HomeMy WebLinkAboutbocc.con.amended.073.23 D8/30/2021 CDD
Contract Information
Contract Number
Project Name
Contractor
Budget Line Item M2001-Construct-Technology
Procurement Method:
Type:
Contract Start Date
Contract End Date
Contract Type
Retainage
If this is a new contractor, please enter the New Vendor information into Munis for workflow approval.
Contact Information:
Department
County Representative Michael Port County Representative
Phone (970) 379-2031
Provide a brief description of the Contract or Change Order:
Contract Value Summary:
$ 1,817,000.00
$ 89,427.00
$ 29,770.00
$ 1,936,197.00
Administration
Amendment to scope of work and allocate additional funds in the amount of $29,770.00 for BESS dispatch
scheduling feature
Original Contract Amount
Previous Change Order/Amendment Amount
This Change order/Amendment amount
Contract Total
No
AABC Battery Energy Storage System (BESS) Purchase
WEG Electric Corp.
$ 29,770.00
Additional Budget Line
Item(s)
(Please fully allocate New Contract Total)
$ -
$ -
$ -
$ 29,770.00
Formal
Goods, Equipment, Supplies
11/2/2023
12/31/2025
Change Order/Contract Amendment
073.23 D
Pitkin County
Procurement Cover Sheet
Please complete the Contract Cover Sheet when the contract/task order is complete and fully executed.
Return all Contract Cover Sheets and Contracts/Change Orders/Amendments/Task Orders to Procurement
Contract #: 073.23 Rev. 2018.06.13 btf Budget Line Item #: M2001-Construct-Technology
*Increases over $25,000 and/or 10% (single increase or accumulative) of original contract must
have County Manager signature. 1
CHANGE ORDER / CONTRACT AMENDMENT
Change Order Number: 073.23 D
OWNER:
Pitkin County, Colorado
530 E. Main St., Suite #302
Aspen, CO 81611
CONTRACTOR:
WEG Electric Corp
6655 Sugarloaf Parkway
Duluth, GA 30097
The Provision of AABC BESS 1 (the “Contract”) dated November 2, 2023 between the Board of
County Commissioners of Pitkin County, Colorado (the “County”) and WEG Electric Corp (the
“Contractor”), is hereby amended as follows:
Description of Change:
1. Amendment to scope of work to incorporate the design, engineering and testing of a
dispatch scheduling feature within BESS controls as described in (“Attachment A”).
2. Allocation of additional $29,770.00
Reason for Change:
Implementation of the dispatch scheduling feature will maximize financial value of the BESS
system, improve system longevity, and support grid stability by automating optimal times to
discharge the energy based on a defined schedule.
Original Contract Amount $ 1,817,000.00
Previous Change Order/Amendment Amount $ 89,427.00 This Change Order/Amendment Amount $ 29,770.00
New Contract Total $ 1,936,197.00
Contract #: 073.23 Rev. 2018.06.13 btf Budget Line Item #: M2001-Construct-Technology
*Increases over $25,000 and/or 10% (single increase or accumulative) of original contract must
have County Manager signature. 2
In all other respects, the Contract is in full force and effect and remains unchanged by this
Amendment.
WEG ELECTRIC CORP
________________________________________________ !#VENDOR SIGNATURE#! Date
PITKIN COUNTY, COLORADO
RECOMMENDED FOR APPROVAL:
_________________________________________________ !#DEPARTMENT REPRESENTATIVE#! Date
COUNTY MANAGER APPROVAL:
________________________________________________ !#COUNTY MANAGER#!
Climate Action Analyst
Jul-31-2025
Michael Port
Peter N. Barry
President
Aug-01-2025
Deputy County Manager
Aug-05-2025
Kara Silbernagel
Customer: Pitkin County, CO Ref: AACB_BESS1 Battery Energy Storage System Dispatch Scheduling Feature
TECHNICAL & COMMERCIAL OFFER
DATE: July 9, 2025
Dispatch Scheduling Feature
Attachment A
WEG Electric Corp
Page: 2 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
QUOTE REVISION HISTORY
REVISION DATE DESCRIPTION OF REVIEW
01 07/09/2025 First issue
ATTN: G.R. Fielding gerald.fielding@pitkincounty.com
Michael Port michael.port@pitkincounty.com
On behalf of WEG, I would like to thank you for providing us the opportunity to submit this proposal. We believe you will find that WEG’s ability to deliver tailor made solutions to your energy storage needs will make us your choice for this project. For any further information you may need, please do not hesitate to contact us. We hope you appreciate our offer and we look forward to working with you.
Kyle Ellis Sr. Project Manager Battery Energy Storage
Phone: (802) 595-2504 Email: kellis@weg.net
Giampaolo Costabeber
Mgr., Engineering and Project Management – BESS Phone: (678) 780-0164 Email: giampaolo@weg.net
Attachment A
WEG Electric Corp
Page: 3 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
TABLE OF CONTENTS
1.1 SCOPE OF WORK OVERVIEW __________________________________________________ 4
1.2 COMMERCIAL OFFER ________________________________________________________ 4
1.3 IMPLEMENTATION DETAILS ____________________________________________________ 5
1.3.1 GENERIC DISPATCH EVENT ___________________________________________________ 5
1.3.2 DISPATCH INPUT PARAMETERS_________________________________________________ 5
1.3.3 SCHEDULING INPUT PARAMETERS ______________________________________________ 6
1.3.4 USER INTERFACE ___________________________________________________________ 6
1.3.5 AUTOMATION INTERFACE _____________________________________________________ 7
1.3.6 ALERTS __________________________________________________________________ 7
1.3.7 STATUS OUTPUTS __________________________________________________________ 7
1.3.8 EXECUTION _______________________________________________________________ 8
1.3.9 END OF DISPATCH EVENT ____________________________________________________ 8
1.3.10 SCENARIOS _______________________________________________________________ 8
1.3.11 OTHER CONSIDERATIONS_____________________________________________________ 9
1.3.12 ADDITIONAL NOTES ________________________________________________________ 10
Attachment A
WEG Electric Corp
Page: 4 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
1.1 Scope of Work Overview
This document serves as a technical and commercial proposal to design, engineer and test a scheduling dispatch feature in WEG BESS controls and also advise how a customer can automate it. Once implemented the client will be capable of scheduling a dispatch by providing the input parameters (see sections
1.3.2 and 1.3.3) via a Modbus or DNP3 protocol interface to the BESS controller. Alternatively, using the Acuity User Interface (UI), the client will be able to manually define, schedule, view, edit or cancel a dispatch. Up to (5) five dispatches may be scheduled at any given time. The proposed solution includes the necessary updates to the BESS User Manual and The BESS Controller & User Interface Manual.
The proposal scope excludes any WEG operation, monitoring, or service support once the feature has been implemented. 1.2 Commercial Offer
Item Product Description Total Prices (USD)
10 BESS Scheduling Feature including updates to the Acuity User Interface, BESS Controller & User Interface Manual and BESS User Manual. Price
includes remote testing of the feature with Client
$29,770
Acceptance of this proposal shall be in the form of a change order to the existing contract for the BESS (073.23) The expected delivery of the feature is (6) six weeks after WEG acceptance of issued change order.
This offer is valid for 30 days, counted from date of proposal
Attachment A
WEG Electric Corp
Page: 5 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
1.3 Implementation Details
1.3.1 Generic Dispatch Event
A dispatch is a planned, steady discharge of the battery for a set period, for purposes of peak reduction. They may be used to reduce a large customer’s load during peak times, or provided as a service to a utility. A generic dispatch
event has these segments:
• Pre-charge – BESS charges at fixed rate towards a starting SOC level. The BESS will go to Standby state
(be idle) once it reaches the target.
• Curtailment 1 – A period before the scheduled discharge where no more charging is allowed. All charging
must be complete before the curtailment starts. The BESS will be in Standby state.
• Discharge – BESS discharges at fixed rate for specified time.
• Curtailment 2 – A period after the scheduled discharge before recharging is allowed. The BESS will be in
Standby state.
• Recharge – BESS charges at fixed rate to final SOC level. No end time is given; charging continues until
the final SOC is reached, at which point the BESS turns off and the event ends.
The term “dispatch” refers to the entire sequence.
1.3.2 Dispatch Input Parameters
A dispatch is defined with these parameters:
• Pre-charge kW – power to use when pre-charging (absolute value)
• Pre-charge SOC – desired SOC at start of discharge
• Pre-charge Hours – minimum amount of time before the curtailment to begin pre-charging (optional, can be
used to enforce more margin than BESS calculates)
• Curtail 1 Hours (optional; use when curtailment is needed)
• Discharge kW – power to use when discharging
• Discharge Hours – desired length of discharge
• Discharge Min SOC – a do-not-exceed value; the discharge will terminate early if this SOC is reached
• Curtail 2 Hours (optional; use when curtailment is needed)
• Recharge kW – power to use when recharging (absolute value)
• Recharge SOC – desired SOC to leave system at when dispatch event ends
This is an example of a dispatch that charges to 100% and aims to discharge to 30% over three hours. After a curtailment period, the unit(s) recharge to 75%. Named parameters are italicized.
Pre-charge kW ½ of Discharge kW
Pre-charge SOC 100%
Pre-charge Hours 3 hours minimum
Curtail 1 Hours 1 hour
Discharge kW Calculated for 70% of capacity
Discharge Hours 3 hours
Discharge Min SOC 20% reserve
Curtail 2 Hours 1 hour
Recharge kW ½ of Discharge kW
Recharge SOC 75% desired resting charge
Attachment A
WEG Electric Corp
Page: 6 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
1.3.3 Scheduling Input Parameters
A dispatch is scheduled with these parameters:
• Dispatch Date – date of dispatch event
• Discharge Time – start time of Discharge segment
• Dispatch Enable – True/False to enable or disable
Note, the scheduled starting time is for when the actual requested discharge is to begin. The dispatch event as a
whole begins earlier, when the BESS starts pre-charging. Successful scheduling means that a valid dispatch was defined, and a starting date and time sometime in the future
have been set. A valid set of parameters means:
• Combination of discharge power and time are within BESS kW and kWh ratings.
• Min SOC is below expected SOC at end of discharge.
1.3.4 User Interface
All dispatch and scheduling input parameters and statuses are shown on a dedicated screen within the Acuity User Interface (UI). From here, a discharge event can be manually defined, scheduled, viewed, edited or cancelled. Up
to (5) discharge events can be scheduled at any given time.
The UI shall be updated to include a Scheduling tab with features similar as shown in the following figure.
Attachment A
WEG Electric Corp
Page: 7 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
1.3.5 Automation Interface In addition to manual scheduling via the UI, a more automated approach can be used via the customer Modbus or DNP3 interface. All dispatch and scheduling input parameters and status tags are available on the interface., so an external automation controller can define, schedule, monitor, edit and cancel a dispatch. If the automation controller is able to receive dispatch requests from the utility, it could extract the necessary information and write them to the BESS. The automation controller doesn’t need to execute the dispatch in real time; it just sends the BESS the information it needs so the BESS can execute it. All input parameters must be provided: any parameters that aren’t extracted from the utility’s request must be calculated in the automation controller or given default values. Requests for multiple events can be accepted by the BESS, up to 5 as currently envisioned (ex. utility schedules a dispatch before an existing scheduled dispatch has been executed).
Any automation is outside of WEG scope. BESS controls cannot receive and process dispatch requests from a
utility, but easily interfaces with external controllers that can.
1.3.6 Alerts
There are two possible sources for alerts. One is the clients automated controller using the statuses defined in the following section “Status Outputs”. The other option is using the email or SMS message features in Acuity to generate alerts based on the statuses hitting specific values, for instance, Schedule Status ever being set to Partial or Blocked. This can alert an operator that the dispatch is at risk, and give them a chance to remedy the situation before the
dispatch begins.
1.3.7 Status Outputs There are several tags providing status.
• Schedule Status – An enumerated value that describes the overall state of the event:
0 - None Nothing scheduled
1 - Invalid Invalid parameter set or schedule (see below)
2 - Disabled Valid parameters and schedule defined, not enabled
3 - Ready Dispatch scheduled; all BESS units Available
4 - Active Dispatch in process; all BESS units Available
5 - Partial Dispatch scheduled or in process; some BESS units Unavailable or otherwise unable to contribute (reduced capability) 6 - Blocked Discharge scheduled or in process; no BESS units Available
• Dispatch State (per unit) – An enumerated value describing where each unit is in the dispatch:
0 - None No ongoing dispatch
1 – Pre-charge In Pre-charge segment, charging
Attachment A
WEG Electric Corp
Page: 8 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
2 - Discharge In Discharge segment, discharging
3 - Recharge In Recharge segment, charging
4 - Idle In Pre-charge, Discharge or Recharge segment, but unit is in Standby state
because target or minimum SOC has been reached. 5 - Curtailed In either curtailment segment; unit is in Standby state
6 - Offline Not Available (unit faulted, out of service, etc.)
• Event Start – countdown timer telling approximately when pre-charge will start.
• Event Start Units – enumeration: 0 – None, 1 - Days, 2 - Hours, 3 – Minutes
1.3.8 Execution
Once scheduled, execution of the dispatch is handled entirely in BESS controls. No further operator action is needed, other than to address any fault conditions that might prevent units from turning on, or to edit or cancel the dispatch.
The BESS controller does not assume any initial SOC, or even that units will be at the same SOC. As the scheduled start time approaches, the BESS will monitor the SOC of each unit, and estimate how long it will take to charge that
unit to the desired starting SOC at the specified rate. The BESS will take the longest of those times (from the unit with lowest SOC), add some margin, and also add any curtailment duration. This is the latest that the dispatch event
will start, and depends on the initial SOC. The event can be forced to start at an earlier, specific time by specifying Pre-charge Hours.
When it’s time to start, the BESS turns all units on (if not already on) and starts pre-charging toward the target SOC
at the specified rate. The allocation method will be By Rating, and SOC balancing will be disabled, so each unit will make the same power.
As each unit reaches the target SOC, it goes to Standby state. The other online units maintain the same command,
so the overall power drops with each unit reaching SOC. When all units reach SOC the entire BESS will be idle (Standby state), and it will remain so through the end of the Pre-charge segment and any pre-discharge curtailment.
At the scheduled discharge time, all units will go Active with the same power level. They will make this power steadily until either the scheduled duration is reached, or the unit reaches minimum SOC. After the discharge time is over,
units will go to Standby if there is a curtailment period, otherwise they immediately start recharging.
1.3.9 End of Dispatch Event The event ends when all units have recharged to the desired Recharge SOC level. Schedule Status and all unit Dispatch States go to None, the Discharge Time and Date (which are now in the past) are cleared, and Dispatch Enable is set False. The other parameters are preserved in memory, so a similar dispatch could be done in the future by setting a new starting date and time.
1.3.10 Scenarios
1. BESS reaches initial SOC before curtailment begins. Expected behavior. Each unit will sit in Standby for
the remainder of the pre-charge segment, and throughout the pre-curtailment segment (Dispatch States =
Idle, and then Curtailed).
2. BESS is unable to reach initial SOC before pre-curtailment begins. Unexpected behavior. Units will sit in
Standby (Dispatch State = Idle) for the pre-curtailment segment, and then start the discharge at lower-than-
expected SOC. The required discharge can still be completed if there is enough margin at the low end
(min SOC is sufficiently below expected discharge SOC).
3. BESS completes the discharge without reaching minimum SOC level. Expected behavior. Units will sit in
Standby state for any post-curtailment segment and then start recharging.
4. BESS reaches minimum SOC before discharge ends. Unexpected behavior. Unit will sit in Standby state
for the remainder of the Discharge segment, and throughout any post-curtailment (Dispatch States = Idle,
and then Curtailed).
5. BESS has a fault before the scheduled dispatch event. Schedule Status goes to Blocked or Partial. If an
operator is able to reset the fault, Schedule Status goes back to Ready.
Attachment A
WEG Electric Corp
Page: 9 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
6. BESS unit has a fault during the scheduled dispatch event. Schedule Status goes to Blocked or Partial.
Dispatch State of any affected units goes to Offline. If units can be reset and restarted, the dispatch can
continue.
7. Event needs to be cancelled – set Enable flag input false. Schedule Status changes to None.
This example shows Scenarios 2 & 4 above, where the pre-charge is interrupted long enough to affect the delivered energy. Note that during most of the discharge segment there is full Capability (available power) but reduced Capacity (stored energy).
Figure 1 - Interrupted Dispatch
1.3.11 Other Considerations
These quantities are also defined, but don’t exist as separate parameters:
• Initial SOC – whatever the SOC is before Pre-charge begins. This can vary between units, and the lowest
value determines in part when Pre-charge must begin. This might be a designated resting SOC if the
system is generally idle except for dispatch events, but it could be anything else if the system is used for
other activities.
• Pre-charge Margin – amount of extra time allocated to the Pre-charge segment, beyond the minimum
needed to charge from the initial SOC to the Pre-charge SOC. Since the relationship between charge or
discharge energy and change in SOC is somewhat approximate, sufficient extra time should be provided to
ensure that the battery is sufficiently charged before curtailment or discharge is scheduled to begin. Extra
margin also gives time to recover from a fault if one occurs during Pre-charge.
• Expected Discharge SOC – the anticipated remaining SOC value after constant discharge from the Pre-
charge SOC for the specified Discharge Hours. This is approximate.
Attachment A
WEG Electric Corp
Page: 10 / 10
WEG Electric Corp 6655 Sugarloaf Parkway, Duluth, GA, 30097 – www.weg.net AABC_BESS1 - Proposal WEG Scheduling Feature_v01.docx
• Reserve Capacity – Extra SOC capacity (specified by Discharge Min SOC) that is kept in reserve and not
used for the dispatch. This may be important for microgrid applications, but can be zero for other
applications.
• Discharge Margin – Difference between the expected discharge SOC and Discharge Min SOC. This is the
amount of “headroom” the dispatch has. Margin is useful for when a unit is unable to charge to the desired
starting SOC, or to account for the approximate nature of the energy/SOC relationship. It could be set to
zero if failing to satisfy the complete request does not incur significant penalties.
1.3.12 Additional Notes Curtailment
Charging the battery adds load (demand) to the utility. Since the purpose of a dispatch is to reduce peak demand during some period, the act of charging immediately before or after can be detrimental, and could potentially increase peak demand over what it might have been with no dispatch. This adverse effect can be mitigated by charging at a slower rate and/or aiming to finish the charge some time before the dispatch is scheduled to begin. For this reason, the utility may impose curtailment periods immediately before and after the discharge event, or may specify a maximum charge rate. The pre-discharge curtailment period sets a hard limit on when pre-charge must finish. Ideally pre-charge would have finished well before this, because the starting time would have been calculated with enough margin. Post-discharge curtailment merely imposes an idle time before recharging. Discharge Min SOC
The discharge will continue for the specified duration or until the specified minimum SOC is reached. For microgrid applications, this value should be set to the minimum reserve capacity wanted for resiliency, should the BESS be called upon to black start the microgrid immediately after the discharge ends. For non-microgrid applications, this could be set to 0% (or the minimum allowed for the battery). It may be desirable to choose a discharge power so the expected ending SOC be somewhat higher than the minimum value (to add discharge margin), but that is optional. Example: for a microgrid, you might want to keep the resting SOC at 60%, as a tradeoff between battery longevity and reserve capacity. For a dispatch you might want to charge it to 100%, and then discharge to no lower than 20%, to leave some reserve for black starting. So the calculated maximum discharge power could be based on extracting 80% of the energy, but the agreement with the utility might be only 70% to give some margin in case of charging problems, or to avoid penalties if the BESS fails to discharge the full time. So even though the
minimum SOC is set to 20%, the discharge is expected to go only to 30%, if it is able to start from 100%.
Attachment A
Certificate Of Completion
Envelope Id: 08FCF87A-41AD-4A3E-8592-5761803A4859 Status: Completed
Subject: WEG| Pitkin County Change Order 073.23 D for Review & Signature
Source Envelope:
Document Pages: 13 Signatures: 3 Envelope Originator:
Certificate Pages: 5 Initials: 1 Pitkin County Procurement
AutoNav: Enabled
EnvelopeId Stamping: Disabled
Time Zone: (UTC-07:00) Mountain Time (US & Canada)
530 East Main Street
Suite 203
Aspen, CO 81611
Procurement@PitkinCounty.com
IP Address: 2605:59c8:53a2:
Record Tracking
Status: Original
7/25/2025 12:36:53 PM
Holder: Pitkin County Procurement
Procurement@PitkinCounty.com
Location: DocuSign
Signer Events Signature Timestamp
Connie Baker
connie.baker@pitkincounty.com
Budget Director
Pitkin County
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 65.38.144.66
Sent: 7/25/2025 12:45:03 PM
Viewed: 7/25/2025 12:50:51 PM
Signed: 7/29/2025 11:41:20 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Michael Port
michael.port@pitkincounty.com
Climate Action Analyst
Pitkin County
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 65.38.144.66
Sent: 7/29/2025 11:41:23 AM
Viewed: 7/31/2025 8:59:55 AM
Signed: 7/31/2025 9:00:09 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Peter N. Barry
pbarry@weg.net
President
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 161.69.57.15
Sent: 7/31/2025 9:00:11 AM
Viewed: 7/31/2025 8:45:25 PM
Signed: 8/1/2025 3:02:24 PM
Electronic Record and Signature Disclosure:
Accepted: 7/31/2025 8:45:25 PM
ID: 26e0d653-5773-4f98-8cae-7d85f6ca66da
Company Name: Pitkin County, Colorado
Kara Silbernagel
kara.silbernagel@pitkincounty.com
Deputy County Manager
Pitkin County Colorado
Signing Group: County Manager Group
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 65.38.144.66
Sent: 8/1/2025 3:02:26 PM
Viewed: 8/5/2025 11:25:14 AM
Signed: 8/5/2025 11:25:41 AM
Electronic Record and Signature Disclosure:
Accepted: 6/26/2025 10:29:11 AM
ID: 13c88870-faf6-4375-8fed-1bd1d274f164
Company Name: Pitkin County, Colorado
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Pitkin County Procurement
procurement@pitkincounty.com
Procurement Specialist
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 8/5/2025 11:25:43 AM
Resent: 8/5/2025 11:25:50 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Accounts Payable
AP@pitkincounty.com
Accounts Payable
Pitkin County
Security Level: Email, Account Authentication
(None)
Sent: 8/5/2025 11:25:44 AM
Viewed: 8/5/2025 11:47:16 AM
Electronic Record and Signature Disclosure:
Not Offered via Docusign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 7/25/2025 12:45:03 PM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Envelope Updated Security Checked 7/29/2025 10:46:09 AM
Certified Delivered Security Checked 8/5/2025 11:25:14 AM
Signing Complete Security Checked 8/5/2025 11:25:41 AM
Completed Security Checked 8/5/2025 11:25:44 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Pitkin County (we, us or Pitkin County) may be required by law to provide
you with certain written notices or disclosures. Described below are the terms and conditions for
providing to you such notices and disclosures electronically when we send you documents for
electronic signature.
Acknowledging your Access, Intent, and Consent to Receive and Sign Materials
Electronically
To confirm that you can access this information electronically, which will be similar to other
electronic notices and disclosures that we will provide to you, please verify that you were able to
read this electronic disclosure and that you also were able to print on paper or electronically save
this page for your future reference and access or that you were able to e-mail this disclosure and
consent to an address where you will be able to print on paper or save it for your future reference
and access. Further, if you consent to receive notices and disclosures exclusively in electronic
format on the terms and conditions described above, please let us know by clicking the 'I agree'
button below.
By checking the 'I Agree' box, I confirm that:
I am establishing my intent to be bound to the transaction, and indicating that I am fully
aware of the purpose for which the signature is being provided.
I can access and read this Electronic CONSENT TO ELECTRONIC RECEIPT OF
ELECTRONIC RECORD AND SIGNATURE DISCLOSURES document; and
I can print on paper the disclosure or save or send the disclosure to a place where I can
print it, for future reference and access; and
Until or unless I notify Pitkin County as described above, I consent to receive from
exclusively through electronic means all notices, disclosures, authorizations,
acknowledgments, and other documents that are required to be provided or made
available to me by Pitkin County during the course of my relationship with you.
Signing Documents without a Pitkin County DocuSign Account:
Pitkin County may not require all document signers to be authorized users of the Pitkin County
DocuSign Account. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to these terms and
conditions, please confirm your agreement by clicking the 'I agree' button at the bottom of this
document. When you don't have a DocuSign account, you will be provided the opportunity to
agree to the Legal Disclosure each time you open an "envelope" for signing, at this time, you can
download and retain this disclosure. Pitkin County will forward completed documents that
you've reviewed, processed or signed via email. Should you require copies of these signed
documents (e.g., if they get deleted from your email account) you should request those
documents from Pitkin County under the Colorado Open Records Act by contacting the Pitkin
County custodian who sent you the document for signature.
Signing Documents with a Pitkin County DocuSign Account:
Electronic Record and Signature Disclosure created on: 3/20/2020 3:28:13 PM
Parties agreed to: Peter N. Barry, Kara Silbernagel
Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to these terms and conditions, please
confirm your agreement by clicking the 'I agree' button at the bottom of this document.
Getting paper or electronic copies
At any time, you may request from us a paper or electronic copy of any record provided or made
available electronically to you by us. For such copies, as long as you are an authorized user of
the DocuSign system you will have the ability to download and print any documents we send to
you through your DocuSign user account for a limited period of time (usually 30 days) after such
documents are first sent to you. After such time, if you wish for us to send you paper or
electronic copies of any such documents from our office to you, you may be charged a per-page
fee. You may request delivery of such paper or electronic copies from us by following the
procedure described below.
Withdrawing your consent
If you are an authorized DocuSign Account holder, you can decide to receive notices and
disclosures from us electronically, you may at any time change your mind and tell us that
thereafter you want to receive required notices and disclosures only in paper format. Described
below is the process for informing us of your decision to receive future notices and disclosure in
paper format and also how to withdraw your consent to receive notices and disclosures
electronically.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. To indicate to us that you are changing your mind, you must
withdraw your consent using the DocuSign 'Withdraw Consent' form on the signing page of your
DocuSign account. This will indicate to us that you have withdrawn your consent to receive
required notices and disclosures electronically from us and you will no longer be able to use your
DocuSign user account to receive required notices and consents electronically from us or to sign
electronically documents from us.
All notices and disclosures will be sent to you electronically
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through your DocuSign user account all required notices, disclosures,
authorizations, acknowledgments, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Pitkin County:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to Helpdesk@provelocity.com
To advise Pitkin County of your new e-mail address
To let us know of a change in your e-mail address where we should send notices and disclosures
electronically to you, you must send an email message to us at Helpdesk@provelocity.com and
in the body of such request you must state: your previous e-mail address, your new e-mail
address .
In addition, you must notify DocuSign, Inc to arrange for your new email address to be reflected
in your DocuSign account by following the process for changing e-mail in DocuSign.
To request paper or electronic copies from Pitkin County
To request delivery from us of paper or electronic copies of the notices and disclosures
previously provided by us to you electronically, you should request those documents from Pitkin
County under the Colorado Open Records Act by contacting the Pitkin County custodian who
sent you the document for signature.
To withdraw your consent with Pitkin County
To inform us that you no longer want to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your DocuSign account, and on the subsequent
page, select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an e-mail to Helpdesk@provelocity.com and in the body of such a request, you
must state your e-mail, full name, Postal Address, telephone number, and account
number.