RECOMMENDATIONS FOUNDATIONS The design and construction criteria presented below should be observed for a spread footing foundation system. I) Footings placed on the undisturbed natural granular soils should be designed for an allowable bearing pressure of 2,000 psf. Based on experience, we expect settlement of footings designed and constructed as discussed in this section will be about 1 inch. Additional movement could occur if the bearing soils become wet. The amount of movement would depend on the depth and extent of wetting. For a wetted depth of 10 feet the additional movement could be up to I inch. Care should be taken to Job No. 112 425A G8'ftech M reduce the risk of subsurface wetting by following the recommendations contained in this report 2) The footings should have a minimum width of 16 inches for continuous walls and 2 feet for isolated pads. 3) Exterior footings and footings beneath unheated areas should be provided. with adequate soil cover above their bearing elevation for frost protection. Placement of foundations at least 42 inches below exterior grade is typically used in this area. 4) Continuous foundation walls should be reinforced top and bottom to span local anomalies. Foundation walls acting as retaining structures should also be designed to resist lateral earth pressures as discussed in the "Foundation and Retaining Walls" section of this report. 5) Existing topsoil and any loose or disturbed soils should be removed and the footing bearing level extended down to the undisturbed natural clay soils. The exposed soils in footing area should then be moistened and compacted. 6) A representative of the geotechnical engineer should observe all footing excavations prior to concrete placement to evaluate bearing conditions. FOUNDATION AND RETAINING WALLS Foundation walls and retaining structures which are laterally supported and can be expected to undergo only a slight amount of deflection should be designed for a lateral earth pressure computed on the basis of an equivalent fluid unit weight of at least 55 pcf for backfill consisting of the on-site fine-grained soils. Cantilevered retaining structures which are separate from the residences and can be expected to deflect sufficiently to mobilize the full active earth pressure condition should be designed for a lateral earth pressure computed on the basis of an equivalent fluid unit weight of at least 45 pcf for backfill consisting of the on-site fine-grained soils. Job No. 112425A G-�'Oftech -5 - All foundation and retaining structures should be designed for appropriate hydrostatic and surcharge pressures such as adjacent footings, traffic, construction materials and equipment. The pressures recommended above assume drained conditions behind the walls and a horizontal backfill surface. The buildup of water behind a wall or an upward sloping backfill surface will increase the lateral pressure imposed on a foundation wall or retaining structure. An underdrain should be provided to prevent hydrostatic pressure buildup behind walls. Backfill should be placed in uniform lifts and compacted to at least 90% of the maximum standard Proctor density at a moisture content near optimum. Backfill in pavement and walkway areas should be compacted to at least 95% of the maximum standard Proctor density. Care should be taken not to overcompact the backfill or use large equipment near the wall, since this could cause excessive lateral pressure on the wall. Some settlement of deep foundation wall backfill should be expected, even if the material is placed correctly, and could result in distress to facilities constructed on the backfill. The lateral resistance of foundation or retaining wall footings will. be a combination of the sliding resistance of the footing on the foundation materials and passive earth pressure against the side of the footing. Resistance to sliding at the bottoms of the footings can be calculated based on a coefficient of friction of 0.35. Passive pressure of compacted backfill against the sides of the footings can be calculated using an equivalent fluid unit weight of 350 pc£ The coefficient of friction and passive pressure values recommended above assume ultimate soil strength. Suitable factors of safety should be included in the design to limit the strain which will occur at the ultimate strength, particularly in the case of passive resistance. Fill placed against the sides of the footings to resist lateral loads should be compacted to at least 95% of the maximum standard Proctor density at a moisture content near optimum. Job No. 112 425A GLCPf@Cl 1 -6 - FLOOR SLABS The natural on-site soils, exclusive of topsoil, are suitable to support lightly loaded slab - on -grade construction. To reduce the effects of some differential movement, floor slabs should be separated from all bearing walls and columns with expansion joints which allow unrestrained vertical movement. Floor slab control joints should be used to reduce damage due to shrinkage cracking. The requirements for joint spacing and slab reinforcement should be established by the designer based on experience and the intended slab use. A minimum 4 inch layer of free -draining gravel should be placed beneath basement level slabs to facilitate drainage. This material should consist of minus 2 inch aggregate with at least 50% retained on the No. 4 sieve and less than 2% passing the No. 200 sieve. All fill materials for support of floor slabs should be compacted to at least 95% of maximum standard Proctor density at a moisture content near optimum. Required fill can consist of the on-site granular soils devoid of vegetation, topsoil and oversized rock. UN13ERDRAIN SYSTEM Although free water was not encountered during our exploration, it has been our experience in mountainous areas that local perched groundwater can develop during times of heavy precipitation or seasonal runoff. Frozen ground during spring runoff can also create a perched condition. We recommend below -grade construction, such as retaining walls, crawlspace and basement areas, be protected from wetting and hydrostatic pressure buildup by an underdrain system. The drains should consist of drainpipe placed in the bottom of the wall backfill surrounded above the invert level with free -draining granular material wrapped in filter fabric. The drain should be placed at each level of excavation and at least I foot below lowest adjacent finish grade and sloped at a minimum 1 % to a suitable gravity outlet. Free -draining granular material used in the underdrain system.should contain less than Job No. 112 425A � i GecPtech -7- 2% passing the No. 200 sieve, less than 50% passing the No. 4 sieve and have a maximum size of 2 inches. The drain gravel backfill should be at least 1 % feet deep. An impervious membrane such as 20 mil PVC should be placed beneath the drain gravel in a trough shape and attached to the foundation wall with mastic to prevent wetting of the bearing soils. SURFACE DRAINAGE The following drainage precautions should be observed during construction and maintained at all times after the buildings have been completed: 1) Inundation of the foundation excavations and underslab areas should be avoided during construction. 2) Exterior backfill should be adjusted to near optimum moisture and compacted to at least 95% of the maximum standard Proctor density in pavement and slab areas and to at least 90% of the maximum standard Proctor density in landscape areas. 3) The ground surface surrounding the exterior of the building should be sloped to drain away from the foundation in all directions. We recommend a minimum slope of 12 inches in the first 10 feet in unpaved areas and a minimum slope of 3 inches in the first 10 feet in paved areas. Free -draining wall backfill should be capped with about 2 feet of the on- site soils to reduce surface water infiltration. A swale may be needed above the residence to direct surface runoff and irrigation ditch overflow away from the residence. The irrigation ditch could be lined to reduce the risk of ditch leakage impacting the house. 4) Roof downspouts and drains should discharge well beyond the limits of all backfill. 5) Landscaping which requires regular heavy irrigation should be located at least 10 feet from foundation walls. Consideration should be given to use of xeriscape to reduce the potential for wetting of soils below the building caused by irrigation. Job No. 112 425A r" *`Ptech KIM PERCOLATION TESTING Percolation tests were conducted on November 29, 2012 to evaluate the feasibility of an infiltration septic disposal system at the site. One profile boring and three percolation holes were drilled at locations as shown on Figure 1. The test holes were drilled with 6 inch diameter auger and were soaked with water one day prior to testing. The soils encountered in the percolation holes are similar to those encountered in the Profile Hole shown on Fig. 2 and consist of about 1 foot of topsoil overlying stiff to very stiff, sandy silty clay. The percolation test results are presented in Table 2. A civil engineer should design the infiltration septic disposal system. LIMITATIONS This study has been conducted in accordance with generally accepted geotechnical engineering principles and practices in this area at this time. We make no warranty either express or implied. The conclusions and recommendations submitted in this report are based upon the data obtained from the exploratory borings drilled at the locations indicated on Figure 1, the proposed type of construction and our experience in the area. Our services do not include determining the presence, prevention or possibility of mold or other biological contaminants (MOBC) developing in the future. If the client is concerned about MOBC, then a professional in this special field of practice should be consulted. Our findings include interpolation and extrapolation of the subsurface conditions identified at the exploratory borings and variations in the subsurface conditions may not become evident until excavation is performed. If conditions encountered during construction appear different from those described in this report, we should be notified so that re-evaluation of the recommendations may be made. This report has been prepared for the exclusive use by our client for design purposes. We are not responsible for technical interpret ations.by others of our information. As the project evolves, we should provide continued consultation and field services during construction to review and monitor the implementation of our recommendations, and to Job Na 112 425A G-80'ftech -9 - verify that the recommendations have been appropriately interpreted. Significant design changes may require additional analysis or modifications to the recommendations presented herein. We recommend on-site observation of excavations and foundation bearing strata and testing of structural fill by a representative of the geotechnical engineer. Respectfully Submitted, HEPWORTH - PAWLAK GEOTECHNICAL, INC. 04 Q Robert E. Stempihar Reviewed by: Dani cc: CCY Architects - Attn: Matt Smith (msmith&cyarchitects.com) Carla Ostberg (cbo2610(a7yahoo.com) Job No. 112 425A e tGCh HYDROMETER ANALYSIS I SIEVE ANALYSIS 24 HR. 7 HR TIME READINGS I U.S. STANDARD SERIES I CLEAR SQUARE OPENINGS 0 45 MIN. IN. 60MIN19MIN.4 MIN. 1 MIN. #200 #100 #50 #30 #16 #8 #4 3/8" 3/4" 1 1/2" 3" 5'6"8" 100 10 20 30 0 40 w z Q w cr 50 H Z Lu U w CL 60 70 80 90 90 80 70 60 z U) U) a 50 a Z w U ir w 40 a- 30 20 10 100— 0 .001 .002 .005 .009 .019 .037 .074 .150 .300 .600 1.18 2.36 4.75 9.5 19.0 37.5 76.2 152 203 12.5 127 DIAMETER OF PARTICLES IN MILLIMETERS CLAY SILTSAND GRAVEL COBBLES V. fltE T7 —E MEDIUM COARSE V COARSE : AAM I Miro e GRAVEL 8 % USDA SOIL TYPE: Loam SAND 28 % SILT 38 % CLAY 26 % FROM: Profile Boring at 22 Feet 112 425A I -� i t I USDA GRADATION TEST RESULTS FIGURE 6 HEPWORTH-PAWIAKGEOTECHNICAL J Moisture Content 8.2 percent Dry Density 116 pcf Sample of: Sandy Silty Clay From: Boring 1 at 9 Feet 0 2 0 Compression upon Cl) M 3 wetting M 0 C) 4 5 0.1 1.0 10 100 APPLIED PRESSURE (ksf) Moisture Content 11.8 percent Dry Density 117 pcf Sample of: Sandy Silty Clay From: Boring 1 at 19 Feet 0 z 0 —Compression 1 1 upon U) Lu cc 2 wetting (L 0 i C) 3 4 0.1 1.0 10 100 APPLIED PRESSURE (ksf) 112 425A techSWELL-CONSOLIDATION TEST RESULTS FIGURE 4 G,,g 1 HFPWORTH-PAWLAK GEOTECHNICAL I I LEGEND: ® TOPSOIL; organic slightly clayey, silt and sand, firm, frozen, roots, slightly moist, reddish brown. CLAY (CL); slightly gravelly, sandy, silty to very silty, clayey silty sand to sandy silt lenses, very stiff to hard, slightly moist to moist, reddish brown, rocks consist of sandstone fragments. Relatively undisturbed drive sample; 2 -inch I.D. California liner sample. 22/12 Drive sample blow count; indicates that 22 blows of 140 pound hammer falling 30 inches were required to drive the California sampler 12 inches. —� Indicates depth boring caved when checked on November 29, 2012, NOTES: 1. Exploratory borings were drilled on November 28, 2012 with 4 -inch diameter continuous flight power auger. 2. Locations of exploratory borings were measured approximately by pacing from features shown on the site plan provided. 3. Elevations of exploratory borings were obtained by interpolation between contours shown on the site plan provided. 4. The exploratory boring locations and elevations should be considered accurate only to the degree implied by the method used. 5. The lines between materials shown on the exploratory boring logs represent the approximate boundaries between material types and transitions may be gradual. 6. No free water was encountered in the borings at the time of drilling or when checked 1 day later. Fluctuation in water level may occur with time. 7. Laboratory Testing Results: WC = Water Content (%) DD = Dry Density ( pcf ) +4 = Percent retained on the No. 4 sieve -200 = Percent passing No. 200 sieve LL = Liquid Limit (%) PI = Plasticity Index (%) 112 425A I � ' tech I LEGEND AND NOTES I FIGURE 3 HEPWORThI—PAWtAK rFn7Ftutiir a� 8515 8510 8500 L [7 8495 W W BORING 1 BORING 2 PROFILE BORING ELEV.=8512' ELEV.=8500' ELEV.=8484' 8515 8510 22/12 WC=6.6 DD=106 APPROXIMATE PROPOSED MAIN —2 027 3 RESIDENCE LOWER LEVEL, ELEV.=8,500' 8500 PI=10 20/12 WC=8.2 DD=116 26/12 W 019 8495 I F LL =11Lu z 22/12 O WC=7.9 Q DD=113 > —200=75 41/12 J 8490 LL=23 WC=4.8 W PI=7 DD=110 —200=72 28/12 WC= 11.8 DD=117 —200=77 22/12 8485 WC=15.1 lo DD=115 —� 50/9 35/12 8480 WC=6.9 DD=126 —200=76 8475 9/12 WC=6.9 +4=7 —200 = 74 26/12 Z O F- 8490 8490 J W 8485 8480 8475 NOTE: Explanation of symbols is shown on Figure 3. Hp 112425A HEF'WQG('(r>t ch I LOGS OF EXPLORATORY BORINGS FIGURE 2 RTH—PAWLAK GEOTECHNICAL LPO Box 2844 S t' C Glenwood Springs, CO 81602 P ` Ph 970-618-5033 Fax 303-216-27% February 11, 2013 Tony Rutgers Rutgers Construction tonykrutizersconstruction.com Onsite Wastewater Treatment Systen Tract R-55 Starwood Pitkin County, Colorado Tony, Project No. C 1021 ALL SERVICE septic, LLC performed has designed an onsite wastewater treatment system (OWTS) design for the subject property to' rve two proposed residences. The property is located outside of Aspen, in an area where OWTSs e necessary. Domestic water will be supplied to the residences by a public water system. �� The property is currentfely wo re ' ences are proposed; one main house with less than 6000 square feet of living arrooms, d a guest house with one bedroom. A report prepare by HP Geotech dated D 2012, Job 112 425A, describes the lot as northwest facing with a strongly sloping to mop natural round surface. Vegetation consists of aspen stands, grass, weeds, and brushwo active i igation ditches located on the south and west sides of the lot. _----- BSURFACE The subsurface investigation was rformed by HP Geotech on November 29, 2012. One profile hole and three percolation holes were drill Results are detailed in the above mentioned HP Geotech report. An average of 30 minutes per inch (MPI) ill be used to design the OWTS. SPECIFICATIONS The OWTS design is based on 4 -bedrooms in the main residence with less than 6000 square feet of living area and I -bedroom in the guest house. An average daily wastewater flow of 750 GPD will be used. The installation must include a 1500 -gallon, two-compartment septic tank to serve the main house. The main house tank will be connected to the inlet side of the 1000 -gallon, two-compartment tank which will serve the guest house. A Biotube® pump vault will be installed in the second compartment of the 1000 -gallon tank. An Orenco® P-30 pump will dose effluent to a distribution box, which will distribute effluent to four rows of 23 Quick4 Infiltrator® chambers. Page 2 The trenches may be placed at the base of the grading for the driveway, with each trench following the natural contours. Angle pieces can be used to better follow the contours and keep the depth of trench burial between 2' and 4' over chambers. Construction must be according to Pitkin County Onsite Wastewater Treatment System Regulations, the OWTS Construction Permit provided by Pitkin County Environmental Health Department, and this design. OPERATION INFORMATION AND MAINTENANCE The property owner shall be responsible for the operation and maintenance of each OWTS servicing the property. The property owner is responsible for maintaining service contracts for manufactured units, alternating absorption systems, and any other components needing maintenance. The surface of the drain field should be seeded upon completion. Vegetation is an important factor in drain field performance. Erosion control should be practiced prior to and during re -vegetation. Geo - fabrics or plastics should not be used over the drain field. No heavy equipment, machinery, or materials should be placed on backfilled drain field. Livestock should not graze on the drain field. Plumbing fixtures should be checked to ensure that no additional water is being discharged to OWTS. For example, a running toilet or leaky faucet can discharge hundreds of gallons of water a day and harm a drain field. The homeowner should pump the septic tank every two years, or as needed gauged by measurement of solids in the tank. Garbage disposal use should be minimized, and non -biodegradable materials should not be placed into the OWTS. Grease should not be placed in household drains. Loading from a water softener should not be discharged into the OWTS. No hazardous wastes should be directed into the OWTS. Mechanical room drains should not discharge into the OWTS. The OWTS is engineered for domestic waste only. ADDITIONAL CONSTRUCTION NOTES If design includes a pump, air release valves and weep holes should be installed to allow pump lines to drain to minimize risk of freezing. Excavation equipment must not drive in excavation of drain field due to the potential to compact soil. Extensions should be placed on all septic tank components to allow access to them from existing grade. Precast concrete tanks and distribution boxes should be used, unless plastic or fiberglass is required. Access to all tank compartments and distribution devices is optimal. INSTALLATION OBSERVATIONS ALL SERVICE septic, LLC must view the OWTS during construction. The OWTS observation should be performed before backfill, after placement of OWTS components. Septic tanks, distribution devices, pumps, dosing siphons, and other plumbing, as applicable, must also be observed. ALL SERVICE septic, LLC should be notified 48 hours in advance to observe the installation. LIMITS: Page 3 The design is based on information submitted. If soil conditions encountered are different from conditions described in report, ALL SERVICE septic, LLC should be notified. All OWTS construction must be according to the county regulations. Requirements not specified in this report must follow applicable county regulations. The installer should have documented and demonstrated knowledge of the requirements and regulations of the county in which they are working. Please call with questions. Sincerely, ALL SERVICE septic, LLC 'OA (�- Os�&ALS Carla Ostberg, N4PH, RENS 1101 Reviewed Richard H I N 0 TZ {/f s C'i m n 9 0 O O O O W . X N O N o? �N O � O N w �� W' w O O a 0 m rn 0 N CD I N 0 o? V- w �� I t CD o Ci w j (A m x \� D Z \\ • Q I I _ I N 0 C. rq 4Do 'j0a AcD-i -� ZEA �-Z. < n A 0 m �v — m Cq Z \ --------------- . ( /§ -,|�,, 3- am � `� 2§ƒ j \ -n\ �Z °�Z z ) ( \ m m k Ej k \ m m \ ° 0 \ \ 0°0 m %M,0 # _ 0cn 0 3 / 7 (2 m0 \ \ 0 , •. �k ) A. \}k g§; ImT DESIGN 44BEDROOM RESIDENCE > 6009 SF 1 -BEDROOM GUEST HOUSE (75 GAL/PERSON/DAY x 2 PERSONS/BEDROOM x 5 BEDROOM) AVERAGE DAILY FLOW = 750 GALLONS DESIGN FLOW - Q = 1.5 x 750 = 1125 GALLONS TANKS 1125 x 1.25 = 1406 GALLONS 1500 -GALLON, TWO-COMPARTMENT TANK FOR RESIDENCE 1000 -GALLON, TWO-COMPARTMENT TANK FOR GUEST HOUSE ABSORPTION AREA PERCOLATION RATE = 30 MPI 0/5 X SORT 30 = 1232 SF 30% REDUCTION FOR CHAMBERS IN A TRENCH CONFIGURATION 20% REDUCTION FOR DOSING ABSORPTION AREA REQUIRED - 863 SF 863 SF 19.87 SF/CHAMBER = 87 CHAMBERS 4 ROWS OF 23'QUICK-4' CHAMBERS - 92 Q4 CHAMBERS - 904 SF Septic Tank with the Addition of an Effluent Filter -1500 Gallon, 2 -Comp. bps Ground \ R Away From Rnera 0-0 Systems" Inter Cartridge Handle e (field cut to deeired height) 7to Tof tee to corm Tank Adapter (cast or bolted) from lop of tack Lot R-55 Starwood blit Tee Vert Drifice AY 614 ,n MlE Effluent Discharge 77)7A J y' Laud Carel � � U Modulating Dkcharge Wflcee Aspen, Colorado 81611 Moult Inlet Porte ORENCO BRAND NAME NOT ENFORCED 6DETAIL �� Filter Cartridge Effluent Filter ProPakT1 Effluent Pumping System - 2nd Compartment Drawdown 1000 -Gallon R Scale; )' • 2 Conol Panel Top Via w (NTS) 9lmplex Pumping Sy8mm (71 in ADEOrenco 0-0 Systems" Date: 02111/13 e F1 i l L I—W.w Lot R-55 Starwood Splice Box� AY 614 ,n MlE .Cord Grgym MOLT 1. OREGON Aspen, Colorado 81611 Fiberglass GaWwted Lid wllh 27479-9012 111aS� Fax 303.216.2798 Sfelniees Steel Botts Project Number: C1021 Slop Ground Away from Riser PVC Piser with Grommat(e) TOLL FRET rte. (NO) 116-9aQ - Disc mge Assembly TBINW- (6U) 1.76-1449 Conduh Seal — Fleeibb HM FACSIMILE To Control Panel I Elflwnl Ditchatgfi (%t) - Inlet T. Tank Adapter (Cast or Ballad) Level Control ,_ float Assembly TANK ADETAi Mar Cartridge bhan tnMt Porte Orenco Effluent Pump BlotvI>PPump Vauh R P.O. Box 2844 Roth Residence Date: 02111/13 i l L L Glenwood Springs, Colorado 81602 Lot R-55 Starwood W4.0 tl Phone 970.618.5033 Aspen, Colorado 81611 Designed By: CO 111aS� Fax 303.216.2798 Project Number: C1021 Drawn By: ANG Sheet 4 of 4 RECEtPTION9: 5937",111OW2012 at 12:21:04 PM, 1 OF 7, R $0.00 Doc Code ADMIN DECISION Janice K. Vos Caudill, Pitkin CourttY, CO AttNIINISt RATIVE DETERMINATION OF THE COMMUNITY DEVELOPMENT DIRECTOR OF Pnxw COUNTY, COLORADO, GRANTING APPROVAL FOR THE STARWOOD 55 LLC ACTIVITY ENVELOPE AND SPECIAL REVIEW FOR A CDU ON LOT R-55, BLOCK 8 OF THE BOCC APPROVED STARWOOD SUBDIVISION Administrative Decision No.Za201.2 RECITALS Starwood 55LLC (hereafter referred to as "Applicant") has applied to the Community Development Director of Pitkin County ("Director") for Activity Envelope and Special Review approval for a CDU. This request is a `renewal" of a previous approval. 1. The Loi is zoned AR -10 and is approximately 43 acres making it non -conforming in size. PID#:2643 351-05-003. 2. The Lot received a previous Activity Envelope and Special Review for a CDU approval pursuant to Administrative Decision No. 71-2007 (Rec. No. 540994). The Activity Envelope was recorded at BK 94 PG 79 (Rec. No. 541279)L The Lot is currently vacant. 3. The affidavit of public notice was mailed on October 3' , 2012. No objections were received within 30 days. Public notice was published in the paper on October 0, 2012. 4. The Director finds that the Lot is: (1) mapped adjacent to elk winter range and contains important vegetation for bear habitat; and (2) within a severe wildfire hazard area and the hazard can be mitigated. 6. The Director finds this request is consistent with the requirements of the Land Use Code. APPROVED by the Director, subject to the following conditions: I . The Applicant shall adhere to all material representations made in the current or prior applications or in public meetings or hearings and shall consider those representations to be conditions of approval, unless amended by other conditions_ 2. Site plan approval is required prior to submission of any building permits. Approval of this activity envelope does not ensure approval of site plan review. 3. Prior to submission of any future building permit applications, the Applicants shall be required to submit: for approval by the County Attorney and Community Development an Activity Envelope . in accordance with Land Use Code Section 2-30-20(g) and Application Manual Section 2.1.1. The above referenced approvals shall be a condition precedent to finalization and recordation. 4. No structural development, with the exception of fencing, in excess of 30" shall occur within the setbacks of the Lot. Landscaping in the form of berms shall not exceed four fed from the most restrictive grade_ Any development located within setbacks mandated by County zoning regulations shall require a variance from the Board of Adjustment. Approval of a landscape envelope within such setbacks does not assure approval of a variance. Page 1 of 7 S. The Applicant shall adhere to the following severe wildfire standards: A. Vegetation Management 1. Within 15 feet of all structures, there should he noncombustible hardscape surfaces, low growing perennials, Mmabeds, cart grass, or irrigated plants. Woody vegetation shall not be planted within this area. Firewood or other combustible materials should not be stored within this area. Ornamental trees are permissible if the 15 foot defensible space area is extended outward frmn the furthest growth expected from the mature trees. 2. Beyond the 15' area up to 65' and 40' cross slope from the future buildings, maintain natural vegetation or irrigated grasses of at least 6" and thin existing trees and brush into individual or clusters. Limbs shall be pruned to one half the height of the tree or 10 feet, whichever is less. 3. Clusters of bushes or shrubs shall be separated from each other and from those outside of the 65 and 40 foot areas by a distance of 21A times the height of the mature vegetation. The diameter of a cluster shall be limited to 2 '/Y times the height of the mature vegetation. Plant material growing between trees and clusters shall be maintained at 6 inches or less. 4. linin and remove lower branches or brush or shrubs within clusters or individual plants to eliminate ladder fuels. 5. Apply Garlon or an equivalent to the ends of all vegetation that is cut. 6. The Applicant shall be responsible for the continued maintenance of the defensible space vegetation requirements. 7. All deadfall within 140 feet of the structure shall be removed or chipped and spread B. Water Supply for Fire Safety I . When access to a public or private pressurized water system is not available or if it is necessary to augment fire protection water systems, private ponds may be used if approved by the Community Development Department and the local fire district_ 2. Regardless of size, all structures (including detached garages and horse barns) where humans congregate regularly shall be required to install in-house sprinkler systems that meet the standards of the local fire protection district and the adopted Building Code. 3. All structures greater than five thousand (5.000) square feet in size shall be required to install in-house sprinkler systems that meet the standards of the local fire protection district and the adopted Building Code. C. Roofing Materials, Roofing Vents and Projections At and Below Roof Line, 1. The wildfire expert has recommended alternative methods of construction for roofs and projections at or below roof line in a Severe Wildfire Hazard Area. These techniques are as follows: Page 2 of a) No portion of any building shall be constructed with unenclosed projections such as decks b) Eaves shall be kept to a minimum on the down slope side and on the sides that do not have a ventilation opening unless the design and configuration of the opening is are approved by Pitkin County. Projections include, but are not limited to, eaves, cornices, soffits, roofs over open decks, cantilevered floors, by windows, decks or balconies. c) Projections may cause beat traps and should be protected as follows: L Any projection including guardrails shall be constructed with materials approved for 1 hour fire -resistive construction, and any material underlain by 518, Type x gypboard or approved equal or Type 1V Heavy Timber materials per the currently adopted building code. Projections should have no inside angles of less than 75 degrees. ii. An alternative construction for projections would require the use of non-combustible building materials or materials with a flame spread rating of less than 25 (<25 tested to ASTM E84) and listed for exterior use. Areas below projections should be void of vegetation or other combustible materials. The areas below these projections shall be protected from accumulation of vegetation by placement of stone. There shall be no storage of combustible materials under projections. Wails under projections shall be constructed of materials approved for 1 hour fire resistive construction on the exterior side of the wall. Window openings in walls below projections shall be tempered glass. Doors shall be noncombustible or 1 Y4" solid wood. 2. In addition the following standards shall apply for construction in a Severe Hazard Area a) Roofing Materials i. Class A covering or Class A Assembly as defined by the currently adopted building code. ii. No wood shakes or shingles. b) Roof Venting i. Soffit venting shall be located in the outer 113'a portion of the overhang. ii. Attic, soffit and other roof venting shall be of non -corrosive metal mesh with maximum 1/4" openings. - c) Exterior of the Structure, Including All Walls shall be- i. One (1) hour fire resistive rated materials, or ii. 518" gypboard underlying combustible materials, or iii. Cement stucco, minimum 1/4" thickness.. d) All glazing is to be tempered glazing; and i. Doors to be metal or wood 1 YT thick minimum- PW inimum Pale 3 of I e) Foundations i. Foundations, skirting, and crawl space openings shall be fully enclosed and constructed with materials approved for one (1) hour fine -resistive construction on the exterior side of the walls and shall externa from the top of grade to the underside of the floor decking or walls. D. All Hazard Arm Roofs with less than a 3:12 pitch are not permitted in Low, Medium, or Severe Wildfire Hazard Areas unless they comply with the following: 1. All roof coverings shall be constructed of non-combustible materials and installed on a Class A roof assembly. 2. All roof coverings shall have a surface that shall facilitate the natural process of clearing roof debris. 3. Protrusions above the roofline, such as parapets, shall be prohibited. 4. Roofs shall be installed as required by the adopted Building Code and shall have a minimum pitch of 1:48. S. All roof designs, coverings, or equivalent assemblies shall be specifically approved by the Fire Marshall prior to submittal of a building permit application. E. Maintenance and Miscellaneous Requirements 1. Roofs and gutters shall be kept clear of debris. 2. Roof vents shall be screened with corrosive resistant wire mesh, with mesh ono - fourth (%4) inch maximum. 3. Yards shall be kept clear of all litter, slash and flammable debris. 4. All flammable materials shall be stored on a parallel contour a minimum of fifteen (15) feet away from any structure. S. Weeds and grasses within the ten (10) foot perimeter shall be maintained to a height not more than six (6) inches. 6. Firewood1wood piles shall be stacked on a parallel contour a minimum of fifteen (15) feet away from the structure. 7. Swimming pools and ponds shall be accessible by the local fire district. 8. Fences shall be kept clear of brush and debris. 9. Wood fences shall not connect to other structures. 10. Fuel tanks shall be installed underground with an approved container. 11. Propane tanks shall be buried, if possible, or installed according to NFPA 58 standards and on a contour away from the structure with standard defensible space vegetation mitigation around any aboveground tank. Any wood enclosure around the tank shall be constructed with materials approved for two (2) hour fire -resistive construction on the exterior side of the wal ls. 12. Each structure shall have a minimum of one ten (10) pound ABC fire extinguisher. 13. Addresses shall be clearly marked with two (2) inch non-combustible letters and shall be visible at the primary point of access from the public or common access road and installed on a non-combustible post. 14. The Applicant shall comply with all other standards of the Aspen Fire Protection District Code. 6. The Applicant shall comply with the following general conditions regarding wildlife: A. Manipulation of vegetation outside of the Activity Envelope is prohibited. Page 4 of B. Mesh or woven wire fences are prohibited outside the Activity Envelope. C. Wood rail fencing shall employ three (3) rails or less, be the round or split rail type, shall not exceed fifty-four (54) inches in height above ground level, and twelve (12) inches in width (top view), and shall have at least eighteen (IS) inches between the lower two (2) rails. D. Wire fencing must be three (3) strands or less. The top wire should be a twelve -point -five (12.5) gauge twisted barbless type at a maximum height of forty-two (42) inches. The middle strands (which may be barbed) should be located a minimum twelve (12) inches apart and from the top wire preventing entanglement when mule deer jump over. The bottom strand should be sixteen (16) inches from the ground. E. Tall overly mature trees and standing dead trees (snags) should be retained at the rate of two (2) to five (5) per acre whenever possible as nesting and perching habitat. F. Fruit bearing trees and shrubs shall be prohibited within the Activity Envelope. This does not include pre-existing native trees and shrubs. G. Development shall be clustered to the maximum extent possible to minimize impact on wildlife. It Access shall be provided to the Colorado Division of Wildlife for trapping, tagging, studying, or otherwise managing wildlife. I. Trash/garbage shall be kept in an approved bear resistant container or enclosure_ J. Bird feeders, including hummingbird feeders, shall be hung away from any deck or window, and be at least ten (10) feet from the ground suspended between two (2) trees or posts. All seed feeders shall include a seed catchment pan to catch discarded seed. K. Horse grains, pellets, and cookies shall be stored in bear resistant containers. L. Pet food shall not be left outside. M. The future residence shall utilize round handled door knobs. 7. The Applicant shall also comply with the following conditions regarding wildlife: A. Vegetation outside the activity envelope shall be maintained. Because of the importance of the bear habitat on the Lot, the activity envelope shall not be altered from what is approved_ B. No trees shall be planted next to the future residence that will act as a ladder to the upper floors of the home. C. Bear proof containers shall be on site during construction for use by contractors. D. Contractor or other workers associated with construction of the future residence shall not be allowed to bring dogs on site. S. The detached CDU shall not exceed 1,000 net livable square feet of floor area, which shall count toward the total allowable floor area for the lot. The kitchen contains the following, as defined in the Aspen/Pitkin County Employee Housing Guidelines: a minimum of a two-bumer stove with oven, standard sink, and a refrigerator plus freezer. The oven must be able to bake and broil and be at least 5 cubic feet; the sink must measure at least 14"WX16"DX5.25"H; refrigerator must be at least 5.3 cubic feet and include at least a .73 cubic foot freezer. The floor plan for the CDU shall be submitted to the County Housing Office for review. 9. The Applicant shall, by covenant, guarantee that the caretaker unit: a. Shall not be required to be rented; b. Shall not be sold or otherwise conveyed or separated from the original parcel regardless of the ultimate form of ownership ofthe caretaker unit; Page 5 of 7 c. Shall be limited to occupancy by not more than two adults and related children, who qualify as (and have been found by the Housing Office to be) employees of the community under such guidelines as may be from time to time established, or members of the owner's immediate family, even though they may not qualify as employees of the community; d. Shad be rented for terms not less than 6 months if rented. lo. Upon completion of the CDU, but prior to issuance of the Certificate of Occupancy, County Housing Office staff shall be entitled to conduct an inspection of the CDU for compliance with the above -referenced requirements. 11. The caretaker dwelling unit restriction may be removed by the property owner upon approval of the Community Development Dinxior, subject to the requirement that the dwelling is removed or modified. If modified, the remaining improvements must no longer be capable of occupancy as a dwelling unit and must meet otherwise applicable Code requirements. 12. The provisions of these regulations ane for the purpose of providing a voluntary CDU on a legally created lot or parcel in the County. Any unit approved under this provision of the Pitkin County Land Use shall not- be used for mitigation of employee housing requirements as established elsewhere in said Code. 13. No development shall occur outside the approved activity envelope, with the exception of vegetation removal necessary to comply with the wildfire mitigation measures described above. No structures shall be permitted outside of the approved activity envelope. 14. The access drive shall be built to current County Standards, as described in the Pitkin County Asset Management Plan and submit for an access permit The driveway layout shall be staked in the field and reviewed and approved by the County Engineer, prior to commencement of construction. 15. Prior to commencement of any earthmoving or other construction activity, the Applicant shall - stake the corners of the activity envelope and install construction fencing around the construction site within the perimeter of the building envelope. The fencing shall remain in place until issuance of a Certificate of Occupancy. 16. All areas disturbed by construction shall be re -vegetated with native shrubs and grasses within one growing; season of the project's completion. 17. Statutory vested rights for the approval contained herein are granted pursuant to the Pitkin County Land Use Code and Colorado Statutes, subject to the exceptions set forth in Pitkin County Land Use Code, § 2-20-170 and C.R.S., § 24-68-105. The statutory vested rights granted herein shall expire on November 4 2015. 18. Failure to comply with the conditions of this approval may result in revocation of this approval, or any subsequent permit(s) or approval(s) related to this property, or vested rights associated with this property. Page 6 of 7 PUBLISHED AFTER ADOPTION FOR VESTED REAL PROPERTY Rl(;,M in the As en Times W-LAon tke M day of � , 2012. n APPROVED by the Director, this easy of _ kb v, , 2012. Cindlop e R" CK Community Development Director PMN 264335105003 P0B7-12 Page 7 of 7 RECEPTION#: 600496, 06/19%2013 at 12:05:29 PM, 1 OF 3, R $0-00 Janice K. Vos Caudill, Pitki lounty, CO ADMINISTRATIVE DECISION OF THE PITION COUNTY, COLORADO, COMMUNITY DEVELOPMENT DIRECTOR GRANTING APPROVAL FOR THE STARWOOD 55 LLC SITE PLAN REVIEW Adminwmtive Decision No. _ R -2013 Starwood 55 LLC (hereafter referred to as -Applicant') has applied to the Community Development Director of pitkin County, Colorado C `Director') for Site Plan Review to construct a single family residence and a previously approved detached Caretaker Dwelling Unit (CDU). Total floor area for the proposed to be 8,250 square feet through the use of Transferable Development Rights (MR's). Pursuant to Section 6-30-50(bx2)(a), the Starwood Subdivision may land TDR's exempt from Special Review. 1. The Lot is located at 1115 South Starwood Drive and is legally described as Block 8, Lot R-55, Starwood Eight of the BOCC approved Starwood Subdivision. 2. The Lot is approximately 4.3 acres, is in the AR -10 zone district, and is non -conforming in size. 3. The Lot received Activity Envelope and Special Review approval for a CDU Pursuantand the Administrative Decision No. 71-2007 (Rec. No. 540994). Vesting expired for this approval property was reapproved pursuant to Administrative Decision No. 82-2012 (Rec. No. 593798) with the Activity Envelope Plan recorded at B84 P 79. The Lot is currently vacant. 4. The application was referred to the Starwood Home Owners Association (HOA), Aspen Fire District. Comments were received from Starwood HOA who provided preliminary approval for the project. 5. The Applicant has slightly amended the previously approved envelope for grading around the CDU. The amendment to the envelope is not located within any constrained areas as defined in Chapter 7 of the Land Use Code. 6. Public notice was published in the Aspen Times on March 7"', 2013. An affidavit of public notice was mailed on March e, 2013. No objections were received during the 30 day comment period. 7. The Director fads that the proposal meets the standards of the Land Use Code for Site Plan Review. Tire new structures will not obstruct a ridgeline as viewed from Hwy 82 or McLain Fiats Road, both designated scenic corridors. APPROVED by the Director, subject to the following conditions: The Applicant shall adhere to all material representations made in the current or prior applications or in public meetings or hearings and shall consider those representations to be conditions of approval, unless amended by other conditions. No calculations for height, bulk, setback, size, floor area, or any other building and zoning requirements have been conducted. These requirements will be considered at the time of building Page ! of 3 RECEPTION#: 600496, 06/19/2013 at 12:05:29 PM, 2 OF 3, Janice R. Vos Caudill, Pitki 'ounty, CO permit review. Structures represented in the application aright not be permitted under building and zoning regulations. 3. Additional floor area greater than 5,750 square feet requires the use of Transferrable Development Rights (TDR's). Original TDR's for the additional floor area shall be submitted at the time of building permit submittal. 4. Prior to submission of any future building permit applications, the Applicant shall be required to submit for approval by the County Attorney and Community Development a Site Plan in accordance with Land Use Code Section 2-30-20(g) and Application Manual Section 2.1.12. The above referenced approvals shall be a condition precedent to finalization and recordation. 5. All structures shall utilize indigenous earth -tone colors and non -reflective roofing 6. At building permit application, the Applicant shall: a. Submit a drainage and erosion control plan for review and approval by Planningf&nmg. b. Submit a construction management plan for review and approval by Planning/Zoning showing the locations of staging material storage and employee and constnrction traffic parking. C. Pay the applicable impact fees_ 7. The Applicant shall comply with all conditions of Administrative Decision No. 82-2012 (Rec. No. 593798) and also submit this approval with building permit submittal. 8. Statutory vested rights for the approval contained herein are granted pursuant to the Pitkin County Land Use Code and Colorado Statutes, subject to the exceptions set forth in Pitkin County Land Use Code, § 2-20- 70 and C.R.S., § 24-68-105. The statutory vested rights granted herein shall expire on June 11 2016. 9. Failure to comply with the conditions of this approval may result in revocation of this approval, or any subsequent permit(s) or approval(s) related to this property, or vested rights associated with this property. PUBLISHED AFTER ADOPTION ADOPTION FOR VESTED REAL PROPERTY RIGHTS in the Awn DR Times Weekly on the day of,—ILLM, 2013. APPROVED by the Director, thisA 20,day of :J_ 2 2013. iSAA a- ,r Cindy Aouben, Community Development Director Page 2 of 3 RECEPTION#: 600496, 06/19/2013 at 12:05:29 PM, 3 OF 3, Janice R. Vos Caudill, Pit) County, CO PID# 264335105003 P012-13 Page 3 of 3 51 APPENDIX D Large Scale Construction Management Plan for: Address / ,- / / S S Ta cf-sl f %AQP fJ.� �drP nJ Parcel ID Number k ,�,y.-?3S/o,�"oo,f Permits Applied for: Check all that apply. Demolition Permit x Building Permit __A_Access Permit Earthmoving Permit Floodplain Permit ROW Permit Property Owner's Name Nami Owner's Representative's Name: Name Contractor's Name: Name #ansa. Aa,,.?. AR67"y -b 00 , X0 /I . PR df: ## rJ 0/- 75 .S - Phone Number Phone Number 9 741 cF-;4 Xz) Phone Number Email rHQ,s F,�?�T6 QrGo�✓�'TRUC,-FI Email co ^'t 1.8.10 J ' Ei a APPENDIX D DESCRITION OF WORK NL 1', n< } •9Nt Ha/yt yam i'Fl %Nk e,!" G`IQ C1� 17- 9 .rT-4k-C4 PUBLIC NOTIFICATION PLAN f7ARyVOo11 /Voi f �� DATES OF CONSTRUCTION HOURS OF CONSTRUCTION HOW WILL EXCAVATED SOIL BE USED? 0-,/ f-) %,r" i9c/i—b Go cie i .0 Q ATTACHMENTS: The following items shall be included as attachments: Vicinity Map ➢ Project Sign f ➢ Contact List ➢ Site Plan(s) Showing: 1. Disturbance Area 2. Revegetation Plan 3. Construction Fencing 4. Emergency Vehicle Access S. Construction Parking 6. Staging Areas 7. Trailers, material storage, waste management, etc. ➢ Sequencing Schedule ➢ Traffic Control and Emergency Access Plan ➢ Revegetation Plan ➢ Fugitive Dust Control Plan 1.8.10 ATTACHMENT #8 STARWOOD METROPOLITAN DISTRICT 0121 Stewart Drive Aspen Colorado 81611 970-925-939 TO: Pitkin County Building Department FROM: Heather Dresser, Secretary Starwood Metropolitan District DATE: June 25, 2013 RE: Water Service in Starwood Subdivision This is to confirm that the Starwood Metropolitan District will supply water to the residence on Tract R-55, 1115 South Starwood Drive, Starwood Subdivision, Aspen, Colorado that is owned by Laurence, Nanci and David Roth. Because the Starwood Metropolitan District. supplies all water to the residence and property, it does not, depend on a community well, and therefore, there is not a community well agreement. The Starwood Metropolitan District is an approved public water system and has sufficient water to supply the development, which includes Tract R-55, and the Starwood Metropolitan District agrees to do so. If you have any questions, please call me at 970-925-8939 or Starwood's Manager, Mark Asher, at 970-379-9878. CONTACT LIST Contractor - Rutgers Construction Phone - 970-925-8229 Project Manager - Jan Stenstadvold Phone - Site Supervisor - Phone - Architect - Contact - Phone - 970-309-2966 Chris Morrow 970-379-5810 CCY Matt Smith 970-927-4925 t' REEAR AND ALU. ALU. CAP '\ V, O 5.0' \ \ UTILTIY EASEMENT BK. 211 PG. 229 �OP SEPTIC TNIK.+-, 2 ST DROSS 0 LOWER IN LEVI f _ 9 GAR GARAGE FF=85be \ � Ls— \l' FIRE PIT ti T-� VI / 8837-3' STARNOOD TN SUBDIVISION O I & N ITE AABC 9,^ �A A � � r \ r O�y S21_I. 24'57"E • �' �. ... � VICINITY MAP R-56 R-55 T '1� SEPI% JMrI OF DISTURBANCE SEPTIC RE: SEPT ^ \\ir/ \\�, /Exlsrwcca+r'GUR,Tri/' �' \ 1 REBAR AND / ALU. C APS� t 1 L 1 1\ O n � � O Wim= 0 0 0 0 REB AR AND ALU. CAP ASSUMED ELEVATION= 8486.70" HATCHED MFA INDICATES PROPOSED —NIT, ENVELOPE AMMENDMENT z S= CGDi GROSS AREA a 1100 9F LOWER LEVEL - 8492 rssole MAIN LEVEL =850400 CONCRETE SEPTIC TNIK.+-, 2 ST DROSS 0 LOWER IN LEVI I _ 9 GAR GARAGE FF=85be \ Ls— \l' FIRE PIT T-� VI / 8837-3' I Y HOUSE IEA -7000 SF JEL IFF =8500 -F= 5512-8513 5 I tA.11LEv 100'-0"- SITE ELEV8512'-0" R-54 1 3 0 AVIOOOLNIT \ I _ 9 GAR GARAGE FF=85be \ T-� VI / 8837-3' I Y HOUSE IEA -7000 SF JEL IFF =8500 -F= 5512-8513 5 �A .T.O. GABLE, ll r \ REC<AR AND Alli. CAP S21_I. 24'57"E • �' �. ... � 18.37' R-58 rn"'^ ""TY DEVELOPMENT DIRECTOR APPROVAL The Starwood, R-55 Pitkin County, Site Plan and Activity Envelope amendmenf ie hereby approved this111Yof __ 2013, subjeof to terms and conditions pf Administrative De .I_ No. Recadad as R—pbon No. Co—" Dsvabpmard Dk.W --' �RNAWREGDR998'1 F�ATEAWREGOR�R'SC��F1 This Starwood, R-55 Palen Coumy, See Plan and Activity Envelope amendment has been _.PNd roc recording in the Office or the CW* and Recorder of Pitkin County, Colorado this _they of . 2013, in PMt Book_ at Page_ as Reception No, Clerk 8 Records OWNEfYS ACHNOWLEDGEMENT AND DISCLAIMER Applicant acmuMedges that helshe has been informed by Pitkin County of the existence of e'renvironmental hazard areas that might affect the property, any improvements, and the and occupancy thereof. The pro—ore of the Pitkin County Regulations do not in any way assure or Imply that areas outside of designated hazard areas will be irH from hazards, or that approved mitigation ...aures wiu gaurant.e the safety of any Property Owner. Sh ii Lot R-55, Pricer, County .�o�ld 2o#h 228 Mbland Avenue Post Dlflce Box 529 8awk Colorado 81821 970-927-4925 fax 970-927-8578 coyof oe@aeyamwlectsmm ROTH RESIDENCE STARWOOD, R-55, PITKIN COUNTY PID# 264335105003 DATE: 02.15.2013 DRAWN BY: MS CHECKED BY PROJECT NUMBER: 12020 ISSUE: PITKiN COUNTY SITE PLAN REVIEW REVISIONS: Rev. 1 6-52013 55 Starwood LLC Activity Envelope and Site Plan SCALE I— 2L' 0" A2.1 a VICINITY MAP RE BAR AND ALIJ. CAP (\( IRON PIPE R-45 "TIIITY EASEMENT 711 P0. 279 REBAR AND YPC I RIIIAR/ �. NOW 5V29"W NNo CAP i / "_- _ — — 2.05' R-34 2It I REABARCANND/j[/ / / � I I I AP R-54 00 ` \ o \ o 0TILY EASEMENT 11K. 1 Bk. 211 PG 229 R-56 OWNER'S ACKNOWLEDDEMEM AND OSCLAHAER Applicant acknowledges that he/she has been informed by Potion County of the existence of environmental hazard areas that might affect the property. any improvements, and the use and occupancy thereof. The provisions of the Pitkin County Regulations do not in any re way assuor Imply that areas outside of designated hazard areas will be ft..from hazards, or Nat spDro d mitipalion measures will gaurentes the safety of any propsdy Owner, Sta -55. Pit n County 228 Midland Avenue Post Office Box 529 Basalt, Colorado 81621 970-927-0925 fax 970927-8578 CcydNCe@CcyemhiteCls wm ROTH RESIDENCE STARWOOD, R-55, PITKIN COUNTY PID# 264335105003 DATE: 02.15.2013 DRAWN BY: Author CHECKED BY: Checker PROJECT NUMBER: 12020 - ISSUE: PITKIN COUNTY SITE PLAN REVIEW REVISIONS. Rev. 1 6-5-2013 55 Starwood LLC Activity Envelope and Site Plan SCALE –]G -L A2.1 b MWUMTY DEVELOPMENT DIRECTOR APPROVAL REB AR AND ALV. CAP This Starwood, R-55 Pilkin County. Sae Plan and Activity Envelope ameMment is hereby approved this day of2013, subject to terms and Conditions 20' 24'5T E of Administretiva Ded s'wn No. Recorded as Reception No. 18.37' Communily, Darns ant Dirader ry aRW AND RECORDER'H CERRFICATE –— aniandera has been TNR Starwood. R-55 Pitkin County, Site Plan and Activity En a ope m accepted for recording in the Office of the Clerk and Recorder of Piton County, Coforrada this _ day U 2013, in Plot Book_ at Page_ as Racaption No. Clark H Retarder OWNER'S ACKNOWLEDDEMEM AND OSCLAHAER Applicant acknowledges that he/she has been informed by Potion County of the existence of environmental hazard areas that might affect the property. any improvements, and the use and occupancy thereof. The provisions of the Pitkin County Regulations do not in any re way assuor Imply that areas outside of designated hazard areas will be ft..from hazards, or Nat spDro d mitipalion measures will gaurentes the safety of any propsdy Owner, Sta -55. Pit n County 228 Midland Avenue Post Office Box 529 Basalt, Colorado 81621 970-927-0925 fax 970927-8578 CcydNCe@CcyemhiteCls wm ROTH RESIDENCE STARWOOD, R-55, PITKIN COUNTY PID# 264335105003 DATE: 02.15.2013 DRAWN BY: Author CHECKED BY: Checker PROJECT NUMBER: 12020 - ISSUE: PITKIN COUNTY SITE PLAN REVIEW REVISIONS. Rev. 1 6-5-2013 55 Starwood LLC Activity Envelope and Site Plan SCALE –]G -L A2.1 b 228 Midand Avenue Post Office Box 529 Basalt, Colorado 81621 970-927-4925 fax 970.927-8578 ccyofficeacryarchitects. com ROTH RESIDENCE 1115 S. STARWOOD RD ASPEN, CO 81611 DATE: 07.15.2013 DRAWN BY: Author CHECKED BY: Checker PROJECT NUMBER: 12020 ISSUE: BUILDING PERMIT REVISIONS: O NORTH LOWER LEVEL - HOUSE SCALE Asindicaled A3.01 c IV 228 Midland Avenue Poet Office Box 529 Basalt Colorado 81621 9�0-927A925 fax 970-927-8578 ,Wofficeacoyamthitects com ROTH RESIDENCE 1115 S. STARWOOD RD. ASPEN, CO 81611 DATE: 07.15.2013 DRAWN BY: M.S. CHECKED BY: PROJECT NUMBER: 12020 ISSUE: BUILDING PERMIT REVISIONS: MAIN LEVEL - HOUSE SCALE A­dx,.tI,d amommmamumm .-_...._ &tiLr1FR RE -1— aEYtq,Inn.—`I:ALL RE. CIVIL r. LANDECAFE 228 Midland Avenue Post Office Box 529 Basalt, Colorado 81621 970-9274925 fax 970-927-8578 ccyoffice@ccyarchftects.com ROTH RESIDENCE 1115 S. STARWOOD RD. ASPEN, CO 81811 DATE: 07.15.2013 DRAWN BY: M.S. CHECKED BY: PROJECT NUMBER: 12020 ISSUE: BUILDING PERMIT REVISIONS: O NORTH PLANS - CDU SCALE al A3.10