HomeMy WebLinkAboutbocc.con.008.2019 A-7 2017-11-13 btf
pTKIN Pitkin County
CouNTit Procurement Cover Sheet
Please complete the Contract Cover Sheet when the contract/task order is complete and fully executed.
Return all Contract Cover Sheets and Contracts/Change Orders/Amendments/Task Orders to Procurement
(procurement apitkincounty.com). If not already completed, any contracts$50,000 and over will be routed for signatures
to County Manager and Attorney's Office(if required)by Procurement.
Contract Information
Contract Number 008.2019 A-7
Project Name SMP Irrigation Pond&Riparian Restoration Plan
Contractor Peak Ecological Services,LLC
Budget Line Item 118.57.02294.82841 $ 28,299.80
Additional Budget Line $
Item(s) $
(Please fully allocate New $
Contract Total) $ 28 299.80
Contract Start Date 3/1/2019
Contract End Date 12/31/2019
Renewals Available? Yes ❑X No❑
Retainage Yes$ or % No/1
If this is a new contractor,please request they complete and submit to Finance a New Vendor Request Form.
Contact Information:
Department Open Space and Trails
County Gary Tennenbaum&Lindsey County Representative (970)920-5224
Representative Utter Phone
Provide a brief description of the contract:
Sky Mountain Park Brush Creek Irrigation Ponds and Riparian Habitat Restoration
Contract Value Summary:
Original Contract Amount $28,299.80
Previous Change Order/Amendment Amount $ 0.00
This Change order/Amendment amount $0.00
New Contract Total $28,299.80
Procurement Method:
None ❑ Informal❑ Formal ❑ Sole Source Z Outside Agency ❑ Emergency ❑
Contract Type:
Services/Maintenance ® Construction ❑ Goods,Equipment, Supplies ❑
Change Order/Amendment El Contract Renewal ❑ Other,please explain ❑x Task order for an oncall
services contract
NOTE: CLERKS OFFICE WILL KEEP ORIGINAL DOCUMENTS IN COMPLIANCE WITH COLORADO STATE
ARCHIVES RETAINAGE SCHEDULE. ALL ATTACHMENTS MUST BE WITH THIS CHECKLIST.
Master Service Agreement#: 008.2019
Rev:2018-10-10 btf
iTKIN
COUNTIT
TASK ORDER
Task Order/Project Name: SMP Irrigation Pond&Riparian Restoration Plan
Task Order Number: 008.2019 A-7
Task Order Budget Line Item: 118.57.02294.82841
OWNER: CONTRACTOR:
Pitkin County Peak Ecological Services, LLC
Gary Tennenbaum & Lindsey Utter— Open Space Rea Orthner
and Trails
530 E Main,#202 PO Box 827, 301 Boulder Canyon Drive
Aspen, CO 81611 Nederland, CO 80466
Phone: (970) 920-5355 Phone: (303)258-3556
gary.tennenbaum@pitkincounty.com rea@peakecological.com
lindsey.utter@pitkincounty.com
PROJECT NAME: SMP IRRIGATION POND &RIPARIAN RESTORATION PLAN
START DATE: March 1,2019
END DATE: December 31, 2019
The Master Service Agreement For Provision of On-Call Ecological Services (the "Agreement") dated
January 1, 2019 between the Board of County Commissioners of Pitkin County (the "County") and Peak
Ecological Services, LLC PO Box 827, 301 Boulder Canyon Drive Nederland, CO 80466 (the
"Contractor"), shall include the following services.
1. Contractor's Obligations. Contractor shall complete the following.
1.1 Analysis of Existing Documentation and Team Coordination
The Contractor shall review existing documentation with DHM, Lotic Hydrological, and Irrigation
team. All existing riparian and ecological assessments and plans will be reviewed and will form the
basis of data for riparian/wetland intervention permit and CD level documentation.
Meetings:
• One Meeting with Lotic Hydrological and Peak Ecological to review plan and identify project
needs
• One Meeting with irrigation team to address strategy and overall concept
• Hydrosystems - One meeting to evaluate site conditions and irrigation strategy
• Samuelson Pump Co - One meeting onsite to evaluate and test existing system
1
Master Service Agreement#: 008.2019
Rev:2018-10-10 btf
Deliverables:
• The contractor will provide a detailed plan of action for coordination and milestones to develop
permit and construction documentation.
1.2 Permit Drawings and Construction Documentation
The contractor will create a permit level and construction drawing package incorporating the
restoration plans for ponds and the surrounding hayfield (to be restored to a riparian habitat and
sagebrush shrublands), construction access points and connections, maintenance access, and erosion
control measures. The intent of this product is to provide an exhibit submitted to Pitkin County to
accompany the Earth Moving Permit Application as well as a detailed construction package for
implementation of the plan. The subcontractor Lotic will manage all aspects related to water rights.
Lotic will also work with the design team to ensure that the water diversion, storage and distribution
infrastructure adhere to Department of Water Resources administrative rules for water use. The
Contractor will submit the information and follow up to acquire an official Jurisdictional
Determination letter from the US Army Corps of Engineers (USACE).
The Contractor will provide a permit drawing and construction documentation which will include
details for modification of the landform and area of restoration activities; a planting plan that identifies
woody riparian species for the restoration and identifies the planting method; a seeding plan that
addresses a native seed mix, seedbed preparation, seeding methods; soil amendments and erosion
control measures; and irrigation design. The Contractor will develop restoration success criteria, or
performance standards.
Following Hydrosystems' field visit to evaluate existing conditions and identify tasks to implement
temporary irrigation of the plantings, they will create an irrigation design for permitting and
construction. DHM has documentation of the existing infrastructure. Hydrosystems will produce an
irrigation plan,details and specifications. Samuelson Pump is to conduct a field investigation of pump
infrastructure and create a technical report detailing the rehabilitation of the pump to make it
operational for irrigation. Lotic is to provide the County guidance as it pertains to water rights
administration at the site. Lotic will also function as a liason to the local water commissioner.
Meetings:
• One meeting with Lotic Hydrological and Peak Ecological for plan review and coordination
• One meeting with Pitkin County to review permitting requirements and package
Deliverables:
• Site materials and grading plan
• Design details for planting, erosion mitigation, and re/vegetation protection fencing
• Annotated seeding plan and schedule with planting and seeding notes
• Detailed notes and steps outlining the order of operations and directives to minimize disturbance
• Calculating the area of disturbance and upholding the plan to the corresponding County mandates
• Irrigation construction drawings, details and specifications - KDI/Hydrosystems
2
Master Service Agreement#: 008.2019
Rev:2018-10-10 btf
• Pump rehabilitation technical report and construction details - Samuelson
• Permit Application
• Construction Management Plan
• Specifications Package
1.3 Final Submission to Pitkin County
The Contractor will submit a final construction set to the County for bidding and construction
purposes.
Deliverables:
• Final Drawings and Packages
Budget(see attached spreadsheet)
2. Compensation and Expenses, Invoicing, Payment and Offset. The County shall compensate
Contractor for its services in accordance with the Project Budget and Schedule set out in Paragraph 1
of this Task Order. It is expressly understood and agreed that in no event will the total compensation
and reimbursement to be paid hereunder exceed the sum of twenty eight thousand, two hundred and
ninety nine dollars and eighty cents ($28,299.80) for all services rendered. By Task Order or Task
Order Amendment, the County and Contractor may reallocate the budget among project tasks if the
total budget amount remains unchanged. Contractor shall invoice for the project monthly based on
hours worked, with payment expected within thirty (30) days of invoice, but any payment by the
County may be offset by any amount the Contractor owes the County for any reason.
Any invoices not sent in the following manner may have payment delayed. All invoices for this Task
Order shall reference Task Order 008.2019 A-7 and SMP Irrigation Pond & Riparian Restoration Plan.
Invoices shall be sent electronically in PDF format to lindsey.utter@pitkincounty.com and
gary.tennenbaum@pitkincounty.com with a copy to kim.arensdorf@pitkincounty.com..
3. Pitkin County's Obligations. Pitkin County shall administer this contract through a County
Representative. Gary Tennenbaum & Lindsey Utter, Planning & Outreach Manager will manage the
project as the County's Representative. The services provided and products delivered by the
Contractor under this contract will be subject to review by the County's Representatives,or a designee,
for compliance with Contractor's obligations prior to final payment.
4. Formation of Task Order. This Task Order is issued in accordance with the provisions of the
Agreement. Contractor agrees to provide services subject to the terms of this Task Order and for the
avoidance of doubt this Task Order consists of the terms set out in the Agreement. In all other respects
the Agreement is in full force and effect and remains unchanged by this Task Order.
3
Master Service Agreement#: 008.2019
Rev:2018-10-10 btf
PEAK ECOLOGICAL SERVICES, LLC
kw- ^ ^, Apr-23-2019
Rea Orthner Date
Principal Ecologist / Botanist
PITKIN COUNTY, COLORADO
Gttni tukAALtAinuoi Apr-24-2019
Gary Tennenbaum Date
Pitkin county Open space and Trails Director
Gary Tennenbaum
Pitkin County Open Space and Trails Director
4
Brush Creek Pond and Riparian Habitat Restoration Plan
cc' ct, 4\ s� et\ V 4\
er o`°$y a��� ego �y.�� o`c•�ao ��
e lac `..; y.�O� er N•��'
c°' a`•� Qc �e a`�o Quo
ea�c t��.Q tk's het• 0x• t•t.�O •
\Q�c�` mac° �co ``�c�,\
oe��5c °��` Q`�y�e �`e•�5 .dome` J\�a� o�`a� <6.6 Qea� �4• o�°cQ
r �` �a o J°y 0eh �.5 °5 �e `� �0 yC.
���� �,O °tea h�,r �i�¢P P\�e R) �i��`o 5��c0 �\�a QetOe Se' C.°�`•e\
2019 Rate $ 153.83 $153.83 $169.74 $ 122.00 $95.48 $ 100.00 $ 140.00 $0.58 $200.00 $0.58 GRAND TOTAL
Task 1.Analysis of Existing Conditions and Site Visit 8 8 6 8 8.8 4 400 1 62 40
Subtotal $1,230.64 $1,230.64 $1,018.44 $976.00 $880.00 $560.00 $232.00 $200.00 $35.96 $40.00 $6,403.68
Task 2.Permit Drawings and Construction Documentation 2 10 12 40 10 18.5 4 40
Subtotal $307.66 $1,538.30 $2,036.88 $4,880.00 $954.80 $1,850.00 $560.00 $40.00 $12,167.64
Task 3.Revisions and Final Drafts 2 2 12 40 100
Subtotal _ $307.66 $307.66 $2,036.88 $4,880.00 $100.00 $7,632.20
Total $26,203.52
8%Admin Fee $2,096.28
GRAND TOTAL $1,845.96 $3,076.60 $5,092.20 $10,736.00 $954.80 $2,730.00 $1,120.00 $232.00 $200.00 $35.96 $180.00 $28,299.80
3/28/2019 8:47:44