Contract Number:
Project Name:
Contractor:
Budget Line Item:!#BUDGET#!
!#BUDGET#!
!#BUDGET#!
!#BUDGET#!
!#BUDGET#!
Procurement Method:
Type:
Task Order Effective
Task Order End Date
Contract Type:
Retainage/Bonding:
County Representative: Dan Bartholomew County Rep. Phone #: (970) 429-2851
Department:
Provide a brief description of the Contract or Change Order:
$ 1,557,751.00
$ -
$ -
$ 1,557,751.00
003.22 A-1
Pitkin County
Contract Cover Sheet
Formal
Services/Maintenance
8/17/2022
8/16/2023
Task Order
Please fully allocate New Contract
Total if there are multiple codes
$ -
$ -
$ -
$ -
If this is a new Vendor, please enter the New Vendor information into Munis for workflow approval and include a complete W-9.
Contact Information for Pitkin County Contract/Project Lead:
Contract Information
Airport
Task order for consultancy services for the development of an updated ALP for the ASE Airport. Multiple
funding sources apply along with any requirements for reporting and performance.
Original Contract Amount:
Previous Change Order/Amendment Amount(s):
This Change order/Amendment Amount:
Contract Total:
Contract Value Summary:
No
ASE Airport Layout Plan Consultancy Services
Jacobsen Daniels, LLC
$ - 40451100.531000
Rev. 2022.08.17 CDD
NOTICE TO PROCEED
ASE AIRPORT LAYOUT PLAN CONSULTANCY SERVICES
DATE: August 17, 2022
TO: Jacobsen Daniels, LLC
121 Pearl Street
Ypsilanti, MI 48197
FROM: Pitkin County
530 E. Main St., Suite 302
Aspen, Colorado 81611
Jacobsen Daniels, LLC, following the completion of an Independent Fee Analysis and
receiving concurrence of such from the Federal Aviation Administration, is hereby
authorized to proceed on August 17, 2022, or as soon as practicable thereafter, with
the work covered by Pitkin County Task Order 003.22 A-1.
The work must be coordinated with Dan Bartholomew, ASE Airport Director at (970)
429-2851 or Dan.Bartholomew@AspenAirport.com.
PITKIN COUNTY, COLORADO
_________________________________________________
!#DEPARTMENT REPRESENTATIVE#!Date
Airport Director
Aug-18-2022
Dan Bartholomew
Master Service Agreement #: 003.22 Rev: 2022.07.27 CDD
1
TASK ORDER
Task Order/Project Name: ASE Airport Layout Plan Consultancy Services
Task Order Number: 003.22 A-1
Task Order Budget Line Item: Multiple
OWNER: CONTRACTOR:
Pitkin County Jacobsen Daniels, LLC
Dan Bartholomew – Aspen/Pitkin County Airport Brad Jacobsen
0233 E. Airport Road, Suite A 121 Pearl Street
Aspen, CO 81611 Ypsilanti, MI 48197
Phone: (970) 975-3162 Phone: (734) 961-3200
Dan.Bartholomew@AspenAirport.com Brad.Jacobsen@JacobsenDaniels.com
PROJECT NAME: ASE AIRPORT LAYOUT PLAN CONSULTANCY SERVICES
START DATE: August 17, 2022
END DATE: August 16, 2023
THIS TASK ORDER MAY BE EXTENDED BY MUTUALLY SIGNED CHANGE ORDER THROUGH THE COMPLETION OF THE ASSOCIATED TASKS
The ASE Airport Layout Plan ("ALP") Update Services (the “Agreement”) dated April 1, 2022 between
the Board of County Commissioners of Pitkin County (the “County”) and Jacobsen Daniels, LLC 121
Pearl Street Ypsilanti, MI 48197 (the “Contractor”), shall include the following services.
1. Contractor’s Obligations. Contractor shall perform the services outlined in the attached Scope of Work,
Exhibit A, in coordination with County Staff, FAA/TSA Personnel, CDOT Personnel, and any additional
stakeholders identified in accordance with the fee schedule(s) provided for primary and subcontracted
services as detailed in the Summary Fee Schedule, Exhibit B. The included fees and scope of work have
been independently evaluated (see Exhibit C) with concurrence received from the Federal Aviation
Administration for the work to be performed under this Task Order; any material adjustment(s) to the
scope of services or fees for such as provided for herein must be documented via mutually signed
Amendment and may be subject to additional evaluation and approval from the FAA and/or other Third
Parties.
Contractor will perform all work under this Task Order with the explicit understanding that the terms,
conditions, clauses, and requirements provided in the Master Service Agreement 003.22, executed on
April 11, 2022, shall govern and apply equally to any and all work performed and work product resultant
of this Task Order, including, but not limited to, those requirements as set forth by the Federal Aviation
Administration. The schedule for completion of each task shall be clearly communicated and coordinated
with Project Lead with expectations for the duration of each being derivative of the schedule provided in
the Qualifications form submitted in response to RFQ 003.22 and memorialized in Master Service
Agreement 003.22, Attachment B.
Master Service Agreement #: 003.22 Rev: 2022.07.27 CDD
2
2. Compensation and Expenses, Invoicing, Payment and Offset. The Agreement is funded in part
through grant funds the County will receive through the FAA. The County shall compensate
Contractor for its services in accordance with the Project Budget and Schedule set out in Paragraph 1
of this Task Order. It is expressly understood and agreed that in no event will the total compensation
and reimbursement to be paid hereunder exceed the sum of One-Million Five-Hundred Fifty-Seven
Thousand Seven-Hundred Fifty-One dollars and Zero cents ($1,557,751.00) for all services rendered.
By Task Order or Task Order Amendment, the County and Contractor may reallocate the budget
among project tasks if the total budget amount remains unchanged. Contractor shall invoice for the
project monthly based on hours worked, with payment expected within thirty (30) days of invoice, but
any payment by the County may be offset by any amount the Contractor owes the County for any
reason. Further, the County and the Contractor agree as this Contract is federally funded, it is therefore
subject to the requirements set forth in Title 49 CFR Part 18.36.
Any invoices not sent in the following manner may have payment delayed. All invoices for this Task
Order shall reference Task Order 003.22 A-1 and ASE Airport Layout Plan Consultancy Services.
Invoices shall be sent electronically in PDF format to Dan.Bartholomew@AspenAirport.com with
AP@PitkinCounty.com in copy.
3. Pitkin County’s Obligations. Pitkin County shall administer this Task Order through a County
Representative. Dan Bartholomew, ASE Airport Director will manage the project as the County’s
Representative. The services provided and products delivered by the Contractor under this contract
will be subject to review by the County’s Representatives, or a designee, for compliance with
Contractor’s obligations prior to final payment.
4. Formation of Task Order. This Task Order is issued in accordance with the provisions of the
Agreement. Contractor agrees to provide services subject to the terms of this Task Order and for the
avoidance of doubt this Task Order consists of the terms set out in the Agreement. In all other respects
the Agreement is in full force and effect and remains unchanged by this Task Order.
Signatures on Following Page
Master Service Agreement #: 003.22 Rev: 2022.07.27 CDD
3
JACOBSEN DANIELS, LLC
________________________________________________
!#VENDOR SIGNATURE#! Date
ASPEN/PITKIN COUNTY AIRPORT
DIRECTOR APPROVAL:
________________________________________________
!#DEPARTMENT REPRESENTATIVE#!Date
COUNTY MANAGER:
________________________________________________
!#COUNTY MANAGER#! Date
Aug-18-2022
Dan Bartholomew
Airport Director
Executive Vice President
Brad Jacobsen
Aug-18-2022
Deputy County Manager
Aug-18-2022
Rich Englehart
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 1
AIRPORT LAYOUT PLAN UPDATE CONSULTANCY SERVICES
SCOPE OF WORK
The following describes the scope of services for the preparation of an Airport Layout Plan (ALP)
Update as well as environmental processing and approval for Aspen/Pitkin County Airport (ASE)
under the governance of the Pitkin County Board of County Commissioners (BoCC). This effort will
translate, analyze, resolve and document the Common Ground Recommendations from the ASE
Visioning process into an FAA‐approved ALP plan set that represents the planned changes at ASE
over the next 20 years. In preparing the ALP plan set and narrative report, our team will utilize the
following FAA guidance:
AC 150/5070‐6B, Change 2 “Airport Master Plans”
AC 150/5300‐13B, “Airport Design”
AC 150/5300‐16B “General Guidance and Specifications for Aeronautical Surveys: Establishment
of Geodetic Control and Submission to the National Geodetic Survey”
AC 150/5300‐17C, Change 1 “Standards for Using Remote Sensing Technologies in Airport
Surveys”
AC 150/5300‐18B, Change 1 “Survey and Data Standards for Submission of Aeronautical Data
Using Airports GIS
FAA ARP SOP 2.0 ‐ Standard Procedure for FAA Review and Approval of Airport Layout Plans
(October 1, 2013)
National Environmental Policy Act (NEPA)
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 2
The following outlines the primary tasks required to complete the ASE Airport Layout Plan. Further
detail is then provided for each task describing the specific agreed upon scope of services.
Task 1: Project Scoping
Task 2: Project Management & Quality Control
Task 3: Community Outreach & Stakeholder Engagement
Task 4: Forecasts of Aviation Demand
Task 5: Facility Requirements & Demand/Capacity Analysis
Task 6: Alternatives (Common Ground Recommendations) Validation
Task 7: Facilities Implementation/Capital Improvement Plan Roadmap
Task 8: Sustainability & Environmental Overview
Task 9: AGIS & Airport Layout Plan Set
Task 10: Environmental Processing & Approval
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 3
TASK 1: PROJECT SCOPING
1.1 PROJECT SCOPING
1.1.1 Project Team Kick‐off Meeting
A project team kick‐off meeting will coordinate the initiation of the project with the entire
consultant team. This meeting will occur via conference call. This meeting will introduce the
project team; discuss roles and responsibilities; discuss project scope and schedule; review
documentation guidelines; and provide other relevant project protocols.
Deliverable(s):
Presentation materials from the meeting, will be shared and distributed
internally with team members.
1.1.2 Airport Team Kick‐off Meeting and Facility Tour
A project kick‐off meeting in Aspen will initiate the project with the Pitkin County. The overall
project team will be introduced to the Pitkin County staff, and a general review of the overall
airport operation will be discussed. Pitkin County will lead the consultant team on a series of tours
of the existing facilities. These tours will prepare the project team for much of the data collection
and inventory. Team Members will tour the landside, terminal, and airside facilities. This meeting
will occur over one half‐day.
Deliverable(s):
Meeting notes, including presentation materials from the meeting, will be
prepared following the meeting and distributed electronically in PDF format to
the meeting participants.
Airport Advisory Board Meeting #1
1.1.3 Scoping Workshops with Pitkin County
The remaining one half‐day will encompass the visioning session with Pitkin County staff. This
process is intended to develop an initial framework for the study that identifies the priorities at
ASE and specific goals and objectives for the study. These resulting goals and objectives will drive
the development of alternatives, how those alternatives are compared/contrasted, and the
implementation of the Common Ground Recommendations approved by the Pitkin County Board
of County Commissioners (BoCC).
Additional scoping session(s) may be required to develop and refine the draft and final scope of
services. These sessions will include a dialog that will assist in ensuring a clear understanding of
ASE’s relevant issues, concerns and the potential opportunities that should be explored to achieve
the desired results. These sessions are also aimed at providing and exploring new ideas and more
clarity regarding the study’s efforts and implementation of results.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 4
Deliverable(s):
Draft and final scope of services will be prepared following the meeting and
distributed electronically in PDF format to the airport staff for review and
comment. Edits and revisions to the draft scope of services will be incorporated
into the final scope of services.
1.1.4 Establish Document Templates
Document templates will be developed in coordination with Pitkin County. These will provide
guidelines for formatting documents in Microsoft Office, Adobe InDesign, and AutoCAD.
Templates will be developed for each of the following:
Technical Memorandums (MS Word)
Narrative/Chapter Reports (MS Word and/or InDesign)
PowerPoint template (MS PowerPoint)
Exhibit templates (AutoCAD, MS Word and/or InDesign)
Title blocks (AutoCAD)
1.1.5 Establish Base Files
Relevant base files will be developed for use on this project and distributed to the project team.
Updated base file information will be obtained with this Airport Layout Plan’s proposed AGIS
submittal (Task 9).
1.1.6 Collect and Analyze Historical Data and Information
Available historical data and information will be collected and analyzed in context to the various
tasks of the ALP Update. This data and information will be provided from ASE and Pitkin County
and reviewed by the project team. These documents will provide background information and
understanding to the project team during ALP Update tasks and analyses.
Data and information to be provided by Pitkin County:
Regional environmental studies (within the last 20 years), if any
Regional transportation studies (if any)
Regional land use studies (if any)
Pavement condition and strength reports
Fuel flowage activity, if available
FBO user data, including aircraft type and hours of operation
FAA tower counts (from Pitkin County and/or coordination with FAA)
Tenant leases, for tenants outside the main terminal
Airport Property Map
Gate/hardstand optimization analysis/study
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 5
List of documents to be expanded based on scope discussions.
Deliverable(s):
Coordination with Airport and/or their consultants to obtain requested reports.
Data and Information – no synthesizing will be provided.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 6
TASK 2: PROJECT MANAGEMENT & QUALITY CONTROL
2.1 PROJECT MANAGEMENT
An Airport Layout Plan Update requires oversight to ensure the project scope is delivered as
intended, on schedule and within budget. Throughout the project J|D will be responsible for the
delivery of all project elements and compliance of contract agreements. The project will be
managed through close oversight and communication with the Project Team and Pitkin County to
ensure consistency in assumptions, product, and content. All attempts will be made to coordinate
on‐site meetings with other on‐site coordination meeting to reduce travel costs and promote
efficiency in the project. The following describes the key ongoing project management tasks. For
scoping purposes, an 18‐month project duration is assumed.
2.1.1 Bi‐Weekly Team Meetings
30‐minute bi‐weekly weekly management coordination meetings, via phone, with Pitkin County
staff. Will cover Project updates, coordination of meeting invitations between the project team
and Pitkin County and/or project stakeholders and other project needs.
Meetings:
Ongoing coordination as described above
2.1.2 Bi‐Weekly Project Coordination Meetings
30‐minute bi‐weekly project team coordination calls (occurring on opposing weeks from the team
calls). Will include internal coordination of the project and product delivery/deadlines and review
of project scope schedule and budget.
Meetings:
Ongoing coordination as described above
2.1.3 Administrative Activities
Administrative functions related to project coordination and logistics, monthly invoicing, project
status reports, etc.
Deliverable(s):
Monthly Invoices and other administrative deliverables
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 7
2.2 ONGOING QUALITY CONTROL
A thorough quality control (QC) process will be followed for all project deliverables in
development of the Airport Layout Plan set. The QC team will consist of one (1) technical member
and one (1) editorial member of the consultant team. Specifically, the QC team will be responsible
for review of all Deliverable Presentations, all Stakeholder Presentations and all Airport Layout
Plan documents and reports. As it pertains to reports, it is assumed that each Airport Layout Plan
document and presentation will include two (2) draft document reviews and one (1) Final
Document Review.
Participants:
One (1) Jacobsen|Daniels technical (Director) and one (1) editorial member (Vice
President).
Meetings:
Internal QC team meetings only as described above.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 8
TASK 3: COMMUNITY OUTREACH & STAKEHOLDER
ENGAGEMENT
This section provides detail of the required logistics behind the execution of the community
outreach and public participation program.
3.1 FAA COORDINATION
This task will include six (6) milestone meetings with the FAA including a meeting that will focus
on the updated data collection, fleet mix, and forecast development, and a third meeting will
occur during the Facilities Implementation Plan/Capital Improvement Plan Roadmap portion of
the project. The forecast meeting will focus on the updated forecast and fleet mix and its
implications to the project and any concerns the FAA may have. This meeting will be in addition
to the typical coordination associated with the Aviation Forecast and Fleet Mix (Task 4). The final
FAA meeting will focus on FAA funding for the plan and understanding the type of support Pitkin
County can expect from the FAA during implementation of the plan. Three additional ad‐hoc
meetings with the FAA are anticipated as issues arise that require additional coordination with
the FAA. It is expected that these meetings will be in‐person at the FAA ADO offices in Denver
and will require the development and delivery of presentation material related to the project.
Meetings:
FAA coordination meetings only as described above.
Deliverable(s):
Presentations on relevant project material.
3.2 AIRPORT ADVISORY BOARD
Airport Advisory Board (AAB) Meetings are intended to provide project updates, review data and
analysis, solicit input on key issue, and present findings and recommendations. For this process
we are anticipating nine (9) meetings over the 18 month duration of the project. It is expected
that these meetings will be in‐person and will require the development and delivery of
presentation material related to the project.
Meetings:
Airport Advisory Board meetings only as described above.
Seven (7) focus area meetings highlighted within scope elements for reference.
Two (2) additional meetings are undefined to provide meeting flexibility during
the ALP project.
Deliverable(s):
Presentations on relevant project material.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 9
3.3 TENANTS (AIRLINES/CONCESSIONAIRES/RENTAL CARS/FBO)
Up to four (4) tenant meetings will be held with project stakeholders including the airlines, airport
concessionaires, rental car companies, and fixed based operators to gather information and data,
solicit input and feedback and resolve technical issues. The project manager and /or other key
Members of the Airport Layout Plan Update Team will coordinate with airport tenants as
necessary throughout the project duration. It is expected that these meetings will be in‐person
and will require the development and delivery of presentation material related to the project.
Meetings:
Stakeholder meetings only as described above.
Deliverable(s):
Presentations on relevant project material.
3.4 AD HOC STAKEHOLDER COORDINATION MEETINGS
Up to four (4) ad hoc stakeholder coordination meetings are anticipated for other project
stakeholders including the Board of County Commissioners (BoCC), community groups or
members, and other interested project stakeholders. These meetings are anticipated to include
previously prepared information and therefore no new information or presentations will be
required for these ad hoc meetings.
Meetings:
Ad hoc meetings only as described above.
Deliverable(s):
Existing presentations on relevant project material.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 10
TASK 4: FORECASTS OF AVIATION DEMAND
This task will provide both a constrained and unconstrained aviation demand forecast for the
baseline year (to be determined by the airport), and the 5‐, 10‐, 15‐, and 20‐year planning
horizons. An unconstrained forecast will be developed first based on the results of various
industry forecasting methodologies and our best judgment of future aviation demand. The
constrained forecast will be based on the unconstrained forecast with factors such as Airport
operations policies, local curfews or government agreements, airfield/airport facility limitations
and other factors (as directed by the Airport) applied to constrain future aviation activity to the
community recommended 0.8% average annual compound growth rate.
4.1 DATA COLLECTION
Interviews of Stakeholders
Information regarding historical and (currently known) planned airline activity, schedules, fleet
mix, etc. will be collected and organized for use in development of forecast methodologies and
presentation in the final report. This process may include interviews with Airport management,
airlines, cargo carriers and FBOs (GA and corporate operations), ASE air service consultant as well
as coordination with a member of the community chosen by the airport to satisfy concerns about
the validity of the forecast assumptions and/or conclusions.
Historical Aviation Activity Statistics
Historical aviation activity statistics, including latest available year‐to‐date activity will be collected
from Airport activity records for historical and current airline flight schedules, enplanements, air
cargo tonnage, aircraft operations, and based aircraft. Airport activity statistics will be
supplemented by airline flight schedules sourced from Cirium Diio Mi Schedule database, U.S.
Department of Transportation Statistics T‐100 and Origin and Destination databases. The FAA
Aerospace Forecast, FAA Terminal Area Forecast (TAF) and other recent Airport and/or industry
forecasts will be reviewed and referenced, as necessary.
Socio‐Economic Data
Socio‐economic data for the Airport catchment area, state and U.S. will be collected, tabulated,
and analyzed to identify trends that may impact the Airport’s aviation demand forecasts. Data for
population, employment, personal income, gross domestic product, and other related
information (existing and planned lodging facility rooms) will be sourced from the U.S.
Department of Commerce (Census Bureau, Bureau of Economic Analysis, Bureau of Labor
Statistics, etc.), state and local planning agencies, universities, and other sources as available.
Forecasts of socio‐economic data will be sourced from Woods & Poole Economics, Inc. latest
available “MSA Profile” database and supplemented by available local and regional forecast data.
The collective historical and forecast socio‐economic data may be used directly or indirectly to
inform the forecast and will be summarized at the beginning of the forecast document to provide
an overview of the local, state and U.S. historical and projected socio‐economic trends.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 11
4.2 FORECAST DEVELOPMENT
Aviation Demand Forecasts
The Consultant Team will develop an independent aviation demand forecasts for the Airport
based on industry standard forecasting methodologies including linear regression, trend line
analysis, market share, and comparison to industry forecasts, and other methodologies where
appropriate. The forecast will include unconstrained and constrained aviation demand (limited to
0.8% average annual compound passenger growth) projections for a base year and five‐, 10‐, 15‐
and 20‐year forecast horizons for the following activity categories:
1. Enplanements
o Total annual domestic and international enplanements
o Air carrier and commuter enplanements
o Peak month and peak hour enplanements
2. Operations
o Total annual operations
o Air carrier and air taxi/commuter operations
o Local and itinerant GA and government operations
o GA operations by aircraft category (piston, turboprop, jet, etc.)
o Air Cargo operations and tonnage
o Peak month and peak hour operations (total and by type of operation)
o Aircraft fleet mix forecast for passenger, cargo and GA operations
3. Based Aircraft
o By aircraft type
Develop Future Design Day Flight Schedule
Design Day Flight Schedules (DDFS) will be developed for the base year and a future planning
activity level for the unconstrained and constrained forecasts. The DDFS will be based on the
average day peak month departures as projected in the aviation demand forecast and will include
anticipated future changes to aviation activity such as changes in aircraft fleet mix, airline service
(new entrants and destinations as well as potential loss of service), gate utilization, and industry
trends anticipated within the planning period. The design day flight schedule will be used to
validate the number of gates and determine the appropriate size for each gate based on the fleet
mix.
FAA TAF and Airport Forecast Comparison
The results of the Airport forecast will be compared to the latest available TAF to determine if its
forecast projections are consistent with the TAF ‐ meaning the results of the Airport forecast differ
from the TAF by less than 10 percent in the 5‐year forecast and 15 percent in the 10‐year forecast.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 12
Note: If new FAA guidance and requirements are established due to the COVID‐19 pandemic during the
time of the preparation of the forecast but before approval, additional scope and fee will be required to
attain critical FAA approval of the aviation activity forecasts, before further demand‐driven planning can
proceed.
4.3 FORECAST WORKSHOP AND REPORT
Forecast Review Workshop and Report
Following completion of the forecast, but prior to issuing the forecast draft report, a workshop
via a conference call will be held with the Airport to brief them regarding the draft forecast
findings and address any comments.
Meetings:
Virtual meetings with the Airport and FAA to address any comments to the draft
forecast
Airport Advisory Board Meeting #2 (Primarily focused on Fleet Mix)
Deliverable(s):
Technical report of the forecast findings from the above sections, compare the
draft forecast with the most recent FAA TAF for the Airport, and submit to Pitkin
County for review.
Document the results of the forecasting exercise and comments from Pitkin
County into a Draft Report, for formal submittal to the FAA for their review.
Consultant team will address any comments from the FAA and issue a final
Report of the forecast.
Fleet mix and gate utilization sub‐report will derive from the DDFS and Forecast.
The report is intended to validate the size and number of gates proposed at ASE
and be used as a baseline for facility requirements (Task 5) and alternatives
validation (Task 6).
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 13
TASK 5: FACILITY REQUIREMENTS & DEMAND / CAPACITY
ANALYSIS
This task focuses on conducting a demand/capacity analysis and developing the future facility
requirements based on the forecast scenarios and then assessing what improvements will be
needed to meet those requirements. Demand/capacity and facility requirements will be
completed for those elements of the approved Common Ground Recommendations that need
further review and/or validation. Emerging trends in the industry will be identified and discussed
in the context of how they may impact future facility needs.
5.1 AIRFIELD ANALYSIS
5.1.1 Validate Airfield Demand/Capacity Analysis and Future Requirements
The Airport Layout Plan team will prepare a high‐level demand‐capacity analysis of airfield
elements from the approved Common Ground Recommendations that require additional
validation, including the west side parallel taxiway, relocated deicing pad, and elements of the
terminal apron. These facilities will be evaluated based on existing and forecasted demand (e.g.,
maximum aircraft size) to determine if alternatives are required. In addition, we will work with
Pitkin County staff and stakeholders (Airlines, FBO, others) to document airfield facility,
operational, and procedural improvements required for the safe and efficient operation of the
airfield.
Evaluate the potential impacts of technology, airline fleet mix changes, and other industry trends
on the need for new or modified airfield facilities.
Meetings:
Review meeting with the Airport to discuss preliminary analysis (coordinated
with other demand/capacity and facility requirements review meetings)
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
5.2 COMMERCIAL PASSENGER TERMINAL ANALYSIS
5.2.1 Develop Passenger Terminal Space Requirements
Develop projected passenger terminal space requirements, in aggregate, based on the Common
Ground Recommendations for the following major processing functions of the terminal such as:;
curb front and non‐secure space; check‐in and passenger processing areas; baggage processing
and screening; security screening checkpoint and TSA; concessions; airline support space
(including ATO, lounges and bag service offices); airport administration and support space;;
circulation and other public functions (including restrooms); aircraft parking/gates and passenger
boarding bridges. These requirements will be validated and reconciled with the terminal space
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 14
requirements considered within the Common Ground Recommendations and will be closely
coordinated as appropriate to support the anticipated concurrent terminal design effort.
Additionally, we anticipate developing similar component space requirements for a potential
Charter Terminal.
Meetings:
Review meeting with the Airport to discuss preliminary analysis (coordinated
with other demand/capacity and facility requirements review meetings)
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
5.3 LANDSIDE FACILITIES ANALYSIS
5.3.1 Roadways
Terminal and non‐terminal area roadway traffic requirements will be performed by identifying
design‐day activity from the activity forecast and other available data from the airport and
comparing with current activity.
5.3.2 Curbside Facilities
Terminal curbside area requirements will be performed by identifying design‐day activity from the
activity forecast and other available data from the airport and comparing with current activity.
5.3.3 Parking (Passengers & Employees) Facilities
Passenger and employee parking facility requirements will be performed by identifying design‐
day activity from the activity forecast and other available data from the airport and comparing
with current activity.
5.3.4 Rental Car Facilities
Rental car facilities area requirements will be performed by identifying design‐day activity from
the activity forecast and other available data from the airport and comparing with current activity
and through observations of existing operating patterns and facility utilization.
5.3.5 Commercial Vehicle Facilities
Commercial vehicle staging area requirements will be performed by identifying design‐day activity
from the activity forecast and other available data from the airport and comparing with current
activity and through observations of existing operating patterns and facility utilization.
5.3.5 Regional Transportation Connections
Regional transportation connection requirements will be developed through observations of
existing operating patterns and facility utilization and coordination with regional planning
information.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 15
Meetings:
Review meeting with the Airport to discuss preliminary analysis (coordinated
with other demand/capacity and facility requirements review meetings)
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
5.4 SUPPORT FACILITIES ANALYSIS
The Airport Layout Plan team will prepare a high‐level demand‐capacity analysis of support
facilities elements from the approved Common Ground Recommendations that require additional
validation such as corporate/general aviation and relocation of the Air Traffic Control Tower.
Additional facility requirements for Aircraft Rescue and Fire Fighting (ARFF) and Snow Removal
Equipment (SRE) building will be considered but are anticipated to be adequate based on existing
expansion capacity.
5.4.1 Corporate/General Aviation
Forecast demand will be used to establish future requirements for general aviation facilities at the
Airport. Assessment of aircraft parking (ramp, tie‐down, hangar, etc.) for based and transient
activity will include the impact of shifting the taxiway to achieve adequate separation from the
runway. Assessment will also include review of additional aircraft parking necessary to reduce or
eliminate “drop and go” operations if existing or planned ramp space is inadequate to do so. In
addition, the viability of using ICAO parking standards for GA aircraft, as suggested in the Common
Ground Recommendations, and their possible impacts on operational efficiency/safety will be
evaluated. Additional future aeronautical uses will also be considered for development options
along the west side of the airport.
5.4.2 Air Traffic Control Tower Siting
Air Traffic Control Tower (ATCT) siting analysis will determine up to three viable site locations and
tower height for a new ATCT. The analysis will use standards set forth in FAA Order 6480.4B,
Airport Traffic Control Tower Siting Process.
Meetings:
Review meeting with the Airport to discuss preliminary analysis (coordinated
with other demand/capacity and facility requirements review meetings)
Airport Advisory Board Meeting #3 (discuss facility analysis and obtain input)
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 16
TASK 6: ALTERNATIVES (COMMON GROUND
RECOMMENDATIONS) VALIDATION
This task focuses on validating and translating the facilities identified in the approved Common
Ground Recommendations as well as providing recommendations for enhancing or
supplementing the facilities that were either not included or not defined adequately in the
Common Ground Recommendations. These facilities will be addressed by general function to
include airfield/airspace, terminal, landside and support facilities.
6.1 ESTABLISH ALTERNATIVES APPROACH
6.1.1 Identify Issues, Opportunities and Constraints
Based on the CGR and any demand/capacity and facility requirements analysis, identify issues,
opportunities, and constraints of the CGR and the existing airport and site. Diagrams and analysis
will represent the translation of the CGR program to the physical existing airport environment and
existing FAA criteria. Through this analysis we will identify the critical issues and constraints that
need to be refined/resolved. Alternative solutions for these technical deficiencies will be
developed for consideration by the airport.
Deliverable:
A written summary of the Issues, Opportunities, Constraints, and Evaluation
criteria will be prepared with supporting graphics to be included in the
Alternatives task summary report along with potential solutions
6.2 AIRFIELD ALTERNATIVES
6.2.1 Develop Airfield Alternatives
Airfield alternatives will focus on specific elements of the Common Ground Recommendations
that are already approved by the Pitkin County BoCC, including a west side taxiway, terminal apron
and aircraft gating area, and the aircraft deice facility. This task will provide Airport staff with a
preferred alternative, along with the associated justification of airfield facility and operational
improvements. Consideration of a new runway or additional items outside of the already
approved Common Ground Recommendations will not be part of this alternatives’ analysis.
Meetings:
Meeting with the Airport to discuss Airside Alternatives (coordinated as part of
the Alternatives Workshops)
Deliverable(s):
Prepare a planning level conceptual drawing of the preferred airfield alternative
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 17
6.3 COMMERCIAL PASSENGER TERMINAL BUILDING ALTERNATIVES
6.3.1 Develop Terminal Building Alternatives
Based on the terminal description in the Common Ground Recommendations, and in
consideration of the landside requirements, preliminary passenger terminal, concourse, and
charter terminal alternatives will be developed in block diagrams. Preliminary terminal
alternatives will be developed using 2D AutoCAD block diagrams.
The preferred alternative will be refined to incorporate relevant comments from the evaluation
process and to more clearly explore how it meets the long‐term passenger demand.
6.3.2 Concourse and Gating Alternatives
This subtask will validate the number and size of the gates at the terminal that were established
in the Common Ground Recommendations. The evaluation/resolution of 7 v 8 aircraft gates, fleet
mix, terminal, and gate configuration. The validation of the Common Ground Recommendations
will also consider the Forecast (Task 4) results including the fleet mix validation.
Meetings:
Meeting with the Airport to discuss Terminal and Concourse and Gating
Alternatives (coordinated as part of the Alternatives Workshops)
Coordination with the Airport’s Terminal Designer to ensure design elements are
accurately reflected on the ALP.
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
6.4 LANDSIDE ALTERNATIVES
All relevant roadway, curbside, commercial ground transportation, public transit, public and
employee parking, and rental car facility needs will be addressed through a comprehensive
alternative, including:
Landside functions related to the new terminal concept
Improvements to expand landside facility capacities (e.g., adding parking spaces,
widening roadways, intersection/interchange re‐configurations, road relocations,
and adding new roadway links.
Operational improvements including minor changes to roadway operations or
curb space allocation.
Potential improvements to respond to changes to regional access roadways or
changes in adjacent land uses and terminal integrated intermodal facilities, such
as RFTA and RACs.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 18
6.4.1 Develop Terminal Curb and Ground Transportation Alternatives
Based on the recommended terminal alternatives, up to two (2) alternatives will be developed for
terminal curb and ground transportation configurations. If necessary, both alternatives will be
costed with a refined/preferred alternative cost estimate developed as well.
Meetings:
Meeting with the Airport to discuss Landside Alternatives (coordinated as part of
the Alternatives Workshops)
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
6.5 SUPPORT FACILITY ALTERNATIVES
6.5.1 Develop General Aviation Facility Alternatives
This task consists of the preparation of up to two (2) concepts for the future development of the
general aviation facilities of the airport based on their individual facility requirements. The initial
alternatives development will match up general aviation facility requirements with available land
with a focus on evaluating the use of specific parcels for general aviation against other needs,
including airfield access and midfield runway crossings. The alternatives will also address
development options that reduce or eliminate the need for drop and go type operations and
incorporate ICAO standards for aircraft parking, unless determined to be non‐viable in Task 5.
6.5.1 Air Traffic Control Tower Siting Alternatives
This task consists of identifying up to three (3) conceptual locations for the future development
of the Air Traffic Control Tower. Siting considerations identified in Section 5 will be
integrated/modified with other alternatives components (airside, terminal, landside, support) to
minimize operational and functional impacts and maximize operational efficiency and flexibility.
The siting alternatives for the ATCT will include coordination with the FAA to ensure all site
selection impacts are known and feasibility with other air traffic functions are addressed. A
detailed assessment of the structure or materials used for design is not included.
6.5.2 Additional Support Facility Alternatives
Alternatives will be developed for certain ancillary support facilities that meet the community
goals identified in the Common Ground Recommendations, including employee housing, airport
micro grid, solar/solar farm, public aircraft viewing area/s, noise and visual berms, and geothermal
opportunities. Alternatives for these support facilities will be identified in coordination with the
Aspen Public Works Master Plan and other relevant planning efforts. Working with the Airport, a
preferred site for each facility will be identified. Additional analysis may be required to identify
areas for electric vehicle charging stations, micro grid battery packs, and transformers prior to the
completion of the ALP document.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 19
Meetings:
Meeting with the Airport to discuss General Aviation, ATCT, and additional
Support Facility Alternatives (coordinated as part of the Alternatives Workshops)
Meeting with Pitkin County Public Works Department to coordinate their Master
Plan goals and objectives.
Deliverable(s):
A written summary will be prepared with supporting tables and graphics to be
used for presentation materials, and ALP narrative report.
6.6 COST ESTIMATION
Develop Rough Order of Magnitude Cost Estimates using local market information and aviation
cost database. Rough order of magnitude cost estimate will be prepared for up to two initial
alternatives, as well as the recommended airport improvements. Conceptual Rough Order of
Magnitude Cost Estimates will be reviewed with Pitkin County and updated based on their input.
6.6.1 Initial alternative for Cost Estimation purposes:
Terminal
Charter Terminal
Airfield
Widening of existing runway from 100’ to 150’
New west parallel taxiway, if feasible
Relocation of other facilities (de‐ice pad, etc.)
Clean‐up runway/taxiway geometry issues
Landside, integrated with terminal
Support facilities
Air Traffic Control Tower
6.6.2 Refined Alternatives for Cost Estimation purposes (see the above details and limit to 1 refined
concept):
Terminal – one (1) preferred concept
Airfield – one (1) preferred concept
Landside – one (1) preferred concept
Support Facilities – one (1) set of preferred concepts
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 20
Meetings:
Two (2) meetings per round of Alternatives (for a total of four (4) meetings):
Meeting with the consultant team for clarity on the Initial and Final Alternatives
Meeting with the Airport to present the initial and final alternatives’ cost
estimates
Airport Advisory Board Meeting #4 (present the initial and final alternatives’ cost
estimates.
Deliverable:
A written summary of the Cost Estimate along with tables and assumptions will
be prepared with supporting graphics to be used for presentation materials, and
ALP narrative report.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 21
TASK 7: FACILITIES IMPLEMENTATION PLAN/ CAPITAL
IMPROVEMENT PLAN ROADMAP
The proposed development plan will identify each individual Airport project proposed within the
planning horizon, along with the supporting cost data. Construction duration and sequencing will
be included through the development of the roadmap. This task also includes development of a
financial action plan which will identify the sources and uses of funds necessary for financing
projects included in the 20‐year implementation plan.
7.1 PRIORITIZED/SEQUENCED CAPITAL IMPROVEMENT PLAN
Using the results from the CGR and ALP Update analysis, the needs identified in the Facility
Requirements, the projected passenger activity, and assumptions on available funding, the
sequence of the recommended projects will be identified and prioritized. Project phasing
requirements will reflect enabling and successor projects within the roadmap.
7.2 SOURCES AND USES OF FUNDS
7.2.1 Available Funding/Funding Plan
Identify available, and appropriate (i.e., grants, bonds, airport cash, private investment, PFC, CFC,
etc.), project funding opportunities and assumptions and map them to eligible projects over the
course of the program. Funding assumptions will be verified with appropriate authorities (airport,
FAA, etc.)
Option: Funding Plan includes assessment of an option for the Airport to construct and maintain
Air Traffic Control Tower and lease the facility back to the FAA. Note: This option will only be
considered if all federal funding options are not viable.
Meetings:
Meeting with the Airport to prioritize recommended improvements and establish
the development plan
Meeting with Airport’s financial consultant to evaluate cash flow, PFC capacity,
and days of cash on hand. Meeting will include other applicable financial
representatives as identified by the Airport.
Deliverable:
A written summary will be prepared with the appropriate tables and graphics to
be used for presentations, and ALP narrative report.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 22
7.3 PROJECT SEQUENCING
7.3.1 Phasing Plan
Identify the phasing/implementation plan for all projects identified through Alternatives (Task 6)
that are proposed to be carried forward as the Airport’s preferred development. Identify/define
enabling and successor projects.
Meetings:
Meeting with the Airport to prioritize recommended improvements and establish
the development phasing plan
Deliverable:
A written summary will be prepared with the appropriate tables and graphics to
be used for presentations, and ALP narrative report. Phasing Plan should include
an Microsoft Project sheet.
7.4 WORKPLAN AND CASHFLOW
Using the project sequencing plan, a workplan will be developed that reflects the planning, design
and construction elements of each project over the life of the program. Project dependencies will
be identified to ensure coordination between enabling and successor projects is clear. A matching
cash flow projection will be provided to illustrate the annual cash requirements that align with
the sources and uses of funds analysis.
Meetings:
Meeting with the Airport to prioritize recommended improvements and establish
the development plan
Airport Advisory Board Meeting #5
Deliverable:
A written summary will be prepared with the appropriate tables and graphics to
be used for presentations, and the ALP narrative report.
Microsoft Project diagram including related projects and timelines for actions
including funding, design, planning, environmental actions (Task 8
recommendations), and step by step Implementation Guide.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 23
TASK 8: SUSTAINABILITY & ENVIRONMENTAL OVERVIEW
8.1 PRELIMINARY REVIEW OF SUSTAINABILITY COMPONENTS
To ensure the projects meet the county/airport/community goals established in the ASE Visioning
process, a high‐level review and coordination of sustainability aspects specific to the ALP Update
components (i.e., Common Ground Recommendations) will be conducted and documented.
Goals include noise and emission reduction, sustainable operations, carbon offsets, etc. This effort
will compile and organize the ongoing as well as future sustainability efforts at the airport and
discuss opportunities to leverage the ALP Update components to further these efforts. This task
does not include environmental processing (NEPA) resulting from changes to the previously
approved FAA projects.
8.2 ENVIRONMENTAL OVERVIEW (PROPOSED DEVELOPMENT PLAN)
8.2.1 Review Proposed Development Plan
Prior to implementation of recommended Airport Layout Plan update projects, the potential
environmental effects of each project must be reviewed in accordance with NEPA. The
Environmental Overview typically provides a summary of environmental review considerations
related to the set of recommended development projects identified in the Airport Layout Plan to
support development of an environmental processing strategy for Airport Layout Plan projects.
Because NEPA processing is included a separate task for this contract, the environmental overview
is omitted from this section.
Meetings:
Airport Advisory Board Meeting #6
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 24
TASK 9: AGIS & AIRPORT LAYOUT PLANS PACKAGE
This summary of work describes the scope of work and services required for an Airport Layout
Plan update and aeronautical obstruction survey at the Aspen‐Pitkin County Airport located in
Aspen, CO. The project will be done in compliance with ADIP (Airport Data and Information)
policies and will include an airport airspace analysis for vertically guided operations for existing
Runway 15/33. The Advisory Circulars identified below detail the data collection requirements
and accuracies for the project and the verification process by the Federal Aviation Administration
(FAA) and the National Geodetic Survey (NGS).
AC 150/5070‐6B, Change 2 “Airport Master Plans”
AC 150/5300‐13B, “Airport Design”
AC 150/5300‐16B “General Guidance and Specifications for Aeronautical Surveys:
Establishment of Geodetic Control and Submission to the National Geodetic
Survey”
AC 150/5300‐17C, Change 1 “Standards for Using Remote Sensing Technologies
in Airport Surveys”
AC 150/5300‐18B, Change 1 “Survey and Data Standards for Submission of
Aeronautical Data Using Airports GIS
9.1 UPDATE AGIS IMAGERY AND MAPPING
The purpose of this project is to accomplish an FAA Airport Airspace Analysis Survey for all
surfaces defined in FAA Advisory Circular 150/5300 ‐ 18B: Section 2.7.1.1 Runways with Vertical
Guidance. For this project, we will acquire new vertical stereo digital imagery at a physical image
scale of 1” = 2,500’ of the obstruction surface areas and 1” =1,250’ of the mapping limits. The
aerial imagery will cover all the Airspace Analysis surfaces using an UltraCam Falcon prime (UCFp),
or comparable, during leaf‐on conditions.
From the 1” = 2,500 imagery, we will produce the following:
Limited landmark feature planimetric mapping
Color digital orthophotos with a 1.0’ pixel resolution
Identification and mapping of obstruction obstacles for all VG surfaces
From the 1” = 1,250 imagery, we will produce the following:
100 scale mapping with 2’ contours of the existing airport property (788 acres)
Color digital orthophotos with a 0.5’ pixel resolution
Identification and mapping of obstruction obstacles for the VGRPS, VGPCS &
VGPS surfaces
The online SOW will be prepared during project initiation with input from the airport and the
Airport Layout Plan team. The Airport Layout Plan team will be responsible for preparation and
submittal of the Survey and Quality Control Plan, Imagery Acquisition Plan, Imagery Acquisition
Report and all associated data files as required for submission to the FAA ADIP.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 25
Quality Standards
The project has been designed to conform to the National Map Accuracy Standards for 1”=100’
scale planimetric feature collection, two foot contours and six and twelve inch orthophoto
production. In addition, we ensure that the photogrammetric mapping will meet all FAA and NGS
standards. We will exercise reasonable care and will conform to the standards of practice
ordinarily used by the photogrammetric profession.
Project Area
The project area encompasses all of Aspen/Pitkin County Airport (ASE) inclusive of the obstruction
surfaces as defined in AC 150/5300‐18B.
Control Surveying
The aerial photography will be completed with ABGPS control which will be used for the base
control for the geo‐referencing of the aerial imagery. The Consultant will process the ABGPS data
using COR stations and reference it to the project control datums:
Horizontal: North American Datum of 1983/2011 (NAD 83(2011)), in the CO State
Plane Coordinate System, Central Zone in US survey feet.
Vertical: North American Vertical Datum of 1988 (NAVD 88)
The Airport Layout Plan Team will complete all the remaining on‐site ground control surveys,
including:
Geodetic control validation of the existing airport PACS and SACS stations or
establish temporary airport control according to the guidelines established in AC
150/5300‐16B
Establishing all necessary photo‐identifiable ground control and FAA mandated
checkpoints required to validate the ABGPS and IMU control.
Collection of all the airport runway end positions
Collection of vertical profiles for all runways
Collection of the position, elevation, and where required the appropriate
navigational aid perpendicular point of all electronic and visual navigational aids
(NAVAIDS) located on the airport and associated with any current instrument
approach servicing the airport
Full field‐collected attribution of all airport features
All other tasks, not specifically listed above, as outlined in FAA AC‐18B, Table 2‐1
“Survey Requirements Matrix for Airport Layout Plan.”
Final Survey Report
Photogrammetric Mapping
We will collect the features normally shown on 1" = 100' scale mapping within the mapping limits
identified. We will build a digital terrain model (DTM) by collecting masspoints and breaklines.
These DTM elements will be used to construct a triangulated irregular network (TIN) surface from
which 2' contours will be interpolated. Contours will be dashed in areas where the ground is
obscured by trees, dense brush, deep shadows or other obstructing features. Dashed contours
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 26
indicate a lower level of accuracy. Additional field surveys should be performed in areas of dashed
contours prior to design. All contours will be continuous polylines. The final data will be delivered
in ESRI Shapefile and AutoCAD formats and will include Digital Elevation Model (DEMs) and
Triangulated Irregular Network (TINs) representations as deliverables.
Orthophoto Mapping
We will use the control solution and imagery to generate a Digital Elevation Model (DEM) of the
VG surfaces. The imagery will be processed into color digital orthophotos using the DEMs to
rectify the images. Orthophotos for the entire project area will be developed with a 1.0’ pixel
resolution and for the airport property, with a 0.5’ pixel resolution. Orthos will be delivered in a
GeoTIFF file format.
18B/Other Obstruction Surveys
The Obstructions Surfaces to be uploaded to ADIP will satisfy the requirements of AC 150/5300‐
18B:
2.7.1.2 Analysis of EXISTING Runways 15/33 with Vertically Guided Operations
(Surfaces include the VGRPS, VGPCS, VGAS, VGPS, VGATS, VGHS and VGCS)
Other obstruction survey data for the runways in AutoCAD/Excel/CSV file format:
Existing Runway 15 – Part 77 NPIR(C)
Existing Runway 33 – Part 77 VIS(B)
Existing Runway 15 – Advisory Circular 13B Surface 4 (20:1)
Existing Runway 33 – Advisory Circular 13B Surface 3
Existing Runway 33 – Advisory Circular 13B Surface 7 (100 ft wide RWY)
Existing Runway 33 – Advisory Circular 13B Surface 7 (150 ft wide RWY)
The specific types and quantities of obstructions for each surface are outlined and clearly defined
for the surface in each circular section. Any obstructions that meet the requirement of the circular
but are of a nature that elevations at the highest point of the obstruction are virtually impossible
to read through photogrammetric methods (cell tower, electrical tower, etc.), will be identified
and relayed to the surveyor to initiate field surveyed elevations for the obstruction.
The obstruction delivery will include the limited landmark planimetric feature collection.
All planimetric features will be developed in both AutoCAD and ESRI Shape File formats (including
appropriate attribute related tables). Format will be in appropriate and logical feature type
(Point/Line/Polygon/Text) for analytical and display purposes.
Deliverable(s): 18B elements will be uploaded to the ADIP website
Imagery Plan and Survey and Quality Control Plan
Image Delivery (sent to FAA)
Color digital orthophotos (sent to FAA)
Digital limited landmark detail outside the airport
Obstruction survey data for EXISTING Runway 15/33
Planimetric data and two foot contours to 18B specs (Shapefile format)
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 27
Photogrammetrically derived and surveyed attributes in defined format
Surveyed ends and profile for each runway
NAVAID data
FGDC compliant metadata
Deliverable(s): Other
Planimetric data and two foot contours in AutoCAD format (mapping limits)
Color digital orthophotos with a 1.0’ pixel resolution in GeoTIFF (ortho limits)
Color digital orthophotos with a 0.5’ pixel resolution in GeoTIFF (mapping limits)
Other obstruction survey data for Runway 15/33 in AutoCAD/Excel/CSV file
format
2 color enlargements (30”x40”) covering the airport and surrounding area
(mounted/laminated/framed)
All data to be delivered in both AutoCAD and Esri Shape File formats w/
attribution.
DEMs and TINs
9.2: INVENTORY VALIDATION
The AGIS survey will be used to document a baseline of the airport and used to develop attributes
for all existing airport infrastructure and land uses. The inventory validation will document the
existing facilities at the Airport in support of completing the ALP and other tasks within the scope
of work. The following describes the required elements of this task. The inventory will rely on
documents provided by Pitkin County, collected from other sources by the Airport Layout Plan
team, interviews with tenants and Pitkin County staff and site observations. The validated
inventory will be put into a GIS database and web based application that supports
access/visibility/use for the airport.
9.2.1 Airfield/Airspace Inventory
Develop an inventory of existing airfield facilities in graphic formats using existing aerial
photography and information from the Airport. Recent planning studies will serve as a basis for
identifying existing conditions. Data will be validated through the sources and means described
in the task summary. Specific subtasks include:
Obtain available documentation on previous Pitkin County analyses and
recommendations on arrival/departure efficiencies, taxiing efficiencies, and
gate/hardstand optimization.
Obtain copies of other recent relevant operational studies such as the
Environmental Assessment
Using existing drawings, updated based on aerial survey data, assess whether
existing airfield components meet current FAA airport design standards as
identified in FAA Advisory Circular 150/5300‐13B Airport Design. Non‐
conforming conditions shall be noted and incorporated in the technical
memorandum.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 28
Document current air traffic control systems, agreements, and procedures to the
extent required for the purposes of the Airport Layout Plan.
Obtain most recent 10‐year data on distributions of the ceiling, visibility, and
winds from the National Weather Service’s hourly Surface Weather Observations
and data on runway‐use configurations and associated weather conditions from
the FAA Aviation System Performance Metrics (ASPM) database. Information will
result in the development of appropriate Wind Rose diagrams.
Obtain information/copies of any existing modifications to airport design
standards (MOS).
Meetings:
Potential meeting with the Airport and FAA to discuss available airfield
information.
9.2.2 General Aviation Facilities Inventory
Develop an inventory of existing general aviation facilities in graphic formats using existing aerial
photography and information from the Airport. The summary will include the general operational
characteristics of the facilities along with a table summarizing the facility type, tenant, and size.
The facilities will be verified by review of available documentation, field visits, and discussions
with individual stakeholders. Information to be collected includes:
Based Aircraft (Number and mix)
Fuel storage facilities (size and location)
Conventional/Corporate hangars (size and location)
Transient aircraft parking/storage areas and number of tie‐down positions (size
and location)
Based aircraft parking/storage areas and number of tie‐down positions (size and
location)
Number and type of based aircraft stored in hangars and on tie‐downs
FBO facilities (tenant, size, and location)
Activity information – average day operations by based and transient aircraft;
peak day(s) and times of year; known operational or facility challenges (excess
demand, location, landside, airside, hangars/facilities)
Lease term and extents
9.2.3 Support Facilities Inventory
Develop an inventory of existing support facilities in graphic formats using existing aerial
photography and information from the Airport. The summary will include documentation of the
present use, configuration and size of the following support/ancillary facilities will be developed.
Multi‐Purpose and Ground Service Equipment (GSE) Maintenance Facilities
Aircraft Maintenance Facilities
FAA Facilities
Aircraft Rescue and Fire Fighting (ARFF) Facilities
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 29
Fuel Storage and Dispensing Systems
Electric Ground Service Equipment (eGSE) Charging Facilities
Deicing Fluid Containment Facilities
Miscellaneous Pitkin County Facilities including Airport Maintenance and
Operations
Meetings:
Potential meeting with the Airport to discuss available support facilities
information. Meeting will be coordinated with Kick off meeting.
Additional meetings with Airport departments, stakeholders, and tenants,
coordinated by the Airport, as appropriate to discuss existing operations
including Airport Operations, Airport Maintenance, ARFF, ATCT.
9.2.4 Existing Terminal Space Inventory & Operations
This section will document existing floor plans, with room numbers and utilization, along with
current lease areas and tenants for all passenger terminal and concourse buildings. Information
regarding the utilization of the existing terminal building, airline gates and apron area will be
collected. The terminal building will be analyzed to understand the existing functional layout and
general facility operation. A summary of the existing operation will be prepared with supporting
photographs and graphics of the existing flow of passengers, baggage, and the flow of goods
through the terminal building.
A table will be developed to summarize the existing terminal square footage by function. This
table will also serve as the format for the Facility Program Requirements. The assumption is that
CAD versions of the floor plan of each building will be made available to the project team.
Meetings:
Meeting with the Airport to discuss available terminal information. Site visit to
review existing terminal layout, utilization and leases including back‐of‐house
space. Meeting will be coordinated with Kick off meeting.
9.2.6 Develop Landside Inventory
This task will involve collection and review of available relevant studies and data related to ground
transportation and parking facilities. The areas to be included in the assessment of existing
conditions for ground transportation and parking facilities include:
Roadways and vehicular traffic—both on the Airport and on roadways connecting the Airport to
the regional highway network
Terminal curbsides
Parking facilities, including public parking, employee parking, and cell phone lots
Taxi, TNC, and commercial vehicle staging areas
Rental car facilities
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 30
Public transit
Other landside facilities and/or transportation networks on airport landside property (i.e. bike
path, future aircraft viewing area/s, etc.)
Information will be collected as‐follows:
Base mapping and plans depicting the size and layout for the following:
Airport roadway network including number of travel lanes.
The layout and space allocations for terminal building curbside areas.
The layout and inventory for each on‐Airport parking facility (public, employee,
etc.)
Space allocation for taxi, TNC, and commercial vehicle staging areas.
Other landside facilities and/or transportation networks on airport landside
property (i.e. bike path, future aircraft viewing area/s, etc.)
Meetings:
Virtual meeting with the Airport to discuss available information in the above
request. Site visit to review existing facilities. Meeting will be coordinated with
Kick off meeting.
9.2.7 Existing Land Use Plan review and Baseline
Review and assess existing land use plans, other studies and associated efforts recently completed
to establish and integrate baseline considerations for land use and development planning. A
summary of the existing Land Use Plan will be prepared for incorporation into the Airport Layout
Plan to integrate with vision and identify overlapping goals and objectives. Preferences and
priorities for future use and airport targets and opportunities related to land use and real estate
identified in the Plan will be included.
Meetings (Additional Coordination):
Public Works Department (Public Works Master Plan)
Micro grid project
PC and COA Planning and Zoning Departments.
9.3 COMPLETE AIRPORT LAYOUT PLAN PACKAGE
Using the data from the prior tasks, the Consultant will produce a complete plan set comprising
the traditional ALP. The drawing set will be prepared in AutoCAD and will be delivered in
Electronic PDFs, original CAD files and GIS Shapefiles. Consultant will prepare a full and
comprehensive set of drawings, as defined in Chapter 10 of FAA Advisory Circular 150/5070‐6B
Airport Master Plans, FAA ARP SOP 2.00, Standard Procedure for FAA Review and Approval of
Airport Layout Plans. The ALP drawing set will include the following sheets:
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 31
Cover Sheet
General Data Sheet
Existing Airport Layout Drawing
Future Airport Layout Drawing
Terminal Area Drawing
Airport Airspace Drawing
Inner Portion of the Approach Surface Drawings
Runway Departure Surface Drawings (for each runway end)
On‐Airport Land Use Drawing
Airport Property Map/Exhibit A (will reference Exhibit A linework and recent
airport survey provided by Pitkin County)
A Draft of the ALP package will be delivered to Pitkin County and then the FAA for review. Three
(3) rounds of review comments and edits are included in this scope, which includes two (2) with
Pitkin County and one (1) with FAA. Electronic PDFs of the full ALP set will be provided for each of
the review periods. Consultant will coordinate with county staff to ensure the final ALP set
deliverable products are useful and usable, this includes the incorporation of the ALP into a web
application.
The final ALP package will be delivered to the FAA for Final approval. One final round of review
comments and edits are included in this scope. Electronic PDFs, original CAD files and GIS
Shapefiles of the full ALP set will be provided.
9.4 ALP REPORT AND WORKSHOPS
9.4.1 ALP Narrative Report
Documentation will be provided in the form of a Summary Report compliant with the format as
outlined in FAA ARP SOP 2.0 ‐ Standard Procedure for FAA Review and Approval of Airport Layout
Plans (October 1, 2013). No other documentation will be provided.
9.4.2 ALP Workshops
It is anticipated that this task will include up to two meetings. The two meetings include: (1) one
meeting to discuss the draft ALP with Pitkin County staff, the Airport Advisory Board (Airport
Advisory Board Meeting #7), and possibly the BOCC; and (1) one meeting with the FAA to discuss
the draft ALP and comments associated with it. FAA comments may be addressed via the
telephone or email communications.
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 32
TASK 10: ENVIRONMENTAL PROCESSING AND APPROVAL
The FAA issued a FONSI/ROD in July 2018 for an Environmental Assessment (EA) for runway and
terminal area improvements at the Aspen/Pitkin County Airport (ASE). Since the issuance of the
FONSI/ROD, however, Pitkin County (the County) has adopted the Common Ground
Recommendations which vary from the scope of the EA approved in 2018, including shifting
Taxiway A to the northeast and relocating the air traffic control tower (ATCT) instead of shifting
Runway 15‐33 to the southwest. Both of these modifications may be considered by the FAA to
be outside of the scope of the Proposed Action put forth in the previous EA. Therefore, three
potential tasks associated with addressing the proposed changes to the EA approved in 2018 are
considered below.
10.1 – COMPARE EA PROJECT COMPONENTS TO PROPOSED COMMUNITY CHANGES
Thoroughly review the currently approved EA and compare it to the measures proposed through
community engagement, which will include:
The ALP team will develop a Project Comparison Matrix, which documents:
Differences between and similarities with project components of the EA and
proposed community changes
Environmental impacts documented in the EA and anticipated environmental
impacts of proposed community changes
The results of the Project Comparison Matrix will likely suggest one of three possible outcomes:
1. If certain project elements (e.g., the terminal) and their related impacts are similar enough to
the original EA, the FAA may concur that those specific project elements are adequately
addressed, relative to NEPA under the previous EA.
2. If remaining project elements or their expected environmental impacts are noticeably different
from what is documented in the EA, and based on public controversy, FAA may require the
County to update the EA through a Supplemental EA.
3. If the remaining project elements and their related impacts vary substantially from what was
evaluated in the original EA, and based on public controversy, FAA may require the County to
perform an entirely new EA.
Based on an analysis of the Project Comparison Matrix, the ALP team will assist the County in
developing a FAA coordination plans for one or more of the three possible outcomes, as
necessary. Factors that are likely to affect which approach the County puts forward to FAA
includes:
The ability to “salvage” the terminal improvements portion of the original EA, including the
more recent related stakeholder suggestions, to avoid performing a Supplemental or entirely
new EA for those project elements
Relatedly, the ability to “dis‐connect” the Taxiway A shift as a separate safety‐related
improvement, thereby avoiding delay in implementing the terminal improvements
Assumes a potential subsequent EA for the Taxiway A and ATCT shifts
Potential Section 163 impacts and resulting changes to the scope of analysis
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 33
Anticipated levels of public interest and engagement
Environmental review and project implementation schedules
The ALP team would prepare written documentation that supports the County’s desired approach
and clearly identifies the both the similarities and differences between the EA and the proposed
community changes:
Project description
Purpose and need
Proposed action
Updated and/or newly required resource‐specific analyses
Summary of Project Comparison Matrix
Deliverable(s):
Project comparison matrix
Memorandum summarizing proposed approach and project changes
Assumptions:
Data gathered will be able to be used for the Purpose and Need, Project
Description, and Alternatives sections for the Supplemental EA.
One coordination site visit with two (2) ALP team members
10.2 – COORDINATE WITH FAA ON DESIRED APPROACH
The ALP team would assist, as necessary, in supporting the County in its efforts to coordinate with
FAA ADO staff regarding the County’s desired course of action. The ALP team will assist in
coordinating the following FAA determinations and approvals:
Concurrence on project elements already addressed in the previous EA
Section 163 determination for remaining project elements to determine those projects where
FAA retains regulatory authority
Appropriate NEPA approach to address remaining project elements
Deliverable(s):
Section 163 supporting materials
FAA meeting material (agenda, presentation, and meeting notes).
Memorandum documenting the agreed‐upon approach to satisfy NEPA
requirements.
Assumptions:
All meetings would be conducted virtually
ASPEN/PITKIN COUNTY AIRPORT
AIRPORT LAYOUT PLAN UPDATE
SCOPE OF WORK
121 Pearl Street, Ypsilanti, MI 48197 | Tel. 734 961 3200 | JacobsenDaniels.com 34
10.3 – PERFORM NEPA ANALYSIS TO SECURE UNCONDITIONAL FAA ALP APPROVAL
Given the ALP team’s current understanding of the proposed changes to the project, it is
anticipated that the FAA will likely require at least a supplemental EA for the revised project
elements. This supplemental EA would build on the analyses performed in the previous NEPA
document and would likely include:
Refinement of the Purpose and Need and addition of an alternative that reflects the current
Proposed Action elements
Alternative screening would consider all alternatives for addressing the current Modification of
Standards (MOS)
Affected Environment and Environmental Consequences would be updated to reflect the latest
conditions and the effects of the preferred alternative
FAA and Stakeholder Involvement would be incorporated at key points in the NEPA process and
comments, and concerns would be addressed in the supporting NEPA documentation
Deliverable(s):
Draft Supplemental EA
Draft EA Public Workshop/Public Hearing materials
Final Supplemental EA
GIS Shape file depicting geographic coverage of environmental evaluation
coverage/s by project.
Assumptions:
Project description, purpose and need, and alternatives would be consistent with
analysis from Task 10.1, and would be carried forward to the Supplemental EA.
Environmental analyses used in the 2018 is available for verification and use in
the Supplemental EA.
No public or agency scoping meeting(s) would be held.
One Public Meeting/Public Hearing on the Draft EA, with up to three (3) ALP
team members in attendance.
Up to 25 public/agency comments and no attorney comments received during
the public outreach process.
No field work or special studies (such as cultural resource assessment, biological
assessment, wetland delineation, traffic studies, geotech, survey, borings, etc.).
TOTAL
COST
Task 1 Project Scoping 29,735$
1.1 Project Scoping
1.1.1 Project Team Kickoff Meeting 2,399$
1.1.2 Airport Team Kickoff Meeting and Facility Tour 2,399$
1.1.3 Scoping Workshops with Pitkin County 9,963$
1.1.4 Establish Document Templates 4,582$
1.1.5 Establish Base Files 6,150$
1.1.6 Collect and Analyze Historical Data and Information 4,244$
Task 2 Project Management & Quality Control 76,106$
2.1 Project Management
2.1.1 Bi‐Weekly Team Meetings (18 months = 36 meetings)9,225$
2.1.2 Bi‐Weekly Project Coordination Calls (18 months = 36 meetings)6,919$
2.1.3 Administrative Activities (18 months)13,838$
2.2 Ongoing Quality Control (QA/QC)
Meeting Materials (2 meetings per month = 36 Presentations)15,375$
Draft Report Reviews (8 Documents x 2 Reviews)20,500$
Final Report Reviews (8 Documents)10,250$
Task 3 Community Outreach & Stakeholder Engagement 138,867$
3.1 FAA Coordination Meetings
FAA Coordination Meetings (6 Meetings + Meeting Preparation)50,922$
3.2 Airport Advisory Board (AAB) Meetings
AAB Meetings (9 Meetings + Meeting Preparation)54,243$
3.3 Airline/Concessionaires/Rental Car/FBO Meetings
Stakeholder Coordination Meetings (4 Meetings + Meeting Preparation)24,108$
3.4 Ad Hoc Stakeholder Coordination Meetings
Stakeholder Coordination Meetings (4 Meetings)9,594$
Task 4 Forecasts of Aviation Demand 153,627$
4.1 Data Collection
Interview of Stakeholders 9,840$
Historical Aviation Activity Statistics 9,840$
Socio Economic Data 9,840$
4.2 Forecast Development
Aviation Demand Forecasts 29,520$
Develop Future Design Day Flight Schedules 29,520$
FAA TAF and Airport Forecast Comparison 29,520$
4.3 Forecast Documentation and Workshop
Review Workshop (Virtual)13,407$
Report Documentation 22,140$
Task 5 Facility Requirements & Demand/Capacity Analysis 89,052$
5.1 Airfield Requirements
5.1.1 Validate Airfield Demand/Capacity and Future Requirements 14,945$
5.2 Commercial Passenger Terminal Requirements
5.2.1 Develop Passenger Terminal Space Requirements 18,942$
5.3 Landside Requirements
5.3.1 Roadways 5,166$
5.3.2 Curbside Facilities 2,583$
5.3.3 Parking (Passenger & Employee) Facilities 5,166$
5.3.4 Rental Car Facilities 2,583$
5.3.5 Commercial Vehicle Facilities 2,583$
5.3.6 Regional Transportation Connection 2,583$
5.4 Support Facilities Requirements
5.4.1 Corporate/General Aviation 18,020$
5.4.2 Air Traffic Control Tower Siting 16,482$
Task 6 Alternatives (Common Ground Recommendations) Validation 120,017$
6.1 Establish Alternatives Approach
6.1.1 Identify Issues, Opportunities and Constraints 7,872$
6.1.2 Establish Evaluation Criteria 6,027$
6.2 Airfield Alternatives
6.2.1 Develop Airfield Alternatives 14,945$
6.3 Commercial Passenger Terminal Alternatives
Aspen/Pitkin County Airport
Airport Layout Plan Update Consultancy Services
Scope of Work Fee Schedule
Jacobsen|Daniels Team
TOTAL
COST
Aspen/Pitkin County Airport
Airport Layout Plan Update Consultancy Services
Scope of Work Fee Schedule
Jacobsen|Daniels Team
6.3.1 Develop Terminal Building Alternatives 15,129$
6.3.2 Concourse and Gating Alternatives 14,822$
6.4 Landside Alternatives
6.4.1 Develop Access and Roadway Alternatives 6,396$
6.4.2 Develop Parking Alternatives 4,428$
6.4.3 Develop Terminal Curb and Ground Transportation Alternatives 3,198$
6.5 Support Facilities Alternatives
6.5.1 Corporate/General Aviation 8,487$
6.5.2 Air Traffic Control Tower Siting (Includes FAA Coordination)8,487$
6.5.3 Additional Support Facilities (Employee Housing, Solar Farm, Microgrid, etc.)8,487$
6.6 Cost Estimation
6.6.1 Initial alternatives for Cost Estimation purposes 11,255$
6.6.2 Final Alternatives for Cost Estimation purposes 10,486$
Task 7 Facilities Implementation/Capital Improvement Plan Roadmap 84,624$
7.1 Identify & Prioritize Recommended Development 20,049$
7.2 Sources and Uses of Funds
7.2.1 Available Funding/Funding Plan 24,477$
7.3 Project Sequencing
7.3.1 Phasing Plan 20,049$
7.4 Workplan and Cashflow 20,049$
Task 8 Sustainability & Environmental Overview 28,044$
8.1 Preliminary Review of Sustainability Components
8.1.1 County/Airport/Community Sustainability Goals Assessment 14,022$
8.2 Environmental Overview (Proposed Development Plan)
8.2.1 Review Proposed Development Plan 14,022$
Task 9 AGIS & Airport Layout Plan Set 364,175$
9.1 Update AGIS Imagery & Mapping
Additional AGIS Coordination/Studies 128,743$
9.2 Inventory Validation/GIS Attribution
9.2.1 Develop Airfield Inventory 5,279$
9.2.2 Develop General Aviation Facilities Inventory 5,279$
9.2.3 Develop Support Facilities Inventory 5,279$
9.2.4 Develop Existing Terminal Space Inventory 7,585$
9.2.5 Develop Building Systems Inventory 5,279$
9.2.6 Develop Landside Inventory 5,279$
9.2.7 Existing Landuse Plan Review and Baseline 10,988$
9.3 Complete Full Airport Layout Plan Package
Cover Sheet 6,765$
Data Sheet 15,068$
Existing Airport Layout Drawing 15,068$
Future Airport Layout Drawing 15,068$
Terminal Area Drawing 8,918$
Airport Airspace Drawing 10,148$
Inner Portion of the Approach Surface Drawings 29,623$
Runway Departure Surface Drawings 12,403$
On‐Airport Land Use Drawing 12,608$
Property Map/Exhibit A 12,403$
Address and Coordinate Review Comments 30,074$
9.4 ALP Narrative Report and Workshops
9.4.1 Draft ALP Narrative Report 15,006$
9.4.2 Workshop 7,319$
Task 10 Environmental Processing & Approval 348,503$
10.1 Compare EA Project Components to Proposed Community Changes
10.1.1 Evaluation of Project Components and Anticipated Environmental Impacts 22,480$
10.1.2 Summary of Evaluation and Recommended Approach 15,880$
10.2 Coordinate with FAA on Desired Approach
10.2.1 County and FAA Coordination 15,860$
10.2.2 Other Coordination/Research 5,340$
10.3 Coordinate with FAA on Desired Approach
10.3.1 Incorporate Purpose and Need, Description, and Alternatives Analysis from 10.1 3,930$
TOTAL
COST
Aspen/Pitkin County Airport
Airport Layout Plan Update Consultancy Services
Scope of Work Fee Schedule
Jacobsen|Daniels Team
10.3.2 General Study Area and Base Maps 3,536$
10.3.3 Description of the Affected Environment 46,991$
10.3.4 Air Quality 15,751$
10.3.5 Biological Resources 6,111$
10.3.6 Climate 3,491$
10.3.7 Hazardous Materials 2,511$
10.3.8 Historic and Cultural Resources 5,271$
10.3.9 Land Use 2,891$
10.3.10 Natural Resources and Energy Supply 1,911$
10.3.11 Noise and Noise‐Compatible Land Use 26,651$
10.3.12 Socioeconomic, Environmental Justice, and Children's Environmental Health and Safety Risks 9,011$
10.3.13 Visual Effects 1,851$
10.3.14 Water Resources 4,631$
10.3.15 Cumulative Impacts and Other Considerations 5,611$
10.3.16 Preliminary Draft EA 15,080$
10.3.17 Draft EA 12,740$
10.3.18 Agency/Public Coordination 48,740$
10.3.19 Draft EA Comment Analysis and Response 23,530$
10.3.20 Preliminary Final EA 11,300$
10.3.21 Final EA 9,780$
10.3.22 Supplemental EA Project Management 27,620$
Task 11 Expenses 125,000$
Project Expenses
Travel/Expenses 125,000$
TOTAL PROJECT COST 1,557,751$
Certificate Of Completion
Envelope Id: 04C0F2FFB0F24C37A1211E090ED63F72 Status: Completed
Subject: Jacobsen Daniels, LLC | Pitkin County NTP & Task Order 003.22 A-1 for Review and Signature
Source Envelope:
Document Pages: 43 Signatures: 4 Envelope Originator:
Certificate Pages: 5 Initials: 0 Pitkin County Procurement
AutoNav: Enabled
EnvelopeId Stamping: Disabled
Time Zone: (UTC-07:00) Mountain Time (US & Canada)
530 East Main Street
Suite 203
Aspen, CO 81611
Procurement@PitkinCounty.com
IP Address: 216.147.123.217
Record Tracking
Status: Original
8/17/2022 7:18:09 PM
Holder: Pitkin County Procurement
Procurement@PitkinCounty.com
Location: DocuSign
Signer Events Signature Timestamp
Connie Baker
connie.baker@pitkincounty.com
Budget Director
Pitkin County
Security Level: Email, Account Authentication
(None)
Completed
Using IP Address: 75.71.106.213
Sent: 8/17/2022 7:25:19 PM
Viewed: 8/18/2022 8:27:40 AM
Signed: 8/18/2022 11:34:48 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Dan Bartholomew
dan.bartholomew@aspenairport.com
Airport Director
Aspen/Pitkin County Airport
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 65.38.144.66
Sent: 8/18/2022 11:34:49 AM
Viewed: 8/18/2022 6:29:07 PM
Signed: 8/18/2022 6:30:24 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Brad Jacobsen
brad.jacobsen@jacobsendaniels.com
Executive Vice President
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 98.224.219.78
Sent: 8/18/2022 6:30:25 PM
Viewed: 8/18/2022 7:33:32 PM
Signed: 8/18/2022 7:35:54 PM
Electronic Record and Signature Disclosure:
Accepted: 4/4/2022 1:30:27 PM
ID: 77d74145-4854-4803-b1ec-800580bc02bd
Company Name: Pitkin County, Colorado
Rich Englehart
rich.englehart@pitkincounty.com
Deputy County Manager
Pitkin County
Signing Group: County Manager Group
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 216.189.14.21
Signed using mobile
Sent: 8/18/2022 7:35:56 PM
Viewed: 8/18/2022 9:33:15 PM
Signed: 8/18/2022 9:33:23 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Pitkin County Procurement
procurement@pitkincounty.com
Procurement Manager
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 8/18/2022 9:33:25 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Accounts Payable
AP@pitkincounty.com
Accounts Payable
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 8/18/2022 9:33:26 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 8/17/2022 7:25:19 PM
Certified Delivered Security Checked 8/18/2022 9:33:15 PM
Signing Complete Security Checked 8/18/2022 9:33:23 PM
Completed Security Checked 8/18/2022 9:33:26 PM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Pitkin County (we, us or Pitkin County) may be required by law to provide
you with certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically when we send you documents for
electronic signature.
Acknowledging your Access, Intent, and Consent to Receive and Sign Materials
Electronically
To confirm that you can access this information electronically, which will be similar to other
electronic notices and disclosures that we will provide to you, please verify that you were able to
read this electronic disclosure and that you also were able to print on paper or electronically save
this page for your future reference and access or that you were able to e-mail this disclosure and
consent to an address where you will be able to print on paper or save it for your future reference
and access. Further, if you consent to receive notices and disclosures exclusively in electronic
format on the terms and conditions described above, please let us know by clicking the 'I agree'
button below.
By checking the 'I Agree' box, I confirm that:
I am establishing my intent to be bound to the transaction, and indicating that I am fully
aware of the purpose for which the signature is being provided.
I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
Until or unless I notify Pitkin County as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgments, and other documents that are required to be provided or made
available to me by Pitkin County during the course of my relationship with you.
Signing Documents without a Pitkin County DocuSign Account:
Pitkin County may not require all document signers to be authorized users of the Pitkin County
DocuSign Account. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to these terms and
conditions, please confirm your agreement by clicking the 'I agree' button at the bottom of this
document. When you don't have a DocuSign account, you will be provided the opportunity to
agree to the Legal Disclosure each time you open an "envelope" for signing, at this time, you can
download and retain this disclosure. Pitkin County will forward completed documents that
you've reviewed, processed or signed via email. Should you require copies of these signed
documents (e.g., if they get deleted from your email account) you should request those
documents from Pitkin County under the Colorado Open Records Act by contacting the Pitkin
County custodian who sent you the document for signature.
Signing Documents with a Pitkin County DocuSign Account:
Electronic Record and Signature Disclosure created on: 3/20/2020 3:28:13 PM
Parties agreed to: Brad Jacobsen
Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to these terms and conditions, please
confirm your agreement by clicking the 'I agree' button at the bottom of this document.
Getting paper or electronic copies
At any time, you may request from us a paper or electronic copy of any record provided or made
available electronically to you by us. For such copies, as long as you are an authorized user of
the DocuSign system you will have the ability to download and print any documents we send to
you through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper or
electronic copies of any such documents from our office to you, you may be charged a per-page
fee. You may request delivery of such paper or electronic copies from us by following the
procedure described below.
Withdrawing your consent
If you are an authorized DocuSign Account holder, you can decide to receive notices and
disclosures from us electronically, you may at any time change your mind and tell us that
thereafter you want to receive required notices and disclosures only in paper format. Described
below is the process for informing us of your decision to receive future notices and disclosure in
paper format and also how to withdraw your consent to receive notices and disclosures
electronically.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign 'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign user account to receive required notices and consents electronically from us or to sign
electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgments, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Pitkin County:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to Helpdesk@provelocity.com
To advise Pitkin County of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at Helpdesk@provelocity.com and
in the body of such request you must state: your previous e-mail address, your new e-mail
address .
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper or electronic copies from Pitkin County
To request delivery from us of paper or electronic copies of the notices and disclosures
previously provided by us to you electronically, you should request those documents from Pitkin
County under the Colorado Open Records Act by contacting the Pitkin County custodian who
sent you the document for signature.
To withdraw your consent with Pitkin County
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;