HomeMy WebLinkAboutbocc.con.amended.060.21 A-78/30/2021 CDD
Contract Information
Contract Number
Project Name
Contractor
Budget Line Item 12233150.531000.10007
Procurement Method:
Type:
Contract Start Date
Contract End Date
Contract Type
Retainage
If this is a new contractor, please enter the New Vendor information into Munis for workflow approval.
Contact Information:
Department
County Representative GR Fielding County Representative
Phone (970) 920-5206
Provide a brief description of the Contract or Change Order:
Contract Value Summary:
$ 257,000.00
$ -
$ -
$ 257,000.00
Engineering & Transportation
Task Order to provide preliminary grading and investigate drainage issues related to the existing
site based on any proposed changes to the layout from the architectural disciplines.
Original Contract Amount
Previous Change Order/Amendment Amount
This Change order/Amendment amount
Contract Total
No
Civil Site Design
JVA, Inc
$ 257,000.00
Additional Budget Line
Item(s)
(Please fully allocate New Contract Total)
$ -
$ -
$ -
$ 257,000.00
Formal
Services/Maintenance
10/25/2022
12/31/2023
Task Order
060.21 A-7
Pitkin County
Procurement Cover Sheet
Please complete the Contract Cover Sheet when the contract/task order is complete and fully executed.
Return all Contract Cover Sheets and Contracts/Change Orders/Amendments/Task Orders to Procurement
Master Service Agreement #: 060.21 Rev: 2018-10-10 btf
1
TASK ORDER
Task Order/Project Name: Civil Site Design Task Order Number: A-7 Task Order Budget Line Item: 12233150.531000.10007
OWNER: CONTRACTOR: Pitkin County JVA, Inc. G.R. Fielding – Engineering Cooper Best, Regional Office Manager 76 Service Center Road 817 Colorado Ave, Suite 301 Aspen, CO 81611 Glenwood Springs, CO 81601
Phone: (970) 920-5206 Phone: (970) 987-0354 Gerald.Fielding@PitkinCounty.com CBest@jvajva.com PROJECT NAME: CIVIL SITE DESIGN
START DATE: October 25, 2022 END DATE: December 31, 2023 The Phillips Mobile Home Park Redevelopment Project MSA (the “Agreement”) dated March 1, 2021 between the Board of County Commissioners of Pitkin County (the “County”) and JVA, Inc. 817 Colorado
Ave, Suite 301 Glenwood Springs, CO 81601 (the “Contractor”), shall include the following services.
1. Contractor’s Obligations. Contractor shall provide the engineering services described in the attached letter agreement (“Attachment A”) to provide preliminary grading and investigate drainage issues related to the existing site based on any proposed changes to the layout from the architectural disciplines. JVA
will also provide preliminary design of service extensions and connections to the proposed water and wastewater systems. 2. Compensation and Expenses, Invoicing, Payment and Offset. The County shall compensate Contractor for its services in accordance with the Project Budget and Schedule set out in Paragraph 1
of this Task Order. It is expressly understood and agreed that in no event will the total compensation and reimbursement to be paid hereunder exceed the sum of Two Hundred Fifty-Seven Thousand dollars and Zero cents ($257,000.00) for all services rendered. By Task Order or Task Order Amendment, the County and Contractor may reallocate the budget among project tasks if the total budget amount remains unchanged. Contractor shall invoice for the project monthly based on hours
worked, with payment expected within thirty (30) days of invoice, but any payment by the County may be offset by any amount the Contractor owes the County for any reason.
Master Service Agreement #: 060.21 Rev: 2018-10-10 btf
2
Any invoices not sent in the following manner may have payment delayed. All invoices for this Task
Order shall reference Task Order A-7 and Civil Site Design. Invoices shall be sent electronically in PDF format to Gerald.Fielding@PitkinCounty.com & Romany.Iacono@PitkinCounty.com. 3. Pitkin County’s Obligations. Pitkin County shall administer this contract through a County
Representative. G.R. Fielding, Engineering and Construction Director will manage the project as the
County’s Representative. The services provided and products delivered by the Contractor under this contract will be subject to review by the County’s Representatives, or a designee, for compliance with Contractor’s obligations prior to final payment.
4. Formation of Task Order. This Task Order is issued in accordance with the provisions of the
Agreement. Contractor agrees to provide services subject to the terms of this Task Order and for the avoidance of doubt this Task Order consists of the terms set out in the Agreement. In all other respects the Agreement is in full force and effect and remains unchanged by this Task Order.
JVA, INC.
________________________________________________
!#VENDOR SIGNATURE#! Date PITKIN COUNTY, COLORADO
________________________________________________ !#DEPARTMENT REPRESENTATIVE#!Date
Oct-25-2022
Engineering and Construction Director
Gerald Fielding
Nov-01-2022
Senior Project Manager
JR Spung
September 7, 2022
Mr. Gerald Fielding, County Engineer
Pitkin County
530 East Main
Aspen, CO 81611
Reference: Pitkin County Phillips Mobile Home Park Civil Subconsultant Services –
Task Order for Civil Engineering Subconsultant Services to the Selected
Architect
Dear GR:
JVA, Inc. (JVA) is pleased to submit our proposal to Pitkin County for engineering services
related to the civil subconsultant services for the Pitkin County Phillips Mobile Home Park. JVA
worked on conceptual infrastructure design and understands the County has selected an architect
to progress the design. The scope of work for this proposal is to work with the selected architect
to design the infrastructure improvements around the proposed buildings.
The proposed site sits along both sides of Lower River Road and the Rio Grande Trail in Pitkin
County. The Cerise Ditch also bisects the east parcel. There are 30 existing mobile homes on the
east parcel and one single family home on the west parcel. Pitkin County is proposing to redesign
the access to the north end of the existing mobile homes and are planning on relocating at least
two mobile homes that are currently within the debris flow channel on the north end of the site.
Any relocated mobile homes will be set to the south of the existing homes onsite.
A new access for these relocated mobile homes will be required and this new driveway will also
provide access to the proposed multi-family units east and up the hill from the southern half of
the existing mobile homes. The grade in this area is fairly steep and retaining walls will most
likely be required. JVA will design all these accesses to meet fire truck turnaround requirements.
The initial layout proposed 17 multi-family units east and uphill of the Cerise Ditch. The County
is now contemplating adding additional units in the pasture along Lower River Road.
Layout of water and sewer main extensions from the proposed water tank and wastewater
treatment system will be provided. Layout of dry utility (electric, gas and communication)
extensions will also be shown for coordination. Based on our experience, we anticipate the utility
companies will perform their own final design and the installation will be coordinated by the
contractor.
JVA will provide grading design and investigate drainage issues related to the existing site, and
work with architectural disciplines for site layout. JVA will design the onsite drainage systems,
and coordinate with the design team for sizing and location of drainage structures including any
required stormwater detention and/or water quality enhancement facilities.
Pitkin County Phillips MHP Civil Engineering
September 7, 2022
Page 2 of 5
There are two debris channels located on the existing site. The previously noted one on the north
end of the east parcel and another one towards the south end of the east parcel. From a technical
memo from Tetra Tech dated May 26, 2020, these two debris channels have been preliminarily
analyzed by Tetra Tech. Part of this scope of work is for Tetra Tech to finalize the debris flow
analysis for existing conditions which will in turn be used to define building footprint areas
generally outside of the debris flow limits. Tetra Tech’s proposal is attached to this document.
Areas of debris flow to avoid and design and sizing of channels or infrastructure is included in
this scope of work.
SCOPE OF WORK
Outlined below are key tasks and deliverables for the proposed scope of work. These task are
based on the RFP for Architectural Services for the Affordable Housing Project at Phillips Mobile
Home Park issued on May 13, 2022. Because the number of proposed units and phases of design
are still unknown, fees for the Conceptual Design phase have been provided, but a range of have
been provided for future phases of design.
Conceptual Design
1. JVA will provide preliminary grading and investigate drainage issues related to the existing
site based on any proposed changes to the layout from the architectural disciplines. We will
also provide preliminary design of service extensions and connections to the proposed
water and wastewater systems. The water and wastewater system designs are covered under
a different scope of work through JVA’s environmental design team.
2. We have assumed that detailed site survey and topography will be provided by others. At
this time, we will request any additional surveying efforts and determine the need for
additional geotechnical studies. JVA will gladly assist the owner with obtaining an updated
boundary/design survey, geotechnical report, and traffic study.
3. JVA will produce the conceptual design plans and narrative, including rough earthwork
calculations, required for this phase of design. Weekly team coordination meetings, one
charette meeting and one Owner review is anticipated.
Schematic Design
4. JVA will refine the grading to the one-foot contour interval. JVA will design the onsite
drainage systems, and coordinate with the design team for sizing and location of drainage
structures, including roof, courtyard and foundation drain outfall connections. JVA will
refine the layout of the site access and parking areas. We assume the architectural
disciplines will address layout and grading at detailed plaza areas and other special site
features.
5. JVA will coordinate with the local review agencies, including the Roaring Fork Fire
Rescue fire department. Private onsite water and sewer services to the buildings and main
extensions will be coordinated with the internal JVA environmental design team. We have
assumed that the Fire Department will also require review of the proposed facilities and
hydrant locations.
Pitkin County Phillips MHP Civil Engineering
September 7, 2022
Page 3 of 5
6. JVA will produce the schematic design plans and specifications. We will update the
preliminary earthwork calculations with the more refined grading where applicable. JVA
will provide quantities and opinions of probable costs for civil engineering components.
Weekly coordination meetings with the CLIENT and other project team members are
anticipated.
Design Development/Land Use Process
7. JVA will assist the CLIENT with the PITKIN COUNTY review process. We assume the
CLIENT or owner will complete applications and pay submittal fees. JVA will submit
review drawings for grading & drainage, erosion control, and utilities. JVA will prepare
and submit the Final Drainage Report as required by the municipality. We have assumed
that this report will address site drainage system design and erosion control issues. Based
on our understanding of the site, design of stormwater detention and water quality
enhancement facilities are included. Water and sewer will be prepared by JVA
environmental approved by CDPHE.
Construction Documents
8. JVA will continue to refine the grading from the design development to the final grading
required on the site with critical spot elevations provided. Storm sewer inlets, piping,
grass-lined swales and drainage features will be designed. Estimated earthwork
calculations are anticipated.
9. The water and sanitary sewer connections for the building will also be detailed in this phase
Utility profiles will be provided. We will coordinate with mechanical engineer and
landscape architect for service taps and meters. JVA will assist owner in the easement
process by delineating easements and provided easement CAD files. We assume a licensed
land surveyor will produce all required easement legal descriptions and exhibits, and the
owner will coordinate the easement submittal process.
10. CLIENT and project mechanical/electrical/plumbing engineer will make contact with gas,
electric, telephone, data and other non-municipal utility companies with regard to the utility
service extensions, realignment, load sizing, building entry points, and/or undergrounding
of said utilities. JVA will work with the CLIENT and design team for related site
coordination. JVA will show these non-municipal utilities on our preliminary and final
engineering plans based on design information provided by others. Based on our
experience, we anticipate the utility companies will perform their own final design and the
installation will be coordinated by the contractor.
11. JVA will finalize the design of the sidewalk, parking and access drive extensions for the
site and produce a horizontal control plan with signage and striping. We anticipate
receiving pavement design criteria from the project's geotechnical consultant.
12. JVA anticipates that the architect, mechanical engineer and/or landscape architect will
perform the required design for internal building features including internal roof drains,
perimeter and underslab drains, internal plaza areas, internal/below-grade parking areas,
sump/pump pits, etc., and that JVA will provide support to these efforts by coordinating
exterior connections to adjacent utilities from these internal designs. Perimeter/underdrain
and groundwater remediation design and support are not included at this time.
Pitkin County Phillips MHP Civil Engineering
September 7, 2022
Page 4 of 5
13. JVA will produce the construction plans, technical specifications for pertinent civil
engineering sections, and applicable reports, and update the construction opinion of
probable cost. We will attend weekly coordination meetings with CLIENT and other
project team members to complete the document review process.
Bid and Construction Phase Services
14. Bid phase services include attendance at the prebid meeting and addendum preparation.
Services during construction comprise of the review of product submittals, change order
documentation, and response to contractor information requests for civil engineering
related items. Any combination of six site meetings (construction kick-off meeting, site
observation visits, and/or punchlist meeting) will also be included during the work
progress. Construction record drawings will be produced from contractor submitted
records. We have assumed that the CLIENT will provide the lead on all the bidding and
construction services for this project.
Subconsultant Services
15. DEBRIS FLOW: Tetra Tech has provided a proposal to provide the debris flow study for
the project. Tetra Tech provided a preliminary debris flow report in 2020. The scope of
work for this study is finalize that report and provide final locations, channel and
infrastructure sizes for the debris flows on this project site.
BASIS OF PAYMENT
The basis of payment for the scope of work described above will be monthly billings based on the
percentage of lump sum completed to date including reimbursable expenses. Standard
reimbursable expenses including mileage, shipping and printing are included. Airfare, car rental,
meals and lodging are considered extra and shall be billed at 1.1 times direct cost. This amount
will not be exceeded without written authorization of the CLIENT.
Basic Civil Engineering Services
Conceptual Design $ 17,500
Debris Flow Subconsultant $ 33,000
TOTAL LUMP SUM FEE $ 50,500
Pitkin County Phillips MHP Civil Engineering
September 7, 2022
Page 5 of 5
Note: The exact scope of work is not known at this early stage of the project. The number of
proposed units has not been finalized and the infrastructure required to design these additional
units would greatly affect the design fees for the project. A preliminary budget range is included
for your use. Note that this is our best guess at this time and the actual ranges may vary:
Schematic Design $ 22,000 - $ 45,000
Design Development $ 30,000 - $ 68,000
Construction Documents $ 50,000 - $ 90,000
Bid and Construction Services $ 12,000 - $ 24,000
Exclusions: Services resulting from significant changes to the project scope, significant bid
alternate design, rezoning/replatting, and significant site plan changes and additional design
work or plans related to field conditions or contractor issues after plans are complete that could
not have been reasonably foreseen may require extension of the time scheduled for our work and
additional fees. Additional municipal submittals or public hearings required for planning
department review and approval will be considered additional services may require extension of
the time scheduled for our work and additional fees.
SCHEDULE
JVA anticipates aligning our deliverable schedule with the selected architect.
We appreciate the opportunity to work with the County on this important project. If you have
any questions about this letter or the scope described herein, please do not hesitate to contact me.
Sincerely,
_____________________________
J.R. Spung, P.E.
Senior Project Manager/Regional Engineering Manager
Attachments: Tetra Tech Philips Mobile Home Park Debris Flow Analysis Scope of Work
Accepted by:
PITKIN COUNTY
______________________________
Title Date
Phillips Mobile Home Park
Debris Flow Analysis
August 2022
Phillips Mobile Home Park Mudflow Hazard Overview
Page 1
SCOPE OF WORK
Pitkin County is preparing a site plan for the Phillips Mobile Home Park (Project). The property is located
along the Roaring Fork River, east of Highway 82, approximately 10 miles north of Aspen, Colorado. The
property boundary spans both the east and west sides of the river, however, little or no redevelopment
is proposed on the west side. The eastern part of the project area is located on several alluvial fan deposits
as shown on the Geological Map of the Woody Creek Quadrangle published by the Colorado Geological
Survey (CGS) (USGS GQ-967 1). Three site plan options for the Project were developed by DHM Design
dated December 12, 2018. These plans showed three levels of density and the potential relocation of four
mobile home sites from the west side of the Roaring Fork River to the east side. The site plan options
were the basis for a preliminary mudflow hazard evaluation (see Draft Technical Memorandum from Tetra
Tech (Tetra Tech, 2019) to SGM December 3, 2019).
We understand it is the desire of Pitkin County to complete the mudflow analysis ahead of, or in concert
with the development of the final site plan. The purpose of this scope of work is to prepare a mudflow
analysis for existing conditions which will in turn be used to define building footprint areas generally
outside of the mudflow limits. To accomplish this the following tasks are proposed.
Task 1. Utilize the representative clear-water flood hydrographs for the 2-hour 25-year event and
2-hour 100-year peak flow rainfall event developed by Tetra Tech in the preliminary mudflow
hazard evaluation. The flood hydrographs were developed using the HEC-HMS hydrologic
modeling software and existing available soils mapping.
Task2: Develop a hydraulic model for existing conditions using the FLO-2D software program that
was specifically developed to evaluate mudflows. The model will include the north and middle
basins. For purposes of this scope of work and fee estimate it is assumed that GIS files of the
existing topographic mapping shown on the preliminary site plans will be available electronically
for use in the FLO-2D model. If additional survey data is required, this will be discussed with and
provided by the property owner and owner’s representative. It is anticipated that the FLO-2D
model will have a grid size on the order of 10 to 25 feet.
Task 3. Representative inflow hydrographs will be developed and input into the debris flow
models. The model will be run over the 2-hour 25-year event and 2-hour 100-year event. The FLO-
2D model output for the existing condition will be mapped to show the extents and depths of the
debris flow. This mapping will be provided electronically to Pitkin County for use in developing a
site plan. Tetra Tech will also provide direction for site plan development including the following:
Summarize guidelines, criteria and recommendations for development on active alluvial
fans as required by Pitkin County, FEMA, the Colorado Geological Survey, and other
communities with mud and debris flow regulations.
Identify potential flood hazards areas utilizing guidelines presented in FLO-2D, which uses
the ‘Swiss Method’ adapted from OFEE et al. 1997 and assigns a flood hazard index (FHI)
of low, medium and high as a function of flow depth and velocity on active alluvial fans.
Develop preliminary recommendations regarding channel location and dimensions,
culvert locations and sizes, and guidelines on building locations and first floor elevations.
Phillips Mobile Home Park
Debris Flow Analysis
August 2022
Phillips Mobile Home Park Mudflow Hazard Overview
Page 2
Task 4: For purposes of this scope of work and fee estimate we are assuming once the site plan is
developed and overlaid with the mudflow boundaries, a revised FLO2D model will be executed to
reflect site improvements. Thus, two additional model runs are proposed in order to refine the
site plan to reflect recommendations and prepare the final proposed conditions model.
Task 5: Prepare a summary report and include written recommendations developed from Task 3
and informed in Task 4 including limits of development on the site plan to avoid a debris flow
event, building freeboard requirements (typically height above finished grade adjacent to
structures, and culvert and channel recommendations.
For purposes of this scope of work Tetra Tech is assuming the preliminary site plan and proposed grading
will be completed by others and provided by Pitkin County as well as CAD files for use in developing the
terrain model for both existing and proposed conditions.
QUALIFICATION OF SERVICES
This scope of work is for debris flow hazard characterization of existing conditions only and does not
include geotechnical analysis of slope stability, rock fall hazard, floodplain, or specific design of mitigation
features. In addition, the scope of work and fee estimate assume grading plans and site layout of
proposed conditions will be provided by Pitkin County.
FEE ESTIMATE AND SCHEDULE
Fees for this proposal are based on a lump sum contract for a total cost of $30,000. Tetra Tech’s rates
increase by 3% on January 1, 2023, and there will be a commensurate increase in project cost should the
project extend into 2023.
1 Existing conditions model parameters $ 644
2 Hydrology, 25 and 100 yr $ 570
3 FLO-2D Model Development $ 3,286
4 Existing Conditions Model $ 7,408
5 Proposed Conditions Model w/2 iterations $ 10,856
6 Technical Report $ 7,236
Total Hours
TOTAL COST $ 30,000
Task Description
Total by
Task
Rev. 2018-10-10 btf
NOTICE TO PROCEED DATE: 10/25/2022
TO: JVA, Inc
817 Colorado Avenue, Suite 301 Aspen, CO 81611 FROM: Pitkin County
530 E. Main St., Suite 302
Aspen, Colorado 81611 JVA, Inc is hereby authorized to proceed on 10/25/2022 or within ten (10)
consecutive calendar days thereafter, with the work covered by Pitkin County Contract
# 060.21 A-7. The work must be coordinated with Gerald Fielding, Engineering and Construction Director at 970-920-5206 or gerald.fielding@pitkincounty.com.
PITKIN COUNTY _________________________________________________
!#DEPARTMENT REPRESENTATIVE#!Date
Gerald Fielding
Engineering and Construction Director
Oct-25-2022
Certificate Of Completion
Envelope Id: FD06AD75855645A1B050AF206FB115C1 Status: Completed
Subject: JVA, Inc | Pitkin County Task Order 060.21 A-7 for Review and Signature
Source Envelope:
Document Pages: 11 Signatures: 3 Envelope Originator:
Certificate Pages: 5 Initials: 0 Pitkin County Procurement
AutoNav: Enabled
EnvelopeId Stamping: Disabled
Time Zone: (UTC-07:00) Mountain Time (US & Canada)
530 East Main Street
Suite 203
Aspen, CO 81611
Procurement@PitkinCounty.com
IP Address: 98.50.0.31
Record Tracking
Status: Original
10/25/2022 9:20:18 AM
Holder: Pitkin County Procurement
Procurement@PitkinCounty.com
Location: DocuSign
Signer Events Signature Timestamp
Gerald Fielding
gerald.fielding@pitkincounty.com
Engineering and Construction Director
Pitkin County
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 65.38.144.66
Sent: 10/25/2022 9:24:10 AM
Viewed: 10/25/2022 9:28:34 AM
Signed: 10/25/2022 12:21:03 PM
Electronic Record and Signature Disclosure:
Accepted: 5/4/2020 2:25:51 PM
ID: 119874e5-b793-4ad0-a348-718953f54cfb
Company Name: Pitkin County, Colorado
JR Spung
jspung@jvajva.com
Senior Project Manager
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 209.209.96.55
Sent: 10/25/2022 12:21:06 PM
Resent: 10/25/2022 12:40:11 PM
Viewed: 10/25/2022 12:40:51 PM
Signed: 11/1/2022 11:27:25 AM
Electronic Record and Signature Disclosure:
Accepted: 10/25/2022 12:37:26 PM
ID: 39812f6c-061a-44b4-9f82-6b8a6cf8af51
Company Name: Pitkin County, Colorado
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Pitkin County Procurement
procurement@pitkincounty.com
Procurement Manager
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 11/1/2022 11:27:27 AM
Resent: 11/1/2022 11:27:31 AM
Viewed: 11/1/2022 11:48:58 AM
Carbon Copy Events Status Timestamp
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Accounts Payable
AP@pitkincounty.com
Accounts Payable
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 11/1/2022 11:27:28 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 10/25/2022 9:24:10 AM
Certified Delivered Security Checked 10/25/2022 12:40:51 PM
Signing Complete Security Checked 11/1/2022 11:27:25 AM
Completed Security Checked 11/1/2022 11:27:28 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Pitkin County (we, us or Pitkin County) may be required by law to provide
you with certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically when we send you documents for
electronic signature.
Acknowledging your Access, Intent, and Consent to Receive and Sign Materials
Electronically
To confirm that you can access this information electronically, which will be similar to other
electronic notices and disclosures that we will provide to you, please verify that you were able to
read this electronic disclosure and that you also were able to print on paper or electronically save
this page for your future reference and access or that you were able to e-mail this disclosure and
consent to an address where you will be able to print on paper or save it for your future reference
and access. Further, if you consent to receive notices and disclosures exclusively in electronic
format on the terms and conditions described above, please let us know by clicking the 'I agree'
button below.
By checking the 'I Agree' box, I confirm that:
I am establishing my intent to be bound to the transaction, and indicating that I am fully
aware of the purpose for which the signature is being provided.
I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
Until or unless I notify Pitkin County as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgments, and other documents that are required to be provided or made
available to me by Pitkin County during the course of my relationship with you.
Signing Documents without a Pitkin County DocuSign Account:
Pitkin County may not require all document signers to be authorized users of the Pitkin County
DocuSign Account. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to these terms and
conditions, please confirm your agreement by clicking the 'I agree' button at the bottom of this
document. When you don't have a DocuSign account, you will be provided the opportunity to
agree to the Legal Disclosure each time you open an "envelope" for signing, at this time, you can
download and retain this disclosure. Pitkin County will forward completed documents that
you've reviewed, processed or signed via email. Should you require copies of these signed
documents (e.g., if they get deleted from your email account) you should request those
documents from Pitkin County under the Colorado Open Records Act by contacting the Pitkin
County custodian who sent you the document for signature.
Signing Documents with a Pitkin County DocuSign Account:
Electronic Record and Signature Disclosure created on: 3/20/2020 3:28:13 PM
Parties agreed to: Gerald Fielding, JR Spung
Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to these terms and conditions, please
confirm your agreement by clicking the 'I agree' button at the bottom of this document.
Getting paper or electronic copies
At any time, you may request from us a paper or electronic copy of any record provided or made
available electronically to you by us. For such copies, as long as you are an authorized user of
the DocuSign system you will have the ability to download and print any documents we send to
you through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper or
electronic copies of any such documents from our office to you, you may be charged a per-page
fee. You may request delivery of such paper or electronic copies from us by following the
procedure described below.
Withdrawing your consent
If you are an authorized DocuSign Account holder, you can decide to receive notices and
disclosures from us electronically, you may at any time change your mind and tell us that
thereafter you want to receive required notices and disclosures only in paper format. Described
below is the process for informing us of your decision to receive future notices and disclosure in
paper format and also how to withdraw your consent to receive notices and disclosures
electronically.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign 'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign user account to receive required notices and consents electronically from us or to sign
electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgments, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Pitkin County:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to Helpdesk@provelocity.com
To advise Pitkin County of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at Helpdesk@provelocity.com and
in the body of such request you must state: your previous e-mail address, your new e-mail
address .
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper or electronic copies from Pitkin County
To request delivery from us of paper or electronic copies of the notices and disclosures
previously provided by us to you electronically, you should request those documents from Pitkin
County under the Colorado Open Records Act by contacting the Pitkin County custodian who
sent you the document for signature.
To withdraw your consent with Pitkin County
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an e-mail to Helpdesk@provelocity.com and in the body of such a request, you
must state your e-mail, full name, Postal Address, telephone number, and account
number.