HomeMy WebLinkAboutbocc.con.002.20 C-6 2019-12-17 CDD
T K I N Pitkin County
COUNT Procurement Cover Sheet
Please complete the Contract Cover Sheet when the contract/task order is complete and fully executed.
Return all Contract Cover Sheets and Contracts/Change Orders/Amendments/Task Orders to Procurement
Contract Information
Contract Number 002.20 C-6
Project Name Redstone Park Survey and Design
Contractor SGM Inc
Budget Line Item 11836360.531000.10027 $ -
$ -
Additional Budget Line $ _
Item(s) $ _
(Please fully allocate New Contract Total)
$ —
Procurement Method: Formal
Type: Services/Maintenance
Contract Start Date 9/18/2020
Contract End Date 3/31/2021
Contract Type Task Order
Retainage No
If this is a new contractor, please enter the New Vendor information into Munis for workflow approval.
Contact Information:
Department Open Space & Trails
County Representative Jessie Young County Representative (970)429-6169
Phone
Provide a brief description of the contract:
Task order to provide survey and design at Redstone Park
Contract Value Summary:
Original Contract Amount $ 54,000.00
Previous Change Order/Amendment Amount $This Change order/Amendment amount $New Contract Total $ 54,000.00
Master Service Agreement#: 002.20 Rev:2018-10-10 btf
jKIJ
COUNT
TASK ORDER
Task Order/Project Name: Redstone Park Survey and Design
Task Order Number: 002.20 C-6
Task Order Budget Line Item: 11836360.531000.10027
OWNER: CONTRACTOR:
Pitkin County SGM Inc.
Jessie Young—Open Space and Trails Mike Fowler/Mark Frymoyer
530 East Main St. Suite 202 118 West 6th St., Suite 200
Aspen, CO 81611 Glenwood Springs, CO 81601
Phone: (970)429-6130 Phone: (970) 384-9075
jessie.young@pitkincounty.com mikef@sgm-inc.com/markf@sgm-inc.com
PROJECT NAME: REDSTONE PARK SURVEY AND DESIGN
START DATE: September 18, 2020
END DATE: March 31, 2021
The On-Call Engineering Services(the"Agreement")dated January 1,2020 between the Board of County
Commissioners of Pitkin County (the "County") and SGM Inc. 118 West 6th St., Suite 200 Glenwood
Springs, CO 81601 (the "Contractor"), shall include the following services.
1. Contractor's Obligations. Contractor shall provide the work as described below:
A. Project Description
This project consists of planning and landscape architecture design work and existing conditions
surveying of Redstone Park. The Survey will cover the three parcels that comprise Redstone Park
including utility locates, as well as river cross section data collection and floodplain topographic data
collection. The final survey deliverable will be a map and cad file that can be used for future design
of park improvements and hydraulic modeling of channel and bank improvements for a floodplain
development permit. The park design deliverables are outlined below in the work plan to include
final design for the entirety of the park with bid level construction documents for the portions of the
park above the levee.
B. Work Plan
Task 1 —Existing Conditions Map
Show 1' topography, all existing improvements, trees, current edge of water, floodplain per FEMA
mapping on and adjacent to the properties. River and floodplain survey as needed to develop future
hydraulic modeling for changes to the river bank/levee along Redstone Park. Property lines, existing
1
Master Service Agreement#: 002.20 Rev:2018-10-10 btf
encumbrances of record also shown. Underground utilities will be located by Roaring Fork Utility
Locators. SGM surveyors will survey the utility line locates for the existing conditions map.
• Total Fee for Task- $10,500.
Task 2 —Park Improvements Design (DHM)
DHM will take ideas developed as part of the Redstone Parks and Open Space Management Plan, as
well as any new ideas that fit into the context of Historic Redstone brought forward by DHM or the
steering committee, to;
1. Create a final design direction for the entirety of the park including on-river improvements
on and below the levee
2. Develop bid ready construction documents for the portions of the park above the levee
DHM will work collaboratively with the steering committee (estimated 10-15 members), stakeholder
groups, and OST Staff.
This phase of the Redstone Park Design will include programming/conceptual design for all of
Redstone Park, and final design with bid ready construction documents for the `above levee'
portions of the park. Phase I includes park area from the crest of the levee east to the edge of
Redstone Boulevard, and for convenience will be referred to as the `upland area.' A Phase II bid
ready construction set will be developed for the on and below levee portions of the park when
budget becomes available, but this detailing and documentation is excluded from this task order. The
plan will build on the concepts generated in the 2010 Redstone Parks and Open Space Management
plan, which focused on refining the pavilion and woodland grove concepts (on the Meredith parcel)
and create an access plan. Detailed tasks and work items are identified on the attached spreadsheet.
• Total Fee for Task- $34,000
Task 3 —Structural and Civil Engineering (SGM)
Foundation design and details for park structures. Allowance for incidental civil and utility design.
Allowance for ongoing project management of task order(coordination, invoices, etc.).
• Total Fee for Task- $6,500
Task 4—Irrigation Design (Hydrosystems-KDI)
Schematic and Final irrigation design and plans.
• Total Fee for Task- $3,000
C. OST Will Provide the Following Items:
• Memorial inventory, image collection, condition reporting.
• Summer 2020 brainstorming/visioning survey responses.
• Assistance with organizing the steering committee and meetings with other community
groups as needed, meeting facilitation and documentation.
o OST will manage venue logistics, steering committee communication,refreshments, etc.
o Design team(DHM)will provide graphic materials (maps, images, design plans) for the
meetings.
o OST and DHM will collaborate on meeting agenda
o Design team(DHM)to attend 4 steering committee meetings.
o Design team(DHM)to participate in two community group meetings (e.g. RCA, OSTB).
o OST will compile and distribute notes/meeting outcomes as necessary.
2
Master Service Agreement#: 002.20 Rev:2018-10-10 btf
• Assistance with collecting public input on the draft plan, including distribution of materials
to the public, receiving public feedback, compiling and summarizing feedback.
• Organize Application Package for Location and Extent Review prior to construction.
• Geotechnical soils evaluation(if needed for structures).
D. Assumptions:
• Planned upland park improvements (included in this scope)will not negatively affect the
floodway capacity and will not necessitate additional permitting or modeling
• Phase I technical documentation permitting will be possible with a Letter of No Rise related
to work on the flood plain
• Full grading of project site will not be necessary—assumes grading limited to specific areas
around the top of levee,pavilion/park entry/playground, and Meredith parcel
• Irrigation system includes laterals/zones/head layout only (re-use controller, POC equipment)
• Irrigation specifications will be per OST standards/preferences, and identified by reference
on the irrigation drawings
• Irrigation designer will not need to visit the site
• New or permanent light fixtures will be limited to existing electrical service capacity
• Water/sewer services will not be replaced or extended
• Playground equipment will be re-used(if moved/altered) (e.g. scope does not include custom
design of playground features).
• Estimate of cost will be developed by plan takeoffs and OST/SGM/DHM team's unit cost
database and provided at Draft Plan; updated at Final Bid Plans
E. Exclusions and Limitations
• Subsurface Utility Engineering (SUE) investigation
• Mechanical, Electrical or Plumbing engineering
• Stamped civil site drawings (electrical routing to be shown on site plan and permitted by sub-
contractor)
• Construction documentation detailing on-levee, river-bank, and river-channel improvements
• Digital modeling (Civil3D or sketchup)
• Geotechnical investigation and engineering
• ROW or access engineering/permitting
• Detailed cut/fill calculations (estimate volumes will be provided by average area method)
• Custom shelter/pavilion design(scope presumes prefabricated pavilion)
• River modeling/permitting
• Wetlands investigation/mapping/permitting
• Specifications manual (specification notes to be provided on drawings)
• Construction administration/observation
2. Compensation and Expenses, Invoicing, Payment and Offset. The County shall compensate
Contractor for its services in accordance with the Project Budget and Schedule set out in Paragraph 1
of this Task Order. It is expressly understood and agreed that in no event will the total compensation
3
Master Service Agreement#: 002.20 Rev:2018-10-10 btf
and reimbursement to be paid hereunder exceed the sum of fifty four thousand dollars and zero cents
($54,000.00) for all services rendered. By Task Order or Task Order Amendment, the County and
Contractor may reallocate the budget among project tasks if the total budget amount remains
unchanged. Contractor shall invoice for the project monthly based on hours worked, with payment
expected within thirty (30) days of invoice, but any payment by the County may be offset by any
amount the Contractor owes the County for any reason.
Any invoices not sent in the following manner may have payment delayed. All invoices for this Task
Order shall reference Task Order 002.20 C-6 and Redstone Park Survey and Design. Invoices shall be
sent electronically in PDF format to kim.arensdorf@pitkincounty.com.
3. Pitkin County's Obligations. Pitkin County shall administer this contract through a County
Representative. Jessie Young, Senior Planner will manage the project as the County's Representative.
The services provided and products delivered by the Contractor under this contract will be subject to
review by the County's Representatives, or a designee, for compliance with Contractor's obligations
prior to final payment.
4. Formation of Task Order. This Task Order is issued in accordance with the provisions of the
Agreement. Contractor agrees to provide services subject to the terms of this Task Order and for the
avoidance of doubt this Task Order consists of the terms set out in the Agreement. In all other respects
the Agreement is in full force and effect and remains unchanged by this Task Order.
SGM INC.
�lt�c rota' Sep-29-2020
Mike Fowler Date
Project Manager
PITKIN COUNTY, COLORADO
Sep-29-2020
Jessie Young Date
Senior Planner - Open Spaceand Trails
4
Redstone Park Update
Submitted by:DHM Design
DRAFT 1 August 28,2020
Scope to be complete by June 30,2021 DHM Design SGM Engineering Survey Irrigation
Task Task/Item Description PIC Project Project PM Structural Senior Lump Lump Total
(Jaynes) Manager Designer (Fowler) Engineer Engineer Sum Sum
1.0 Project Start Up/Visioning/Brainstorming(October)
Existing conditions survey(SGM) 1
Project team kick-off,team review of management plan,master plan and 2010 priorities. 2 3
Site visit and site evaluation/photo collection,memorial inventory/condition.Including
premiliniary ecological and engineering review(visual/anecdotal)of levee/river bank 4 4
condition and future access improvemnet opportunities.Identify specific areas for Steering
Committee(SC)feedback(eg,parking at Meridith parcel).
Develop and print materials for SC meeting#1:survey,aerial,photo image boards,park
and river bank character imagery.Compile pdfs of materials for distribution to steering 1 8
committee
Team meeting to prep for SC#1(agenda,goals,etc) 1 2
Steering Committee Meeting#1:Kick-off.Intro,calendar,site visit,review 2010 concepts
and priorities and management plan,review 2020 community feedback,establish goals, 4 4
discuss program and character.
Summarize outcomes of meeting and distribute notes to Steering Committee(OST) 1
PHASE 1 TOTAL HOURS 12 22 0 0 0 0 1 0 35
BILLING RATE $ 190 $ 120 $ 105 $ 166 $ 100 $ 100 $ 10,500 $
PHASE 1 TOTAL DOLLARS $ 2,280 $ 2,640 $ - $ - $ - $ - $ 10,500 $ - $ 15,420
2.0 Concept Design(October-mid November);Public Comment(December-January)
Conept design plan and updated character imagery(photos).Enlargements or alternatives 8 32
from SC#1 outcomes
Team review of draft concept(s) 1 1
Edits to conecpt(s)and prepare materials for SC#2 8
Steering Committee Meeting#2:Conceptual Design Discussion.Present programming,site
design options,design character/visual preference discussion.Select preferred 4 4
program/concept
Summarize outcomes of meeting and distribute notes to Steering Committee(OST) 1
Presentation to RCA(OST and DHM) 1 2
Modify preferred concept per results of the above(graphics)and release for public 2 8
comment
(Thanksgiving holiday,public comment period in December)
Steering committee meeting#3:Review public comment and modified plans.(end of 4 8
January)
PHASE 2 TOTAL HOURS 20 64 0 0 0 0 0 0 84
BILLING RATE $ 190 $ 120 $ 105 $ 166 $ 100 $ 100 $ - $
PHASE 2 TOTAL DOLLARS $ 3,800 $ 7,680 $ - $ - $ - $ - $ - $ - $ 11,480
3.0 Draft Plan Develo•ment/Presentation Februa
Develop Schematic Design package-site materials/planting plan,irrigation plan,details, 8 8 32
specification notes.Preliminary materials volumes
Schematic irrigation plan 1
Develop supporting(graphic)materials for SC#4,using SD products and refining prior 4 4
concept materials
Steering Committee#4:Draft Plan Review/recommendation for approval 4 4
OSTB presentation(OST/DHM) 1
RCA,HPC,Caucus presentations(OST)
PHASE 3 TOTAL HOURS 17 16 32 0 0 0 0 1 66
BILLING RATE $ 190 $ 120 $ 105 $ 166 $ 125 $ 153 $ - $ 1,500
PHASE 3 TOTAL DOLLARS $ 3,230 $ 1,920 $ 3,360 $ - $ - $ - $ - $ 1,500 $ 10,010
4.0 Final Bid Plans(end of February to mid March)
Develop 95%Bid Package -site materials/planting plan,irrigation plan,details, 8 8 24
specification notes(on drawing sheets)
Internal review period(including DHM/SGM QA/QC) 2 2
Finalize Bid Set(drawing package and quantities) 4 8 8
Final irrigation plans 1
Foundation design and details 16 4
Allowance for civil and electrical items 16
SGM Project Management for Task Order 8
PHASE 4 TOTAL HOURS 14 18 32 8 16 20 0 1 109
BILLING RATE $ 190 $ 120 $ 105 $ 166 $ 125 $ 153 $ - $ 1,500
PHASE 4 TOTAL DOLLARS $ 2,660 $ 2,160 $ 3,360 $ 1,328 $ 2,000 $ 3,060 $ - $ 1,500 $ 16,068
Total Hours 291.0
Total Dollars $ 52,978
Estimated Travel/Printing Expenses and Reimbursables at Direct Cost $ 500
Total Fee $53,478
Docu 5ir,..
• SECURED
Certificate Of Completion
Envelope Id:91094FD22C804655A110506CB9007094 Status:Completed
Subject:SGM I Pitkin County Contract 002.20 C-6 for Review and Signature
Source Envelope:
Document Pages:6 Signatures:2 Envelope Originator:
Certificate Pages:5 Initials:0 Pitkin County Procurement
AutoNav: Enabled 530 East Main Street
Envelopeld Stamping: Disabled Suite 203
Time Zone: (UTC-07:00)Mountain Time(US&Canada) Aspen,CO 81611
Procurement@PitkinCounty.com
IP Address:24.9.118.68
Record Tracking
Status:Original Holder:Pitkin County Procurement Location: DocuSign
9/29/2020 9:27:07 AM Procurement@PitkinCounty.com
Signer Events Signature Timestamp
Jessie Young Sent:9/29/2020 9:28:01 AM
jessie.young@pitkincounty.com Viewed:9/29/2020 9:32:05 AM
Senior Planner-Open Spaceand Trails Signed:9/29/2020 9:41:52 AM
Security Level: Email,Account Authentication
(None) Signature Adoption: Drawn on Device
Using IP Address:73.3.253.200
Electronic Record and Signature Disclosure:
Accepted:9/29/2020 9:32:05 AM
ID:c470114b-005e-4647-9edc-8338a54aa1a9
Company Name:Pitkin County,Colorado
Mike Fowler Sent:9/29/2020 9:41:54 AM
mikef@sgm-inc.com /kik rbWtt,Y Viewed:9/29/2020 9:42:21 AM
Project Manager Signed:9/29/2020 9:42:34 AM
Security Level: Email,Account Authentication
(None) Signature Adoption: Pre-selected Style
Using IP Address:208.72.68.35
Electronic Record and Signature Disclosure:
Accepted:9/29/2020 9:42:21 AM
ID:d2e0dd58-fa6a-4158-bbca-0eb1778b8b7e
Company Name:Pitkin County,Colorado
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Carbon Copy Events Status Timestamp
Pitkin County Procurement COPIED Sent:9/29/2020 9:42:38 AM
procurement@pitkincounty.com Resent:9/29/2020 9:42:44 AM
Procurement Viewed: 1/26/2021 4:07:49 PM
Pitkin County
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Accounts Payable COPIED Sent:9/29/2020 9:42:39 AM
AP@pitkincounty.com
Accounts Payable
Pitkin County
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Kim Arensdorf COPIED Sent:9/29/2020 9:42:40 AM
kim.arensdorf@pitkincounty.com
Administrative Specialist
Security Level: Email,Account Authentication
(None)
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 9/29/2020 9:28:01 AM
Certified Delivered Security Checked 9/29/2020 9:42:21 AM
Signing Complete Security Checked 9/29/2020 9:42:34 AM
Completed Security Checked 9/29/2020 9:42:40 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
Electronic Record and Signature Disclosure created on:3/20/2020 3:28:13 PM
Parties agreed to:Jessie Young, Mike Fowler
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Pitkin County(we, us or Pitkin County)may be required by law to provide
you with certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically when we send you documents for
electronic signature.
Acknowledging your Access, Intent, and Consent to Receive and Sign Materials
Electronically
To confirm that you can access this information electronically, which will be similar to other
electronic notices and disclosures that we will provide to you,please verify that you were able to
read this electronic disclosure and that you also were able to print on paper or electronically save
this page for your future reference and access or that you were able to e-mail this disclosure and
consent to an address where you will be able to print on paper or save it for your future reference
and access. Further, if you consent to receive notices and disclosures exclusively in electronic
format on the terms and conditions described above,please let us know by clicking the 'I agree'
button below.
By checking the 'I Agree' box, I confirm that:
• I am establishing my intent to be bound to the transaction, and indicating that I am fully
aware of the purpose for which the signature is being provided.
• I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
• I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
• Until or unless I notify Pitkin County as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgments, and other documents that are required to be provided or made
available to me by Pitkin County during the course of my relationship with you.
Signing Documents without a Pitkin County DocuSign Account:
Pitkin County may not require all document signers to be authorized users of the Pitkin County
DocuSign Account. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to these terms and
conditions, please confirm your agreement by clicking the 'I agree'button at the bottom of this
document. When you don't have a DocuSign account, you will be provided the opportunity to
agree to the Legal Disclosure each time you open an "envelope" for signing, at this time, you can
download and retain this disclosure. Pitkin County will forward completed documents that
you've reviewed, processed or signed via email. Should you require copies of these signed
documents (e.g., if they get deleted from your email account) you should request those
documents from Pitkin County under the Colorado Open Records Act by contacting the Pitkin
County custodian who sent you the document for signature.
Signing Documents with a Pitkin County DocuSign Account:
Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to these terms and conditions,please
confirm your agreement by clicking the 'I agree'button at the bottom of this document.
Getting paper or electronic copies
At any time, you may request from us a paper or electronic copy of any record provided or made
available electronically to you by us. For such copies, as long as you are an authorized user of
the DocuSign system you will have the ability to download and print any documents we send to
you through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper or
electronic copies of any such documents from our office to you, you may be charged a per-page
fee. You may request delivery of such paper or electronic copies from us by following the
procedure described below.
Withdrawing your consent
If you are an authorized DocuSign Account holder, you can decide to receive notices and
disclosures from us electronically, you may at any time change your mind and tell us that
thereafter you want to receive required notices and disclosures only in paper format. Described
below is the process for informing us of your decision to receive future notices and disclosure in
paper format and also how to withdraw your consent to receive notices and disclosures
electronically.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign user account to receive required notices and consents electronically from us or to sign
electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgments, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process,please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Pitkin County:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to Helpdesk@provelocity.com
To advise Pitkin County of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at Helpdesk@provelocity.com and
in the body of such request you must state: your previous e-mail address, your new e-mail
address .
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper or electronic copies from Pitkin County
To request delivery from us of paper or electronic copies of the notices and disclosures
previously provided by us to you electronically, you should request those documents from Pitkin
County under the Colorado Open Records Act by contacting the Pitkin County custodian who
sent you the document for signature.
To withdraw your consent with Pitkin County
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an e-mail to Helpdesk@provelocity.com and in the body of such a request, you
must state your e-mail, full name, Postal Address, telephone number, and account
number.