HomeMy WebLinkAboutbocc.con.amended.052.18 K-1 2017-11-13 btf
pTKIN Pitkin County
Procurement Cover Sheet
COUNT
Please complete the Contract Cover Sheet when the contract/task order is complete and fully executed.
Return all Contract Cover Sheets and Contracts/Change Orders/Amendments/Task Orders to Procurement
Contract Information
Contract Number 052.2018 K-1
Project Name Airfield Pavement Rehabilitation - Phase 2
Contractor Kimley-Horn and Associates, Inc.
Budget Line Item 40451150.546500 $ 202,007.87
Additional Budget Line $
Item(s) $ _
(Please fully allocate New Contract Total)
$ 202,007.87
Procurement Method: Formal
Type: Services/Maintenance
Contract Start Date 6/1/2021
Contract End Date 12/31/2021
Contract Type Task Order
Retainage No
If this is a new contractor,please request they complete and submit to Finance a New Vendor Request Form.
Contact Information:
Department Airport
County Representative Matt Whitelock County Representative (970) 429-1880
Phone
Provide a brief description of the contract:
Task Order to provide design and construction services for the Airfield Pavement Rehabilitation Phase 2 project.
Contract Value Summary:
Original Contract Amount S 202,007.87
Previous Change Order/Amendment Amount S This Change order/Amendment amount
New Contract Total S 202,007.87
NOTE: Clerks Office will keep original documents in compliance with Colorado State Archives retainage
Master Service Agreement#: 052.18 Rev:2018-01-17 btf
TKIJ It
COUNT
— @-)� -
TASK ORDER
Task Order/Project Name: Airfield Pavement Rehabilitation- Phase 2
Task Order Number: K-1
Task Order Budget Line Item: 40451150.546500
OWNER: CONTRACTOR:
Pitkin County Kimley-Horn and Associates, Inc.
Matt Whitelock—Airport Robert Jones,PE
233 Airport Road, Suite A 16 Kearns Road, Suite 310 C/D
Aspen, CO 81611 Snowmass Village, CO 81615
Phone: (970)429-1880 Phone: (303)228-2313
matt.whitelock@aspenairport.com robert.jones@kimley-horn.corn
PROJECT NAME: AIRFIELD PAVEMENT REHABILITATION-PHASE 2
START DATE: June 1,2021
END DATE: December 31, 2021
The Program Management Services For The Aspen/Pitkin County Airport Capital Improvements Project
(the"Agreement") dated August 23, 2018 between the Board of County Commissioners of Pitkin County
(the "County") and Kimley-Horn and Associates, Inc. 16 Kearns Road, Suite 310 C/D Snowmass Village,
CO 81615 (the "Contractor"), shall include the following services.
1. Contractor's Obligations. Contractor shall provide design and construction in accordance with the
attached Scope of Work(Attachment A) and Fee Summary(Attachment B).
2. Compensation and Expenses, Invoicing, Payment and Offset. The Agreement is funded in part
through grant funds the County will receive through the FAA. The County shall compensate
Contractor for its services in accordance with the Project Budget and Schedule set out in Paragraph 1
of this Task Order. It is expressly understood and agreed that in no event will the total compensation
and reimbursement to be paid hereunder exceed the sum of Two Hundred Two Thousand and Seven
dollars and eighty-seven cents ($202,007.87) for all services rendered. By Task Order or Task Order
Amendment, the County and Contractor may reallocate the budget among project tasks if the total
budget amount remains unchanged. Contractor shall invoice for the project monthly based on hours
worked, with payment expected within thirty (30) days of invoice, but any payment by the County
may be offset by any amount the Contractor owes the County for any reason. Further, the County and
the Contractor agree as this Contract is federally funded, it is therefore subject to the requirements set
forth in Title 49 CFR Part 18.36.
1
Master Service Agreement#: 052.18 Rev:2018-01-17 btf
Any invoices not sent in the following manner may have payment delayed. All invoices for this Task
Order shall reference Task Order K-1 and Airfield Pavement Rehabilitation-Phase 2. Invoices shall be
sent electronically in PDF format to jennifer.mitchley@aspenairport.com.
3. Pitkin County's Obligations. Pitkin County shall administer this Task Order through a County
Representative. Matt Whitelock, Director of Security and Construction will manage the project as the
County's Representative. The services provided and products delivered by the Contractor under this
contract will be subject to review by the County's Representatives, or a designee, for compliance with
Contractor's obligations prior to final payment.
4. Formation of Task Order. This Task Order is issued in accordance with the provisions of the
Agreement. Contractor agrees to provide services subject to the terms of this Task Order and for the
avoidance of doubt this Task Order consists of the terms set out in the Agreement. In all other respects
the Agreement is in full force and effect and remains unchanged by this Task Order.
KIMLEY-HORN AND ASSOCIATES, INC.
Ili V l Jun-08-2021
Brian Valentine Date
Senior vice President
PITKIN COUNTY,COLORADO
RECOMMENDED FOR APPROVAL:
Mt-iftiOdc Jun-09-2021
Matt Whitelock Date
Director of Security and Construction
Vat& jA.rgatomug Jun-09-2021
Dan Bartholomew Date
Airport Director
DEPUTY COUNTY MANAGER:
rat, ttAdit u.Arr Jun-09-2021
Rich Englehart Date
Deputy County Manager
KHNVYT
2
i1'KIN
COUNT
•�
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
CONTRACTOR:
Kimley-Horn and Associates, Inc.
Robert Jones, PE—Project Manager
16 Kearns Road, Suite 310 C/D
Snowmass Village, CO 81615
Phone: (970) 429-8855
Robert.jones@kimley-horn.com
START DATE: June 1, 2021
END DATE: December 31, 2021
SCOPE OF WORK
Background
The Aspen-Pitkin County Airport(Client) has requested the development of this Professional
Consulting Services agreement from Kimley-Horn &Associates, Inc. (Consultant) for design
and construction of airfield pavement rehabilitation work at the airport. This project will provide
a second 2021 phase of runway, taxiway, and apron pavement rehabilitation. The scope of this
work includes asphalt pavement mill and overlay, isolated patching, crack routing, crack sealing,
and pavement marking in the rehabilitated areas.
The project will be funded with a FAA AIP grant and local funds. The estimated cost of
construction is $2,000,000.
These services will be provided in accordance with the following sections of the Scope of
Services in the Consultant's Master Services Agreement (MSA):
• Pre-Design Program Management Services
"b. Assist the Airport in identifying potential funding sources and in the completion and
execution of grant applications. "
• Program Management Services During Design
"k. Other design related program management services as requested."
• Pre-Construction Program Management Services
"h. Other pre-construction related program management services as requested. "
• Program Management Services During Construction
"b. Provide or assist Airport in Material Testing for related construction projects.
Page 1 of 8
41)41'KIN
COUNT
���
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
d. Manage Construction to FAA, CDOT, TSA and other Federal Agencies guidelines
and deadlines.
e. Attend Project progress meetings, review pay applications, and ensure compliance
with FAA Requirements.
f Assist in or facilitate needed and required inspection services.
g. Other construction related program management services as requested. "
Task 1-Project Administration & Coordination Services
This Task consists of administrative project related services to assist the Client with FAA grant
administration and project funding reimbursements,project scheduling, and Consultant
invoicing.
This Task consists of the following:
• Attendance at up to two (2) Project Coordination Meetings
• Prepare FAA Grant Application
• Assist with preparation of FAA Requests for Reimbursement
• Maintenance of a Project Schedule
• Monthly Invoicing
The Project Administration Services identified above will be provided throughout the project and
are based upon an assumed six (6)month Design and Construction schedule. The Consultant will
provide services as reasonably necessary throughout Design and Construction.
Task 2 - Scope and Fee Development
This task consists of Scope and Fee Development necessary to generate the project specific
services provided by the Consultant.
This Task consists of the following:
• Development of the Project Scope
• Development of the Project Schedule
• Development of a Fee Proposal
Page 2 of 8
iT'KIN
COUNT
— @Z--)C� �
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
Task 3 - FAA Grant Application, Coordination, and Management
The Consultant will prepare a FAA Grant Application and will assist the Client with
coordination of the grant request and subsequent Grant administration inclusive of preparation of
Requests for Reimbursement forms and preparing grant closeout documentation.
Task 4 - Construction Plans and Contract Documents
This Task includes one site visit to assess current pavement conditions and to map and estimate
the quantities of pavement distresses to be included in the project.
The Consultant will prepare Construction Plans and Contract Documents for use by the Client in
selection of a contractor to complete phase 2 rehabilitation of the runway, taxiway, and apron
pavements.
This Task consists of developing the following deliverables:
• Construction Plans
• Contract Documents & Technical Specifications
• Engineer's Opinion of Probable Construction Cost
• Engineer's Design Report in FAA format
This Task includes the preparation of the plans and documents outlined above and submittal to the
Client and FAA as follows:
• 95%Issued for Review("95%IFR")—The 95% Set Issued for Review Set documents will
consist of approximately 95% complete Construction Plans, Contract Documents &
Technical Specifications,Engineer's Opinion of Probable Construction Cost estimates,and
the Engineer's Design Report. These will be submitted to the Client and FAA for review.
• Issued for Bid ("IFB") - The Issued for Bid documents will include modifications to the
95%IFR documents and our completion our design to the 100%complete level. These IFB
documents will be provided to the Client for project advertisement and bidding.
• Issued for Construction ("IFC") - The Issued for Construction documents will include
addendum changes made during the bidding process, and any changes made during award
of the Contract for Construction. These IFC documents will be provided to the Client,FAA
and Contractor.
Construction Plans
The Consultant will provide detailed design and engineering services required to prepare
Construction Plans for the Project. The following plans are anticipated.
Page 3 of 8
iT'KIN
COUNT
— Q./.--)C� \
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
• Cover Sheet
• Project Layout Plan
• Survey Control Plan
• Construction Safety and Phasing Plan
• Demolition Plans and Details
• Pavement Rehabilitation Plans and Details
• Pavement Marking Plans and Details
Contract Documents and Technical Specifications
The Consultant will prepare contract documents and technical specifications for bidding and
construction of the project. These documents will describe the character and quality of the project
as to types and locations of materials. They also will detail construction phasing and scheduling
requirements, provide information on airport operations and include provisions regarding safety
during construction. The contract documents will include provisions required by the Client and
FAA for contracting purposes and consist of the following:
• Invitation for Bids
• Instruction to Bidders
• Bid Proposal
• Bid Documents
• Notice of Award
• Contract Agreement
• Performance and Payment Bonds
• Notice to Proceed
• Notice of Contractor's Settlement
• FAA Provisions
• General Provisions
• Special Provisions
• Technical Specifications
Where applicable the Consultant will utilize the Clients standard contract and bid documents or
prepare these from an agreed upon source. General and technical specifications will follow the
Client or FAA standards as appropriate.
Engineer's Opinion of Probable Construction Cost
The Consultant will prepare opinions of probable construction cost.
Page 4 of 8
i1'KIN
COUNT
tcy--)��
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
The Consultant will prepare an FAA format Engineer's Design Report that summarizes work
completed during the design process.
Submittal of the Construction Plans, Contract Documents and Specifications, Engineer's Opinion
of Probable Construction Cost, and Engineer's Design Report will consist of an electronic PDF
copy and two (2) hard copies to the Client, FAA, and Contractor as appropriate.
Deliverables:
• Construction Plans (95% IFR/IFB/IFC)
• Contract Documents and Specifications (95% IFR/IFB / IFC)
• Engineer's Opinion of Probable Construction Cost(95% IFR/IFB)
• Engineer's Design Report(95% IFR/IFB)
Task 5—Bidding Services
The Consultant will provide administrative bidding services to the Client to assist with
identification and selection of the Contractor.
This task consists of the following:
• Project Bidding Services
• Bidding Clarifications
• Bid Opening, Evaluation and Award
Advertise for Bids
The Consultant will assist the Client with publication of legal notices and provide notices to
appropriate trade papers and plan rooms as well as print and distribute plans and specifications to
prospective bidders.
Bidding Clarification
The Consultant will coordinate the bidding process and provide clarification of questions received
from Contractors during the bidding period. Bid clarification will be completed through a
maximum of two (2) Bid Addenda relative to Contractor questions.
Bid Opening, Evaluation and Award
The Consultant will assist the Client with the opening of bids, will review the bids for
completeness, will prepare a tabulation of each bid that checks for errors, and will provide a
recommendation of award. It is anticipated that the Client, with assistance from the Consultant,
will solicit formal approval of award from the FAA. After receiving approval to award, the
Page 5 of 8
41)41'KIN
COUNT
���
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
Consultant will prepare the Construction Contract,Notice of Award, and the Notice to Proceed for
use by the Client.
Deliverables:
• Construction and Contract documents will be prepared in electronic PDF format for use as
bidding packages issued to bidding contractors. Bidding packages are anticipated to consist
of one(1) 11 x 17 copy of the Construction Documents and associated Contract Documents.
Additional bidding packages will be issued to the Client and FAA as reasonably requested.
Task 6—Construction Phase Services
The Consultant will provide construction phase services to the Client for this project. The scope
of this task will consist of fulltime construction observation (25 days), response to contractor
questions, observation reporting, and providing clarification of our documents as requested by the
Client or Contractor during the construction period.
This task consists of the following:
• Review of Material Submittals
• Provide Clarification of Construction Plans and Contract Documents
• Conduct a Pre-Construction Meeting
• Provide 25 days of Construction Observation (inclusive of travel)
• Review Contractor Pay Requests
• Conduct a Final Inspection and Prepare a Punchlist for Corrective Work
• Prepare Record Drawings
• Coordinate Construction Close-out with the FAA
The Consultant will coordinate and perform the following as part of this Task:
• Review Proposals, Shop Drawings, and Samples. Review and take appropriate action in
respect to Proposals, Shop Drawings, Samples and other data which the installing
Contractor is required to provide. The Consultant's review of all shop drawings, samples
and proposals shall be for general conformance with the requirements. Such review will
not relieve the Contractor from its responsibility for performance, nor is such a review a
guarantee that the work covered by the shop drawings, samples and proposals is free of
errors, inconsistencies or omissions.
• Correspondence and Communications. Coordinate written communication among the
Contractor, Consultant, and County during construction. The Consultant shall initiate
communication regarding matters important to the County, including items that could
have an impact on project costs, contract time, or require changes to the contract
Page 6 of 8
4)i1'KIN
COUNT
t- )��
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
documents. The Consultant will also advise the County and provide recommendations to
the County for written communication between the County and Contractor.
• Resident Project Representative (RPR). The Consultant will provide an RPR to observe
and monitor project construction,provide escort as needed, and coordinate with airport
staff The RPR is provided for the purpose of monitoring progress, determining if the
work generally conforms to the contract for construction, and assuring quality of
installation.
• Observation of Work, Rejection of Defective Work, and Material Testing. The RPR shall
make routine observations of the Work in progress. The RPR shall report to the Engineer
when it is believed that any work is unsatisfactory, faulty and defective, has been
damaged, or does not meet the requirements of any inspection, test or required approval.
• Project Records. The Consultant shall maintain a record of general observations, specific
observations, and relevant decisions made on the project. As well, the RPR shall monitor
and record quantities for preparing monthly estimates for progress payments to the
Contractor. The Consultant shall also review Contractor certified payroll and perform
labor standards interviews.
• Certificates, Maintenance and Operational Manuals. The Consultant shall verify that all
necessary certificates and/or maintenance and operation manuals are furnished by the
Contractor to the Client.
• Punchlist and Final Inspection. The Consultant shall assist in the performance of progress
walk throughs, the drafting and development of a project punch list, Final Inspections,
and verification that any and all items detailed on those punch lists are completed or
corrected as it concerns final acceptance. Recommendations and punch list items status
shall be conveyed to the Client as well as any recommendations concerning acceptance.
The RPR's observation of the work is not an exhaustive observation of all work performed by
the Contractor. The RPR's observations will not relieve the Contractor from responsibility for
performing the work in accordance with the contract for construction, and the Consultant shall
not assume liability in any respect for the construction of the project. The Consultant shall not be
responsible for the Contractor's means, methods, techniques, equipment choice and usage,
sequence, schedule, safety programs, or safety practices, nor shall the Consultant be responsible
for the Contractor's failure to perform in accordance with the contract documents. The
Consultant neither guarantees the performance of the Contractor, nor assumes responsibility for
any Contractor's failure to perform its work in accordance with the Contract Documents.
Page 7 of 8
iirKIN
COUNT
- •�
SCOPE OF WORK AND FEE SUMMARY
Task Order K-1 —Airfield Pavement Rehabilitation
Should the Consultant discover or believe that any work by the Contractor is defective or not
conforming to the Contract for Construction or applicable rules and regulations, the Consultant
shall bring this to the attention of the Contractor and the County.
Task 7- Close-Out Documents
The Consultant shall prepare Record Drawings based on the redline drawings from the Contractor
and drawing changes generated by the RPR during construction. The Consultant shall also prepare
a Final Construction Report in FAA format that summarizes project construction.
Deliverables:
• Electronic AutoCAD Record Drawings will be submitted to the Client and FAA. The Final
Construction Report will be submitted in electronic PDF format to the Client and FAA.
SCHEDULE
The Consultant will provide the services described as expeditiously as possible on a schedule
agreed to by the Client.
FEE
The scope of services described herein shall be performed on a lump sum basis of$202,000.
This lump sum amount is intended to cover all applicable labor and expense costs.
Individual task amounts are provided for budgeting purposes only. Kimley-Horn reserves the
right to reallocate amounts among labor and expense tasks as necessary.
This project shall be billed monthly on a percent complete basis according to our then-current
rates.
The attached Fee Summary Spreadsheet shows the basis for our lump sum fee.
KH6rT
11
Page 8 of 8
Fee Estimate Summary-Kimley-Horn and Associates,Inc
Contract Number:052.2018(Pitkin County,Co/Aspen/Pitkin County Airport)
Project Name:Program Management Services
Contractor:Kimley-Horn and Assocaites,Inc.
Task Order Name:Airfield Pavement Rehabilitation-Phase 2
Task Order Number:K-1
Salary and Expenses Hours by Classification TOTAL
Task Description Senior Total Labor
Professional Analyst Tech Support Support Staff Total Hours
Professional II Cost
Task 1-Project Administration and Coordination 1 6 20 6 1 1 8 40
Subtotal-Hours I 6 20 6 I 0 I 8 40 S 2,19760
i i — —
Task 2-Scope and Fee Development
Development of Project Scope 1 8 2 11 $ 621.55
Development of Project Schedule 1 2 2 5 $ 286.15
Development of Fee Proposal 1 4 2 7 $ 386.35
Subtotal-Hours 3 14 2 0 4 23 $ 1,294.05
Task 3-FAA Grant Application,Coordination,and Management
Prepare FAA Grant Application 1 2 6 1 10 $ 477.20
FAA Grant Administration 1 6 3 10 $ 535.20
FAA Grant Closeout Documentation 1 2 2 2 7 $ 348.65
Subtotal-Hours 3 10 8 0 6 27 $ 1,361.05
Task 4-Construction Plans and Contract Documents
Construction Plans 2 20 60 40 4 126.0 $ 5,169.30
Contract Documents and Technical Specifications 2 15 40 6 63.0 $ 2,844.80
Opinion of Probable Construction Cost 4 10 20 10 2 46.0 $ 2,127.60
Engineers Design Re ort 2 10 30 8 50.0 $ 2,213.60
Subtotal-Hours 10 55 150 50 20 285.0 $ 12,355.50
sls
Task 5-Bidding Services
Project Bidding Services 2 4 2 8 $ 339.90
Bidding Clarifications 1 6 10 4 21 $ 965.95
Bid O enin,Evaluation,and Award 1 4 4 2 11 $ 546.15
Subtotal-Hours 18 0 8 40 $ 1,852.00
Task 6-Construction Phase Services
Review Material Submittals 1 4 4 1 10 $ 514.90
Provide Clarification of Construction Plans/Contract Docs 2 20 22 $ 1,353.30
Conduct Pre-Construction Meeting 6 15 1 22 $ 1,445.15
Provide Construction Observation 8 40 250 298 $ 13,048.70
Review Contractor Pay Requests 6 4 2 12 $ 575.10
Conduct Final Inspection&Prepare Punchlist _ 4 8 8 20 $ 1,144.60
I Subtotal-Hours I 21 I 93 I 266 I 0 I 4 384 $ 18,081.75
Task 7-Close-Out
Prepare Record Drawings 1 6 10 20 2 39 $ 1,550.45
Final Construction Report 1 8 20 10 8 47 $ 1,931.55
Subtotal-Hours 2 14 30 30 10 86 $ 3,482.00
TOTAL Hours 0 47 218 I 480 I 80 60
Basic Average Hourly Rate $ - $ 88.65 $ 58.80 $ 39.95 $ 32.35 $ 31.25
Direct Salary Cost $ - $ 4,166.55 $ 12,818.40 $ 19,176.00 $ 2,588.00 $ 1,875.00
Labor&Gen.Admin.Overhead 195.24% $ - $ 8,134.77 $ 25,026.64 I$ 37,439.22I$ 5,052.81 $ 3,660.75
Subtotal Salary $ - $ 12,301.32 $ 37,845.04 $ 56,615.22 $ 7,640.81 $ 5,535.75
Profit(Labor Costs) 15% $ - $ 1,845.20 $ 5,676.76 I$ 8,492.28 I$ 1,146.12 $ 830.36
Salary Expenses-Subtotal $ 137,928.87
Non-Salary Expenses
Hotel Nights 35 Nights $ 215.00 $ 7,525.00
Car Rental&Gas 35 Days $ 75.00 $ 2,625.00
Days $ -
Days Per Diem 35 Days $ 64.00 $ 2,240.00
Other Transportation Costs 2050 Miles $ 0.58 $ 1,189.00
Shipping/Misc. 1 LS $ 1,000.00 $ 1,000.00
Sub-consultants Contract Value Contract type Subtotal
Survey $16,500.00 $ 16,500.00
CIA Material Testing $33,000.00 $ 33,000.00
I NonSalary Expenses-Subtotal $ 64,079.00I
(TOTAL $ 202,007.87I
DocuSign
Certificate Of Completion
Envelope Id:6F1D21AE6A184945BFCCC7C2728FFEC2 Status:Completed
Subject:052.18 K-1 Kimley Horn Airfield Pavement Rehab Task Order
Source Envelope:
Document Pages: 12 Signatures:4 Envelope Originator:
Certificate Pages:5 Initials:0 Jennifer Mitchley
AutoNav: Enabled 530 East Main Street
Envelopeld Stamping: Disabled Suite 203
Time Zone: (UTC-07:00)Mountain Time(US&Canada) Aspen,CO 81611
jennifer.mitchley@aspenairport.com
IP Address:216.237.67.7
Record Tracking
Status:Original Holder:Jennifer Mitchley Location: DocuSign
6/7/2021 10:00:14 AM jennifer.mitchley@aspenairport.com
Signer Events Signature Timestamp
Brian Valentine Sent:6/7/2021 10:36:13 AM
brian.valentine@kimley-horn.com brim' VaWIM Viewed:6/8/2021 10:18:16 PM
Senior Vice President Signed:6/8/2021 10:24:40 PM
Security Level: Email,Account Authentication
(None) Signature Adoption: Pre-selected Style
Using IP Address:208.127.242.42
Electronic Record and Signature Disclosure:
Accepted:6/8/2021 10:18:16 PM
ID:ad814a36-069d-40e8-8037-b6e83d2438d3
Company Name:Pitkin County,Colorado
Matt Whitelock 1�'� Sent:6/8/2021 10:24:44 PM
matt.whitelock@aspenairport.com /',' ku6C Viewed:6/9/2021 8:58:13 AM
Director of Security and Construction Signed:6/9/2021 8:59:26 AM
Security Level: Email,Account Authentication
(None) Signature Adoption: Pre-selected Style
Using IP Address: 174.198.128.12
Signed using mobile
Electronic Record and Signature Disclosure:
Accepted:6/9/2021 8:58:13 AM
ID:2707713b-9789-403b-93a6-d4047fb5961 a
Company Name:Pitkin County,Colorado
Dan Bartholomew '�� -" Sent:6/9/2021 8:59:28 AM
Dan.Bartholomew@aspenairport.com V bctitLAlott-lA/ Viewed:6/9/2021 9:03:04 AM
Airport Director Signed:6/9/2021 9:05:57 AM
Security Level: Email,Account Authentication
(None) Signature Adoption: Pre-selected Style
Using IP Address:65.38.144.66
Electronic Record and Signature Disclosure:
Accepted:6/9/2021 9:03:04 AM
ID:776176c3-83f9-456a-bc20-e50b2114dfff
Company Name:Pitkin County,Colorado
Rich Englehart �,� Sent:6/9/2021 9:06:01 AM
rich.englehart@pitkincounty.com K fa"'D"tL4"' Viewed:6/9/2021 10:17:09 AM
Deputy County Manager Signed:6/9/2021 10:17:21 AM
Pitkin County
Security Level: Email,Account Authentication Signature Adoption: Pre-selected Style
(None) Using IP Address:65.38.144.66
Signer Events Signature Timestamp
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Accounts Payable COPIED Sent:6/9/2021 10:17:24 AM
AP@pitkincounty.com
Accounts Payable
Pitkin County
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Evelyn Cruz COPIED Sent:6/9/2021 10:17:24 AM
evelyn.cruz@aspenairport.com
Aspen/Pitkin County Airport
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Accepted:4/12/2021 2:10:41 PM
ID:c1bc55da-6ec1-49bb-8432-a0d7de7ce362
Company Name:Pitkin County,Colorado
Pitkin County Procurement COPIED Sent:6/9/2021 10:17:24 AM
procurement@pitkincounty.com
Procurement
Pitkin County
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 6/7/2021 10:36:13 AM
Certified Delivered Security Checked 6/9/2021 10:17:09 AM
Signing Complete Security Checked 6/9/2021 10:17:21 AM
Completed Security Checked 6/9/2021 10:17:24 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
Electronic Record and Signature Disclosure created on:3/20/2020 3:28:13 PM
Parties agreed to:Brian Valentine, Matt Whitelock,Dan Bartholomew, Evelyn Cruz
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Pitkin County(we, us or Pitkin County)may be required by law to provide
you with certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically when we send you documents for
electronic signature.
Acknowledging your Access, Intent, and Consent to Receive and Sign Materials
Electronically
To confirm that you can access this information electronically, which will be similar to other
electronic notices and disclosures that we will provide to you,please verify that you were able to
read this electronic disclosure and that you also were able to print on paper or electronically save
this page for your future reference and access or that you were able to e-mail this disclosure and
consent to an address where you will be able to print on paper or save it for your future reference
and access. Further, if you consent to receive notices and disclosures exclusively in electronic
format on the terms and conditions described above,please let us know by clicking the 'I agree'
button below.
By checking the 'I Agree' box, I confirm that:
• I am establishing my intent to be bound to the transaction, and indicating that I am fully
aware of the purpose for which the signature is being provided.
• I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
• I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
• Until or unless I notify Pitkin County as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgments, and other documents that are required to be provided or made
available to me by Pitkin County during the course of my relationship with you.
Signing Documents without a Pitkin County DocuSign Account:
Pitkin County may not require all document signers to be authorized users of the Pitkin County
DocuSign Account. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to these terms and
conditions, please confirm your agreement by clicking the 'I agree'button at the bottom of this
document. When you don't have a DocuSign account, you will be provided the opportunity to
agree to the Legal Disclosure each time you open an "envelope" for signing, at this time, you can
download and retain this disclosure. Pitkin County will forward completed documents that
you've reviewed, processed or signed via email. Should you require copies of these signed
documents (e.g., if they get deleted from your email account) you should request those
documents from Pitkin County under the Colorado Open Records Act by contacting the Pitkin
County custodian who sent you the document for signature.
Signing Documents with a Pitkin County DocuSign Account:
Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to these terms and conditions,please
confirm your agreement by clicking the 'I agree'button at the bottom of this document.
Getting paper or electronic copies
At any time, you may request from us a paper or electronic copy of any record provided or made
available electronically to you by us. For such copies, as long as you are an authorized user of
the DocuSign system you will have the ability to download and print any documents we send to
you through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper or
electronic copies of any such documents from our office to you, you may be charged a per-page
fee. You may request delivery of such paper or electronic copies from us by following the
procedure described below.
Withdrawing your consent
If you are an authorized DocuSign Account holder, you can decide to receive notices and
disclosures from us electronically, you may at any time change your mind and tell us that
thereafter you want to receive required notices and disclosures only in paper format. Described
below is the process for informing us of your decision to receive future notices and disclosure in
paper format and also how to withdraw your consent to receive notices and disclosures
electronically.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign user account to receive required notices and consents electronically from us or to sign
electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgments, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process,please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Pitkin County:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to Helpdesk@provelocity.com
To advise Pitkin County of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at Helpdesk@provelocity.com and
in the body of such request you must state: your previous e-mail address, your new e-mail
address .
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper or electronic copies from Pitkin County
To request delivery from us of paper or electronic copies of the notices and disclosures
previously provided by us to you electronically, you should request those documents from Pitkin
County under the Colorado Open Records Act by contacting the Pitkin County custodian who
sent you the document for signature.
To withdraw your consent with Pitkin County
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an e-mail to Helpdesk@provelocity.com and in the body of such a request, you
must state your e-mail, full name, Postal Address, telephone number, and account
number.